Equipment Mobilization and Transport

Active
State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

This subcontract for Equipment Mobilization and Transport involves the hauling of heavy pumping equipment and piping for prime contractors working on Orange County Sanitation District projects. The scope of work specifically requires the transport of five large pumping units and associated support equipment to the Sunflower Lift Station, utilizing heavy-duty flatbeds and cranes for the offloading process. To ensure site entry, the contractor must comply with CARB Clean Truck Check and Truck and Bus Regulation standards. All equipment must be delivered to the project site by November 1, 2026. This opportunity is managed by Plant 1 Maintenance in California under NAICS code 484220, with a response deadline of October 7, 2026.

General Info

Transport five pumping units to Sunflower Lift Station by November 1, 2026.

Agency

California → 870 - Plant 1 MaintenanceView Agency

NAICS

484220 - Specialized Freight (except Used Goods) Trucking, LocalView NAICS

Place of Performance

CA, USA

Set-Aside

NONE

Documents

This scope was carved out of S-2026-747BD.

The full solicitation package (4 documents), including the RFP, is on the prime solicitation, not on this scope.

View the prime solicitation

SUNFLOWER BYPASS PUMPING PLAN FOR WET SEASON 2026-2027

AI Contract Breakdown

Uniform Contract Format

No contract breakdown available.

Cannot generate Contract Breakdown because no documents were found from this contract's source.

Timeline

Posted

subcontract

Response Deadline

Submission deadline

Response Deadline

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia → 870 - Plant 1 Maintenance
ContactsNo contacts available
OfficeN/A
Organization / Agency
California → 870 - Plant 1 Maintenance
View Agency Profile
Office AddressN/A
ContactsNo contact information available

Full Description

Show more
Hauls heavy pumping equipment and piping for prime contractors on Orange County Sanitation District projects. Transports five large pumping units and support equipment to the Sunflower Lift Station using heavy-duty flatbeds and cranes for offloading. Must meet CARB Clean Truck Check and Truck & Bus Regulation standards for site entry. Delivers all required equipment to the project site by November 1, 2026.

Similar Contracts

Same NAICS industry code

More opportunities from California → 870 - Plant 1 Maintenance

Same awarding agency

NAICS: 532490
New
SLED
SUNFLOWER BYPASS PUMPING PLAN FOR WET SEASON 2026-2027
Solicitation # S-2026-747BD
The Orange County Sanitation District (OC San) is soliciting bids for the Sunflower Bypass Pumping Plan for the 2026-2027 wet weather season. This project is necessitated by reliability concerns with Sunflower Pump #1 and requires the procurement of a temporary 40-MGD bypass pumping system to provide redundancy for Sunflower Pump #2. The selected contractor will provide a turnkey service including the mobilization, installation, and operation of a system featuring at least five pumping units with variable frequency drives and SCADA integration. The system must be capable of continuously conveying flows between 10 MGD and 40 MGD, with a tentative performance period running from November 1, 2026, through April 15, 2027. Bids are due by 2:00 pm on October 7, 2026, and will be awarded based on a low-bid selection process. Qualified bidders must be licensed and registered with the California Department of Industrial Relations, adhere to prevailing wage requirements, and maintain a workers compensation experience modification rate of 1.25 or lower. The contract requires the submission of a site-specific safety plan and compliance with Cal/OSHA and OC San safety standards. Key milestones following the Notice to Proceed include the delivery of bypass submittals within 14 days, a review workshop within 21 days, and the completion of installation and testing within 28 days. Payment is based on a bid price form covering mobilization, installation, and rental rates.
Other Commercial and Industrial Machinery and Equipment Rental and Leasing

POSTED

about 15 hours ago

DEADLINE

in 21 days
View Details

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS