J041--SUBJECT* Steam, Plumbing and HVAC Service Contract Bedford VA Medical Center
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
Active Opportunities Like This One
AI Contract Overview
The Bedford VA Medical Center is soliciting quotes for a service-disabled veteran-owned small business set-aside contract to provide comprehensive maintenance, repair, and emergency services for HVAC, steam, and plumbing systems at its Bedford and Lowell, Massachusetts facilities. This contract, with a base year plus four option years, covers preventative maintenance tasks including semi-annual backflow testing, annual boiler inspections and repairs, emergency steam and plumbing repairs with rapid response requirements, duct cleaning for Building 7 during the base year, and specific HVAC repairs across multiple buildings on the medical center campus. Contractors must be licensed and certified in Massachusetts, adhere to all applicable safety and environmental regulations, supply all labor, materials, and equipment, and coordinate all work with the Contracting Officer Representative. The procurement follows FAR streamlined procedures for commercial services and incorporates numerous federal acquisition clauses, ensuring compliance with labor standards, safety, and Buy American requirements. Offerors must submit price schedules, past performance references on similar work, and technical qualifications demonstrating experience and capability to meet the outlined scope. Quotes will be evaluated based on price, past performance, and technical approach with emphasis on timely and efficient service delivery. A site visit is scheduled prior to proposal submission, and all responses must be submitted electronically by the February 20, 2026 deadline. The contract aims to support the VA Medical Center’s operational integrity by ensuring reliable maintenance and emergency response for critical steam, HVAC, and plumbing infrastructure.
General Info
Place of Performance
Bedford VA Medical Center 200 Springs Road, Lowell, MA 01852, MESet-Aside
Timeline
Submission Closed
Organization & Contact Information
Full Description
HVAC and Steam Repairs and Maintenance RFIs Solicitation No.: 36C24126Q0141
1. HVAC SOW Item 4 Duct Cleaning For CLIN 0002, please define the extent of duct cleaning in Building 7: system list (HV/HVAC/EF), areas served, access constraints, and any required after-hours phasing. SOW defines method and reporting but not quantities. Answer: Ducts identified in attached drawing for Bldg #7 identify ducts to be cleaned and inspected Per Scope of Work Attachments Bldg. 7-Attic Heating and Ventilation Color (11469) Bldg 7-Attic Heating and Ventilation (11468) Bldg. 7-F2 Heating and Ventilation (11467) Bldg 7-F2 Heating and Ventilation (11466) Bldg. 7-F1 Heating and Ventilation (11464) Bldg. 7-F1 Heating and Ventilation (11465) Bldg. 7-FB Ventilation (11463) Bldg. 7-FB Ventilation (11462) Work can be performed during normal working hours. After-hour work requires prior approval.
2 HVAC SOW Item 4 Duct Cleaning Confirm whether CLIN 0002 requires restoration only of duct insulation disturbed by access (panels/cuts), or whether it includes replacement of existing/deteriorated duct insulation beyond disturbed areas. Answer: Contractor responsible for means & methods. Damaged caused by work activities shall be restorated to in-kind condition. 3 HVAC Bldg 7 Drawings (added attachments) Bldg 7 drawings indicate 1" thermal duct insulation and 1/2" sound insulation (per plan note). Please confirm what sound insulation means: exterior acoustic wrap vs internal liner vs specified manufacturer system; provide jacket/facing requirements and limits. Answer: Bldg. #7 Drawing identify Duct to be cleaned. The specification or nomenclature designation is not available for the 1960 drawings. No insulation is being replaced for duct cleaning unless removed or damaged by the contractor. 4. HVAC SOW Item 5 Bldg 61 Insulation For CLIN 0011 (Bldg 61 piping insulation), SOW states Furnish and install insulation on piping refer to attached photos . Please provide insulation spec: type, thickness, jacket (PVC/aluminum/ASJ), vapor barrier requirements, and whether valves/fittings require removable covers. Answer: SECTION 22 07 11 PLUMBING INSULATION
5. HVAC SOW Item 5 Bldg 78 Pumps For CLIN 0012, please provide existing circulation pump data: make/model, HP, voltage/phase, flange size, and duty point (GPM/TDH). SOW calls for direct replacement and references picture 78 pump . Answer: Refer to Bldg #78 Pump Pictures 6. HVAC SOW Item 5 Bldg 78 Pumps For CLIN 0012, confirm whether contractor is responsible for system drain/refill, glycol/chemical treatment, and startup/functional testing, and identify allowable shutdown windows. Answer: Pumps can be isolated via valves. Any refilling can be done via the make up water system. Pumps shall be aligned and balanced. 7. HVAC SOW Item 5 Bldg 78 Pumps SOW states pipe reconfigurations are contractor responsibility and contractor must reinsulate disturbed insulation. Please clarify whether VA anticipates minor fit-up only, or significant reroute/valves/strainers/support modifications. Answer: VA expects a direct replacement; disturbed insulation can be reused unless damaged & damaged insulation needs to be replaced. 8. HVAC SOW Item 5 Bldg 78 Insulation For CLIN 0014 (Bldg 78 piping insulation), SOW states Furnish and install insulation on piping refer to attached photos . Please provide insulation spec (type/thickness/jacket/vapor barrier) and whether fittings/valves require covers. Answer: SECTION 22 07 11 PLUMBING INSULATION
9. Safety Insulation work (Bldg 61/78) Please confirm whether any existing pipe/duct insulation in the affected areas is known or presumed ACM and whether VA will provide abatement/testing if encountered. Answer: If ACM is suspected, contractor will notify VA for sampling and testing. 10. HVAC Bldg 80 Chapel Controls For CLINs 0003 0008, SOW is detailed but does not state whether work is DDC conversion and BAS integration. Please confirm required control platform, BAS manufacturer, required points list/sequence, and acceptance/commissioning requirements. Answer: DDC Conversion 11. HVAC Emergency Services / Parts Allowance SOW states contractor shall carry an allowance for emergency repair parts $XX.XX , while price schedule lists Emergency Parts/Materials as N/A. Please clarify how the Government intends offerors to handle parts/materials for emergency work. Answer: per item #3 Contractor shall carry an allowance for parts for emergency repairs at a rate of $30,000.
12. HVAC Louvers (Bldg 7/61/78) For louver replacement CLINs (0001, 0009 0010, 0013), please provide sizes, material/finish, and confirm whether replacement is full assembly (frame/screens) or components only; confirm if structural/masonry modifications are expected. Answer: INKind replacement. Can be field measured. 13. Base Year Duct Cleaning: Are there existing access panels for duct cleaning and is the work to be completed during regular working hours? Answer: Refer to Drawing for any access locations. Work can be performed during normal working hours 14. Can you please provide Mechanical/Electrical drawings for Building 61, 78, & 80 Answer: Up to date as-builts do not exist. VA documents available for viewing in Bldg. #80. 15. Can you please provide pictures of HV-1 & HV-2 in Building 80 above bathroom
Answer: refer to photos for Chapel 16. Can you please provide louvre sizes for Building 78 clothing room Answer: The clothing room HV intake louvre/damper assembly is approximately 4 high by 10 wide 17. Are there any available pictures for any of the 11 boilers at the crescent house? Answer:No, However a site visit can be scheduled via the contractor officer 18. For the Building 78 circulation pumps, please confirm that pumps to be replaced are the 2 on the far left end in the provided picture Answer: Two pumps on right are being replaced. All pumps are that same. 19. Is the pneumatic controls replacement limited to devices associated with the unit only? Answer:Yes 20. Are the other necessary pneumatic components currently functioning and existing to remain? Answer:No 21. Any duct work plans for building 7 if possible please. Answer: Ducts identified in attached drawing for Bldg #7 identify ducts to be cleaned and inspected Per Scope of Work Attachments Bldg. 7-Attic Heating and Ventilation Color (11469) Bldg 7-Attic Heating and Ventilation (11468) Bldg. 7-F2 Heating and Ventilation (11467) Bldg 7-F2 Heating and Ventilation (11466) Bldg. 7-F1 Heating and Ventilation (11464) Bldg. 7-F1 Heating and Ventilation (11465) Bldg. 7-FB Ventilation (11463) Bldg. 7-FB Ventilation (11462)
22. Any information on the backflow preventer scope- model numbers or pictures of the backflow preventers would be helpful. Answer: Refer to backflow inventory attachment for model, SN, and location.
More opportunities from Department Of Veterans Affairs → 241-NETWORK Contract Office 01 (36C241)
Same awarding agency
Find Active Opportunities Like This
Get AI-powered intelligence on the opportunities still open
Every page of the solicitation package shredded into a compliance breakdown
AI-powered matching based on your capabilities and past performance
Competitor and incumbent history on the requirement
Automated alerts on amendments, Q&A deadlines, and award
Join 750+ contractors already using CLEATUS