Former General Leonard Wood Army Community Hospital Demolition, Optical Fabrication Laboratory, with Site Improvements

Closed
W912DQ26RA073Federal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

Active Opportunities Like This One

NAICS: 238910
New
SLED
Demolition of Connex Box Structures and Removal of Debris
Solicitation # ACFD 26-03
The Alameda County Fire Department (ACFD) is soliciting sealed bids for solicitation number ACFD 26-03, focused on the demolition of Connex Box Structures and the removal of debris at 890 Lola Street in San Leandro, California. This is a stipulated sum, single-prime contract with a total project duration of 120 calendar days. Bids must be submitted by 2:00 pm on December 10, 2026, at 6363 Clark Ave., Dublin, California. The contract will be awarded to the lowest responsive and responsible bidder based on the base bid amount. Required submission documents include a bid bond or security of 10 percent of the total bid price, a non-collusion declaration, a debarment form, and a designated subcontractors list. The successful contractor must provide 100 percent performance and payment bonds and adhere to California Public Works Contract requirements, including the payment of prevailing wages. Key operational requirements include the submission of a site security and logistics plan addressing tool control and working around inmates, as well as strict adherence to soil dust mitigation and hazardous materials procedures. Project milestones range from the initial kick-off meeting and equipment delivery to final site clearance. The contractor is also required to comply with the Americans with Disability Act and Title VII of the Civil Rights Act of 1964. All work is subject to inspection and potential rejection by the ACFD and the Construction Manager to ensure conformity with technical specifications and industry standards.
AC Fire Department

POSTED

about 10 hours ago

DEADLINE

in about 1 month

AI Contract Overview

Show more

The U.S. Army Corps of Engineers, Kansas City District, is conducting market research for a Design-Bid-Build contract to demolish and decommission the Former General Leonard Wood Army Community Hospital, Optical Fabrication Laboratory, and Medical Warehouse Phase 2, along with implementing site improvements at Fort Leonard Wood, Missouri. The project encompasses the complete removal of multiple structures including the 472,600-square-foot hospital, Central Utility Plant, fuel tanks, temporary helipad, and associated utilities and infrastructure, with strict requirements for hazardous material abatement including asbestos, mercury, medical gases, refrigerants, and hazardous waste. Decommissioning procedures are extensive, covering medical gas systems, low-voltage networks, HVAC, wastewater lines, fire suppression systems, hydraulic elevators, and diesel fuel tank removal, with all debris and non-salvageable materials to be cleared and disposed of per regulations. The Optical Fabrication Laboratory will undergo targeted demolition of its west wall, removal of MEP equipment, capping of roof penetrations, and new construction of an ADA-compliant entrance vestibule and egress corridor, while ensuring operational continuity. Site improvements include grading, parking maintenance at 970 stalls, sidewalks, landscaping, lighting, wayfinding, and video surveillance, to be completed with minimal disruption to existing operations and through careful phasing and traffic management. The project has an estimated value between $35 million and $95 million, is classified under NAICS 238910 with a $19 million small business size standard, and is expected to be solicited in late 2026. Respondents must provide detailed information on their business size, certifications, qualifications, and past performance on comparable projects, with submissions due by July 30, 2026.

General Info

Demolition of Fort Leonard Wood hospital and lab, hazardous material removal, site prep, small business focus, responses due July 23, 2026.

NAICS

238910 - Site Preparation Contractors

Place of Performance

Former General Leonard Wood Army Community Hospital, Fort Leonard Wood, Missouri , MO, USA

Set-Aside

NONE

Documents

0

No documents available

Documents will appear here when they are available.

AI Contract Breakdown

Uniform Contract Format

No documents to break down

The breakdown needs solicitation documents. None were found from this contract's source.

Timeline

3 updates
PhaseClosed
Posted

Sources Sought

Notice updated

The notice description changed.

Notice updated

The notice description changed. The point of contact changed.

Notice updated

Response deadline changed from Jul 23, 2026 to Jul 30, 2026. The notice description changed.

Response Deadline

Deadline has passed

Submission Closed

Find active opportunities like this

Get full access to discover similar active contracts, track opportunities, and build proposals with AI assistance.

Organization & Contact Information

Show more
AgencyDepartment Of Defense → W071 Endist Kansas City
Contacts2 people available
OfficeKANSAS CITY, MO, 64106-2896, USA
Office AddressKANSAS CITY, MO, 64106-2896, USA

Full Description

Show more

Sources Sought Notice for the Combined Demolition and Decommissioning of the Former General Leonard Wood Army Community Hospital (FGLWACH), Optical Fabrication Laboratory and Medical Warehouse Phase 2, and Site Improvements for the Fort Leonard Wood Hospital Replacement.  This requirement was previously published on SAM.gov as the seed project for the Dismantling, Demolition, and Removal of Improvements Multiple Award Task Order Contract (MATOC) as well as the FGLWACH Demolition and Decommissioning Project.


The U.S. Army Corps of Engineers, Kansas City District intends to solicit and award a Design-BId-Build (DBB) contract for the demolition and decommissioning of the General Leonard Wood Army Community Hospital, Optical Fabrication Laboratory, and Site Improvements on Fort Leonard Wood, Missouri.


The demolition of the former General Leonard Wood Army Community Hospital (GLWACH) consists of the complete removal of the following buildings: hospital and clinic (B310), Central Utility Plant (B311), and temporary Helipad. The project shall include, but is not limited to, the abatement/removal of asbestos containing materials (ACM) and other regulated materials (ORM), disconnect and capping of utilities, diversion and/or disposal of all debris materials, and restoration of the site to a specified condition. Phase 2 of the Optical Fabrication Laboratory includes demolition of the west wall at the current mechanical, electrical, plumbing (MEP) room, removing all equipment inside the MEP and capping all roof penetrations. The site improvements include site grading, parking, sidewalks, landscape, site lighting, wayfinding, and video surveillance.


This Sources Sought notice is for market research and planning purposes only. This does not constitute a solicitation and shall not be construed as a commitment by the Government to award a contract from responses to this announcement, nor does it obligate the Government to produce a solicitation in the future. Any information submitted by interested parties is strictly voluntary and no monetary compensation will be provided for response preparation or follow-up requests.


The purpose of this Sources Sought Notice is to gain knowledge of potential and interested qualified contractors capable of performing hazardous material abatement, building demolition, decommissioning services, removal of improvements, construction, and site improvements.  


This effort is classified through the North American Industry Classification System (NAICS) under 238910 Site Preparation Contractors. The small business size standard for NAICS 238910 is $19M.


The magnitude of this project is between $35M and $95M.


It is anticipated that a solicitation announcement will be published on SAM.gov in late-2026.


The following information is requested in this Sources Sought (SS) announcement:


1. Firm’s name, address, email address, website address, telephone number, and point of contact.  


2. Firm’s CAGE Code and UEI number.


3. Company size (Small or Large), in accordance with the NAICS 238910.


4. If a Small Business, specify if your company is any of the following: Small Disadvantaged Business, Service-Disabled Veteran Owned Small Business (SDVOSB); Veteran Owned Small Business, HUBZone Small Business; 8(a) Small Business concern; or Women-Owned Small Business.


5. Firm’s interest in providing a proposal as the prime contractor on the pending solicitation once issued.


6. Experience: Evidence of capabilities to perform work comparable to that required for the project.


7. Provide a maximum of 3 recent (within the last 6 years) relevant/comparable projects and describe how they are similar to this project.  Include the project name; when the project was completed; dollar value of the project; description of the key/salient features of the project, identify the contracting office & the customer/user (include POC information).  Construction Bonding level per contract and aggregate construction bonding level, both expressed in dollars.


A summary of the scope is below:


  1. Abatement of hazardous materials and environmental liabilities within GLWACH and other facilities to be demolished
  2. Demolition of GLWACH (472,600sf) and Primary Care Clinic structures, including foundations.
  3. Demolition of Central Utility Plant
  4. Demolition of Fuel Tanks
  5. Demolition of utilities, paving and other site appurtenances, within the boundaries identified. 
  6. Demolition of communications infrastructure to various buildings that are currently served from GLWACH.
  7. Demolition of temporary Helipad. 
  8. Construction of new exterior wall between Regional Optical Fabrication Lab and GLWACH. 
  9. Construction of storm drainage and detention
  10. Backfill and establishment of turf following removal of building foundations.

Decommissioning Statement


The contractor shall remove all debris, and any other material not otherwise tagged for salvage or reuse on the project (examples are existing attic stock, old architectural drawings, spare parts & materials, files, etc.)


1. Decommission medical air, vacuum, and gas systems:


a. Disconnect master medical gas alarm


b. Disconnect zone medical gas alarms.


c. Remove medical gas manifolds


d. Remove medical air pumps


e. Remove medical vacuum pump and tank


f. Remove dental air pump


g. Remove dental vacuum pumps and tank


h. Purge and cap medical gas system throughout MTF. Cut and cap MED gas at main entry point, then purge lines at each valve and tag “NOT IN USE”


i. Remove spit tank, filter, and dispose of contaminant off post.


2. Decommission medical low-voltage systems:


a. Disable temperature monitoring system.


b. Deactivate and remove pharmacy duress visible components.


c. Deactivate and remove Infant Abduction System/HUGS systems and visible components.


d. Remove all information technology (IT) switches.


e. Deactivate and remove ceiling mounted Wi-Fi antennas and repeaters


f. Deactivate and remove ceiling and external mounted cameras.


3. Decommission HVAC systems:


a. Clean and cap laboratory & radiology vent hoods, dispose of filters, and remove hazardous signs.


b. Disconnect all HVAC lines for refrigerant systems.


c. Cut and cap chilled water (CHW) from central utility plant (CUP)


d. Drain and purge HVAC CHW and reheat hot water (RHW) in CUP


e. Drain and purge glycol from all HVAC systems.


4. Decommission wastewater systems and laboratory systems:


a. Survey drains and P-traps in Dental and Laboratory for mercury contamination; remove all sink P-traps and remediate.


b. Dental vacuum lines in dental clinic are contaminated for mercury, remove vacuum lines from dental clinic to storage tank.


5. Decommission Nutrition Care Division (NCD) and Sterile Processing Department (SPD):


a. Cut and cap steam lines.


6. Decommission/Deactivate Fire Suppression Systems:


a. Deactivate and secure range hood fire suppression systems in NCD kitchen.


b. Deactivate the Data Center FM200 suppression systems; remove and dispose of storage tanks.


c. Deactivate carbon dioxide extinguishing system in emergency generator room; remove and dispose of storage tanks.


d. Dispose of the left-over fire extinguishers.


7. Decommission Hydraulic Elevators (2):


a. Drain and purge hydraulic oil from elevators (2) from GLWACH.


b. Contractor shall dispose of oil off post.


8. Decommission Two Diesel Fuel Tank (approximately 10,000 Gallons) located next to CUP in an exterior closure.


a. Drain and purge diesel from tanks and lines going to generator and fire pump.


b. Contractor shall take possession of fuel.


Optical Fabrication Laboratory (OFL) and Medical Warehouse Phase 2


The work includes retaining operations of the existing Optical Fabrication Laboratory in support of the Defense Health Agency.


  1. Demolition of the west wall at the current mechanical, electrical, plumbing (MEP) room.
  2. Remove all equipment inside the MEP and capping all roof penetrations.
  3. Construct a new exterior wall as required by the OFL contract.
  4. A new American with Disabilities Act (ADA) compliant entrance vestibule will be provided on the west side of the building.
  5. OFL Space on the lower level will receive a new egress corridor.
  6. Lighting protection on the roof that ties into a new ground loop system.

Site Improvements


This project includes site grading, parking, sidewalks, landscape, site lighting, wayfinding, and video surveillance.


  1. Maintain 970 parking stalls at all times during construction.
  2. Ensure safe pedestrian access to new facilities at all times.
  3. Landscaping includes planting trees.
  4. Utilize existing and DBB installed storm water conveyance channels and infrastructure. Avoid additional storm water detention.
  5. Construction phasing and traffic management.

The responses must be specific to the qualifications listed above to show that the respondent is qualified and possesses the necessary skills, experience, and capabilities. If a response does not clearly demonstrate that the respondent meets the qualifications, possesses the necessary skills, experience, and capability the response will not be considered as confirmed capability for the purposes of market research.


Please send your Sources Sought responses via email to contact@example.gov  and contact@example.gov.  Submissions should be received by 10:00 a.m. Central Daylight Time (CDT), July 30, 2026

More opportunities from Department Of Defense → W071 Endist Kansas City

Same awarding agency

NAICS: 332312
New
Federal
Debris Boom Supply and Install at Harry S. Truman Lake Project
Solicitation # W912DQ26QA080
Solicitation W912DQ26QA080 is a full and open competition for the design, fabrication, delivery, and optional installation of a debris boom system at Harry S. Truman Dam near Warsaw, Missouri. The primary objective is to protect the dam's tainter gates from floating debris to maintain spillway operational capacity and provide a visual barrier for boaters. The required system is approximately 2,000 feet long and must be designed to withstand site-specific hydraulic, wind, and wave conditions, including a minimum safety factor of 2.0 and the impact of a 100-foot log. All metallic components and load-bearing materials must be USA-made with manufacturer certifications. The contract is structured with three base CLINs for the supply and delivery of the boom and anchors, and one option CLIN for installation. Delivery is expected within 240 to 300 days of award, with the installation option exercisable within 270 days. Technical constraints strictly prohibit any drilling into or under the earthen dam, and all lakebed anchors require review by the Kansas City District Dam Safety Manager. Award will be based on the most advantageous offer, evaluating price, relevant experience, and past performance. Quotes must be submitted in PDF format and include a completed SF 1449, pricing, and documented project experience.
Fabricated Structural Metal Manufacturing

POSTED

about 14 hours ago

DEADLINE

in 4 days
View Details
NAICS: 236220
New
Federal
Veterans Affairs St. Louis Health Care System (VASTLHCS) John Cochran (JC) Hospital in St. Louis, Missouri
Solicitation # W912DQ26RA060
The U.S. Army Corps of Engineers Kansas City District is soliciting proposals for an Integrated Design and Construction (IDaC) contract to modernize the Veterans Affairs St. Louis Health Care System John Cochran Hospital in St. Louis, Missouri. This large-scale project involves demolishing deficient buildings and constructing several new seismically compliant facilities, including a new inpatient bed tower, a clinical expansion, an engineering building, a central utility plant, a water tank, and three parking structures. The total construction cost limit for the requirement is 1.42 billion dollars. The project is being solicited as full and open and requires offerors to submit proposals subject to Project Labor Agreement requirements. The contract is structured with a Pre-Construction Services phase (CLIN 0001) with a performance period of 820 calendar days from the Notice to Proceed, followed by various construction options. Award will be made to a single responsible offeror using a best-value tradeoff process, where non-priced factors are significantly more important than price. To be eligible, offerors must achieve at least an acceptable rating for technical factors and small business participation. Required submissions include a proposal guarantee of 20 percent of the proposed price or 3 million dollars, whichever is less, and full payment and performance bonds upon award. Technical requirements mandate compliance with USACE EM 385-1-1 safety standards, LEED v5 building design, and FGI Hospital Guidelines. The scope includes complex deliverables such as a VA swing space and a phased turnover schedule for various medical zones. Offerors must provide a detailed staffing plan, including a Site Safety and Health Officer and a QC Manager, and must utilize a third-party vendor for cybersecurity assessments. Proposals must be submitted electronically in PDF format by November 25, 2026, adhering to strict page limits and formatting guidelines.
Commercial and Institutional Building Construction

POSTED

7 days ago

DEADLINE

in 27 days
View Details
NAICS: 237110
Federal
Atchison Storm Sewer Separation Improvements, Atchison, Kansas
Solicitation # W912DQ27BA002
The U.S. Army Corps of Engineers, Kansas City District, is soliciting bids for the Atchison Storm Sewer Separation Improvements project in Atchison, Kansas. This small business set-aside construction project, with an estimated value between 1 million and 5 million dollars, involves the separation of storm and sanitary sewers. The scope of work includes the installation of reinforced concrete pipe, reinforced concrete box culverts, and storm water inlets and junction boxes, as well as the removal of existing sewer structures. The contractor is responsible for providing all necessary labor, equipment, and supervision, including incidental grading and the restoration of parkways, driveways, sidewalks, and pavement to a condition equal to or better than the original state. The solicitation is issued as a sealed bid under NAICS code 237110, with a response deadline of November 13, 2026. The project is divided into two primary components: the 16th Street Alignment and an optional 15th Street Alignment. Key requirements include adherence to the City of Atchison Public Works Specifications, compliance with the Davis-Bacon Act, and the submission of a project schedule within 42 days of the notice to proceed. Contractors must provide performance and payment bonds and participate in a partnering session within 45 days of the award. Quality assurance involves inspections of precast concrete units upon delivery and mandatory approval of saddle installations by the Contracting Officer's Representative prior to backfilling.
Water and Sewer Line and Related Structures Construction

POSTED

10 days ago

DEADLINE

in 15 days
View Details
NAICS: 562910
Federal
SB ERS MATOC, USACE Northwestern Division and EPA Region 2
Solicitation # W912DQ26RA109
The U.S. Army Corps of Engineers, Kansas City District, is establishing a Multiple Award Task Order Contract (MATOC) for Environmental Remediation Services (ERS) to support the USACE Northwestern Division and EPA Region 2. This total small business set-aside under NAICS 562910 has a maximum value of 245 million dollars, with a minimum guarantee of 2,500 dollars per contract. The period of performance runs from June 4, 2027, to June 3, 2032, with a six-month extension option available through December 3, 2032. The scope of work is extensive, covering in-situ thermal and chemical remediation, operations and maintenance of groundwater treatment and soil vapor extraction systems, field investigations, remedial design, risk assessments, and support for abandoned mines programs. Task orders will be executed as either Firm Fixed Price or Cost Plus Fixed Fee. This is a competitive, best-value acquisition utilizing the Highest Technically Rated Offeror with Reasonable Price methodology. Proposals are evaluated based on corporate experience and past performance, with awards granted to the highest technically rated offerors whose pricing is determined to be fair and reasonable; no price-technical tradeoffs will be performed. Offerors must submit two separate electronic PDF volumes via the PIEE Solicitation Module. Contract administration requires the use of the Wide Area WorkFlow system for invoicing and adherence to strict quality standards, including the preparation of Contractor Quality Control Plans and Quality Assurance Project Plans for each task order.
Remediation Services

POSTED

21 days ago

DEADLINE

in 18 days
View Details

Earlier notices in this NAICS code

Posted before this notice, open and closed

Find Active Opportunities Like This

Get AI-powered intelligence on the opportunities still open

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS