Manufacture and Supply of Thrust Bearing Oil Coolers

Closed
Federal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

Active Opportunities Like This One

AI Contract Overview

Show more

This subcontract involves the design, manufacture, and delivery of two thrust bearing oil coolers for prime contractors working on projects at the Fort Peck Power Plant in Montana. The fabrication process requires specific materials, including C70600 Copper-Nickel for tubes and tube sheets, S.S 304 for supports, and C46400 Aluminum Bronze for covers. The contractor is responsible for performing hydrostatic testing and developing detailed design calculations for pressure drop and surface area. The opportunity is a total small business set-aside under the Department of Defense, specifically through the W071 Endist Omaha agency. To be eligible, the provider must possess at least five years of experience in oil cooler assembly. All completed units must be delivered to the project site in Fort Peck, MT.

General Info

Small business subcontract for two thrust bearing oil coolers for Fort Peck, Montana.

NAICS

332999 - All Other Miscellaneous Fabricated Metal Product Manufacturing

Place of Performance

NE, 59223

Set-Aside

SBA

Documents

This scope was carved out of W9128F26QA075.

The full solicitation package (10 documents), including the RFP, is on the prime solicitation, not on this scope.

View the prime solicitation

FP Thrust Bearing and Air Cooler Supply Purchase

AI Contract Breakdown

Uniform Contract Format

No documents to break down

The breakdown needs solicitation documents. None were found from this contract's source.

Timeline

PhaseClosed
Posted

subcontract

Response Deadline

Deadline has passed

Submission Closed

Find active opportunities like this

Get full access to discover similar active contracts, track opportunities, and build proposals with AI assistance.

Organization & Contact Information

Show more
AgencyDepartment Of Defense → W071 Endist Omaha
ContactsNo contacts available
OfficeN/A
Office AddressN/A
ContactsNo contact information available

Full Description

Show more
Designs, manufactures, and delivers two thrust bearing oil coolers for prime contractors on Fort Peck Power Plant projects. Fabricates units using C70600 Copper-Nickel for tubes and tube sheets, S.S 304 for supports, and C46400 Aluminum Bronze for covers. Performs hydrostatic testing and develops design calculations for surface area and pressure drop. Requires 5 years of experience in oil cooler assembly. Delivers completed coolers to Fort Peck, MT.

More opportunities from Department Of Defense → W071 Endist Omaha

Same awarding agency

NAICS: 236220
New
Federal
High Temp Hot Water Distribution System and Heat Plant Suite of Repairs to the US Air Force Academy COLORADO
Solicitation # W9128F27SM003
The U.S. Army Corps of Engineers is conducting market research via a Sources Sought Notice for a suite of repairs to the High-Temperature Hot Water (HTHW) Distribution System and Heat Plant at the United States Air Force Academy in Colorado Springs, Colorado. The project scope includes the safe abatement and replacement of asbestos-containing insulation on HTHW piping within Cadet Area Utility Tunnels, structural repairs to corroded pipe supports, and a complete overhaul of failing tunnel subdrainage and pump discharge networks. The government is evaluating a Multiple Award Design-Build model utilizing Other Transaction Agreements, with an anticipated performance period of three to five years and funding through annual Organizational and Maintenance (O&M) accounts. The government is seeking firms with proven experience in managing complex, phased mechanical construction within operational facilities and licensed expertise in high-temperature, confined-space asbestos abatement. Interested parties must demonstrate a bonding capacity of up to 45 million dollars for a single project and 95 million dollars in aggregate. Responses must be submitted as a capability narrative not exceeding five pages, including company profiles, entity identifiers, bonding thresholds, and representative project examples, by December 14, 2026. This notice is for market intelligence purposes and does not constitute a formal request for proposal or invitation for bids.
Commercial and Institutional Building Construction

POSTED

about 23 hours ago

DEADLINE

in about 1 month
View Details
NAICS: 237990
New
Federal
LOWER BRULE NORTH SHORELINE STABILIZATION AND ECOSYSTEM RESTORATION, ELEMENT 2
Solicitation # W9128F27BA007
Solicitation W9128F27BA007 is a firm-fixed-price construction project for the Lower Brule North Shoreline Stabilization and Ecosystem Restoration, Element 2, located along the bank of Lake Sharpe near Lower Brule, South Dakota. Managed by the U.S. Army Engineer District, Omaha, this 100% Small Business Set-Aside under NAICS 237990 has an estimated construction value between $10 million and $25 million. The scope of work focuses on erosion control and habitat creation, including the construction of a 200-by-1,500-foot island in shallow water, the installation of a 100-foot-wide riparian planting bench, a riprap revetment for shoreline protection, and a gravel maintenance path. These efforts are designed to develop approximately 5.17 acres of emergent wetland and 32 acres of riparian habitat through extensive earth moving, grading, and rock installation. The project has a performance period of 550 days, with an estimated start date of January 1, 2027, and requires work to commence within 10 calendar days of the notice to proceed. Bids are evaluated based on price and price-related factors and must be submitted via the PIEE Solicitation Module. Key technical requirements include adherence to the Davis-Bacon Act, Buy American statutes, and specific quality standards for concrete and stone protection. The bid schedule consists of 11 line items covering mobilization, breakwater structures, riprap, excavation, and topsoil placement, with a specific note regarding a 4.5% Tribal Employment Rights Ordinance tax. Inspection and acceptance will occur at the destination, specifically the COE Big Bend Project Office in Fort Thompson, South Dakota.
Other Heavy and Civil Engineering Construction

POSTED

about 23 hours ago

DEADLINE

in 20 days
View Details

Find Active Opportunities Like This

Get AI-powered intelligence on the opportunities still open

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS