GSU Transformer Supply, Oahe Dam, SD & Ft Peck Dam, MT
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
AI Contract Overview
This contract, managed by the Department of Defense through the Endist Omaha office, involves the supply of generator step-up transformers for the Fort Peck Dam in Montana and the Oahe Dam in South Dakota. The scope of work includes the design and manufacturing of two transformers for Fort Peck and ten transformers for Oahe, along with all necessary ancillary and control components. The contractor is responsible for conducting Factory Acceptance Testing, delivery, offloading, reassembly, oil processing, and filling at both locations. The project further requires the movement of the units to their final operating locations and the performance of final acceptance testing and commissioning once interconnection is completed by a separate installation contractor. This award is designated as a Total Small Business Set-Aside under NAICS code 335311. Performance will take place primarily in Fort Pierre, South Dakota, and at the Fort Peck Dam site.
General Info
Contract Value
$56,977,893.5Place of Performance
Fort Pierre, SD, 57532, USASet-Aside
Awardee
PAF ELECTRICAL, INC.Award Issued Date
Documents
0AI Contract Breakdown
Uniform Contract FormatNo documents to break down
The breakdown needs solicitation documents. None were found from this contract's source.
Timeline
Organization & Contact Information
Full Description
Project Description: Ft Peck Supply of the generator step-up (GSU) transformers 4 and 5 located in switchyard #2 at the Fort Peck Dam. The final suppy contract for the Fort Peck transformers will include:
* Design and manufacturing of two new GSU transformers.
* Design and manufacturing of ancillary and control components.
* Performance of Factory Acceptance Testing (FAT).
* Delivery to the Fort Peck power plant, offloading at the transformer temporary storage and staging location, transformer reassembly, oil processing and filling, and movement to final operating location as the location is made available by the separate installation contractor.
* Final acceptance testing and commissioning of transformer after interconnection to the power plant is performed by the separate installation contractor.
Oahe Supply of all GSU transformers locatd at Oahe Dam. The supply contract for the Oahe transformers will include:
* Design and manufacturing of 10 new GSU transformers.
* Design and manufacturing of ancillary and control components.
* Performance of Factory Acceptance Testing (FAT).
* Delivery to the Oahe Dam power plant, offloading at the transformer temporary storage and staging location, transformer reassembly, oil processing and filling, and movement to final operating location as the location is made available by the separate installation contractor.
*Final acceptance testing and commissioning of transformer after interconnection to the power plant is performed by the separate installation contractor.
Similar Contracts
Same NAICS industry code
More opportunities from Department Of Defense → W071 Endist Omaha
Same awarding agency
Ready to Pursue This Opportunity?
Get AI-powered intelligence on this solicitation and the ones like it
Every page of the solicitation package shredded into a compliance breakdown
AI-powered matching based on your capabilities and past performance
Competitor and incumbent history on the requirement
Automated alerts on amendments, Q&A deadlines, and award
Join 750+ contractors already using CLEATUS