This Solicitation opportunity from California was posted on February 21, 2024. The submission period has ended. Browse the details below for market research, or find similar active opportunities.
Building K Analyzer Lab Expansion Project
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
Active Opportunities Like This One
AI Contract Overview
The contract involves the construction and expansion of the Analyzer Laboratory at Building K within Santa Clara Valley Medical Center, located at 751 South Bascom Avenue, San Jose. Bids are to be submitted by March 7, 2024, in sealed form to the Clerk of the Board of Supervisors at the County Government Center. The project is divided into two phases, with the first phase focusing on installing or replacing body fluids analyzing equipment and remodeling adjacent spaces such as electrical and IDF rooms, followed by a second phase that must commence only after the completion of the first. The scope includes designing and obtaining necessary permits for fire sprinkler and alarm systems, seismic bracing, and other mechanical, electrical, and plumbing (MEP) work, all to be stamped by a licensed California engineer. Throughout construction, the contractor must ensure the protection of existing utilities and areas, submit infection control risk assessments, and maintain two continuous egress routes for safety. The project requires adherence to Santa Clara Valley Medical Center’s infection prevention protocols and involves careful coordination for utility shutdowns. A mandatory pre-bid conference is scheduled for February 28, 2024, at the project site. Bids must be received by the specified deadline and are available for review through the designated bidding platform.
General Info
Place of Performance
CA, USASet-Aside
Documents
0AI Contract Breakdown
Uniform Contract FormatNo documents to break down
The breakdown needs solicitation documents. None were found from this contract's source.
Timeline
Submission Closed
Organization & Contact Information
Full Description
Phase 1 will need to be done prior to phase 2 work. There may be a schedule gap in phase 1 and phase 2.
Design and Obtain HCAI-OSHPD required approval/permits for Fire sprinklers System, Fire Alarm System, Support and Seismic bracing for pipes, ducts, and conduits (MEP). Refer to G-002 for deferred approval submittals list. Drawings shall be designed and stamped by California licensed engineer.
Protect existing areas including utilities feeding adjacent areas and provide method of procedure (MOP) for any utility’s shutdown.
Submit Infection Control Risk Assessment (ICRA) Permit prior to any construction activities inside the building. Compliant with Santa Clara Valley Medical Center infection prevention manual.
Maintain two (2) continuously temporary egress during construction. A mandatory Pre-Bid Conference/site visit will be held on 2/28/2024, at 11:00 AM at 751 S Bascom Ave, San Jose, CA 95128, Main Lobby Building K. Attached PRE-BID CONFERENCE - Building K Analyzer for meeting location.
More opportunities from California → County of Santa Clara
Same awarding agency
Earlier notices in this NAICS code
Posted before this notice, open and closed
Find Active Opportunities Like This
Get AI-powered intelligence on the opportunities still open
Every page of the solicitation package shredded into a compliance breakdown
AI-powered matching based on your capabilities and past performance
Competitor and incumbent history on the requirement
Automated alerts on amendments, Q&A deadlines, and award
Join 750+ contractors already using CLEATUS