DOCK AND DECK PLATE REPAIR
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
AI Contract Overview
The Department of Veterans Affairs Network Contracting Office 6 has issued solicitation 36C24626Q0889 for dock and dock plate replacement and repair services at the Salem VA Medical Center in Virginia. This project, set aside for Service-Disabled Veteran-Owned Small Businesses under NAICS 238990, involves a construction magnitude between 25,000 and 100,000 dollars. The contractor is required to provide all labor, materials, and supervision to perform structural and concrete work at Buildings 14 and 15. Specific tasks for Building 14 include removing existing dock plates, sawcutting asphalt, installing a new retaining wall and curb, and pouring a new sloped concrete drive. For Building 15, the scope includes removing a pit leveler, infilling the pit with gravel, and installing a new hydraulic pit leveler and frame. All work must adhere to VA design and construction standards, local building codes, and OSHA safety requirements. The period of performance is 120 days from the issuance of the Notice to Proceed. The contractor must coordinate schedules with the VA Engineering Service, provide 48-hour notices for operational disruptions, and ensure all waste is disposed of per EPA regulations. Final acceptance is contingent upon inspection by the Contracting Officer's Representative. Labor for this project is subject to the Davis-Bacon wage determination VA20260172 for the counties of Botetourt, Craig, Franklin, and Roanoke.
General Info
Agency
NAICS
Place of Performance
Salem, VA, 24153, USASet-Aside
Timeline
Response Deadline
Organization & Contact Information
Full Description
Department of Veterans Affairs
Salem VA Medical Center
1970 Roanoke Blvd, Salem, VA 24153
Statement of Work (SOW)
Project Title: Dock and Dock Plate Replacement – Buildings 14 & 15
Facility: Salem VA Medical Center (VAMC)
Date: May 14, 2026
1. Scope of Work
The contractor shall furnish all labor, materials, equipment, and supervision required to remove and replace existing dock plates and perform associated concrete and structural work at Buildings 14 and 15, Salem VAMC. All work shall comply with VA standards, local building codes, and OSHA safety requirements.
2. Description of Work
Building 14
- Remove existing dock plate.
- Sawcut and remove approximately 14 ft × 50 ft of asphalt.
- Remove approximately 50 ft of existing curb.
- Excavate for new footing at existing dock wall to extend dock area.
- Form and pour new 4 ft × 1 ft × 14 ft retaining wall with 4×4 steel angle on edge.
- Form and pour new 6 in × 18 in × 50 ft curb.
- Form and pour new concrete drive (14 ft × 50 ft × 6 in), sloped to allow trucks to back up level with dock.
- Extend existing handrail by 2 ft.
- Install new 4 in × 10 in × 14 in rubber dock bumpers.
Building 15
- Remove existing pit leveler and associated equipment.
- Infill existing pit with #57 gravel.
- Sawcut back of pit at cantilever.
- Pour new 4 in concrete slab pinned to existing foundation.
- Install new 4 in × 4 in pit leveler frame and pour concrete perimeter.
- Install new 6 ft × 8 ft hydraulic pit leveler and 4 in × 10 in × 14 in dock bumpers.
3. Performance Standards
All work shall:
- Meet VA design and construction standards.
- Comply with Applicable Sections of the VA Electrical, Structural, and Safety Guidelines.
- Be executed following OSHA safety practices.
- Be completed per approved construction drawings and specifications.
- Ensure new concrete and metal installations are level, aligned, and finished to VA quality standards.
4. Schedule and Coordination
- Work schedule shall be coordinated with the VA Engineering Service prior to mobilization.
- Contractor shall provide a minimum 48-hour work notice for any activity affecting operations.
- Access to work areas shall be limited to authorized personnel only.
5. Safety and Environmental Requirements
- The contractor shall maintain a safe work environment at all times.
- All waste materials shall be removed and disposed of in accordance with EPA and local regulations.
- Contractor shall ensure dust control and minimal disruption to medical center operations.
6. Inspection and Acceptance
All work will be inspected by the VA contracting officer’s representative (COR).
Final acceptance will occur after successful inspection and demonstration of functionality of all installed components.
Period of Performance is 120 days from issuance of Notice to Proceed (NTP).