Request for Information/Market Intelligence Notice: Multiple Projects at Vandenberg Space Force Base - Use of Progressive Design Build (PDB) with Other Transaction Authority (OTA)

Active
VSFB-FY27-PDBOTAFederal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The 30th Contracting Squadron is conducting market research to evaluate the feasibility of using Progressive Design-Build (PDB) via Other Transaction (OT) Agreements for several infrastructure projects planned for Fiscal Year 2027 at Vandenberg Space Force Base. The potential scope of work includes HVAC repairs, secure facility renovations, medium-to-high voltage electrical distribution replacement, airfield infrastructure repairs, outdoor fitness track restoration, road construction, and the replacement of fire alarms and freight elevators. This is a voluntary Request for Information (RFI) and not a formal solicitation. The government is seeking detailed feedback from industry partners regarding their company profiles, experience with OTA and PDB delivery methods, bonding capabilities, and recommendations on acquisition strategies. Interested firms must submit their responses by October 20, 2026, to help shape the final procurement approach.

General Info

RFI for FY2027 infrastructure projects at Vandenberg SFB using Progressive Design-Build OTA.

NAICS

236220 - Commercial and Institutional Building Construction

Place of Performance

Lompoc, CA, 93437, USA

Set-Aside

NONE

Documents

0

No documents available

Documents will appear here when they are available.

AI Contract Breakdown

Uniform Contract Format

No documents to break down

The breakdown needs solicitation documents. None were found from this contract's source.

Timeline

PhaseSources Sought
Posted

Sources Sought

Response Deadline

Submission deadline

Response Deadline

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyDepartment Of Defense → FA4610 30 Cons Pk
Contacts2 people available
OfficeVANDENBERG SFB, CA, 93437-5212, USA
Office AddressVANDENBERG SFB, CA, 93437-5212, USA
Contacts
Jeffrey Grelck
Alyson Kolding

Full Description

Show more

REQUEST FOR INFORMATION (RFI) / MARKET RESEARCH NOTICE: This is a request for information (RFI) for market intelligence and for informational purposes only. This announcement does not constitute a solicitation or a request for proposal (RFP), and no solicitation is currently available. Participation in this RFI is strictly voluntary. The Government will not be obligated to award any agreement or contract because of this RFI, nor will it reimburse respondents for any costs associated with the preparation or submission of information. Submitting a response will not affect a firm’s ability to submit a proposal should a formal solicitation be issued in the future.

NAICS CODE:
236220 Commercial and Institutional Building Construction
237130 Power and Communication Line and Related Structures Construction

SMALL BUSINESS STANDARD: $45,000,000.00

NOTE: While Other Transaction Authority is not subject to FAR based small business regulations, these NAICS codes are provided for market research to help the Government understand the size and demographics of the interested industrial base.

PROGRAM/PROJECT OVERVIEW: The 30th Contracting Squadron has multiple infrastructure repair and construction projects planned in Fiscal Year 2027 including heating, ventilation and air conditioning (HVAC) repair, secure facility renovation, medium-high voltage electrical distribution line repair/replacement, airfield lighting repair, fitness track repair/replacement, and road repair/construction, fire alarm and elevator repair/replacement. The Government is evaluating the feasibility of executing these requirements via Progressive Design-Build (PDB) utilizing an Other Transaction (OT) Agreement under the statutory authority of 10 U.S.C. § 2808a in conjunction with the United States Space Force (USSF) Construction Commercial Solutions Opening (CSO) at https://sam.gov/workspace/contract/opp/68c3d9f987984f448cd067abaf2950d0/view.

Summaries of potential projects being considered for this acquisition strategy are as follows:


  1. HVAC Repair: Design and construct the repair and replacement of the HVAC for a multi-tenant office building.
  2. Secure Facility Renovation: Design and construction of renovations of a secure facility to meet revised mission requirements Renovation is expected to include wall relocation, electrical, communications, HVAC, and associated finished associated with a facility renovation.
  3. Medium-High Voltage Electrical Distribution: Design and construction of the replacement of an aged electrical distribution system ranging from 15kV to 70kV.
  4. Airfield Repair: Investigate, design, and construct repairs to various airfield infrastructure to bring it up to current FAA and military airfield code and standards.
  5. Outdoor Fitness Track Repair/Replacement: Design and construct repairs to stabilize the soil conditions and repair failing rubberized track surface.
  6. Road Repair/Construction: Design and construct road repairs to stabilize subsurface conditions and improve roadways to meet increasing haul capacity and traffic.
  7. Fire Suppression and Elevator Repair/Replacement: Design and construct the replacement of a freight elevator for personnel and freight access and the replacement of the existing fire alarm system to include connectivity with the new elevator.


INFORMATION REQUESTED: Interested industry partners are requested to respond to the following questions to help shape the final acquisition strategy:

Company Profile:
Q1. Business Name
Q2. Address
Q3. Point of Contract (Name, Title)
Q4. Phone Number
Q5. Email Address
Q6. Unique Entity ID
Q7. Cage Code
Q8. Socioeconomic Status (Other Than Small, Small, 8(a), SDVOSB, etc.)
Q9. Participating Role (Prime Contractor, Subcontractor, Design Firm, Other)
Q10: Which of the seven (7) projects your company may be interested in responding to if the projects are issued as PDB OT Agreements.

Other Transaction Authority (OTA) & Statutory Compliance:
Q11. OTA Experience – Describe your firm’s previous experience, if any, executing projects utilizing OTA. Please select from one of the following:


  • No experience
  • Limited Experience (1 – 5 projects completed)
  • Very Experienced (5+ projects completed)

Q12. What project characteristics make PDB OTA particularly advantageous or disadvantageous for these requirements

Progressive Design-Build (PDB) / Early Contractor Involvement:
Q13. What minimum level of detail (e.g., Statement of Need, conceptual site plans, target budget) does your firm require prior to submitting a White Paper (Executive Summary, Outline of proposed construction method, estimated schedule, Rough Order of Magnitude (ROM) price)?
Q14. What minimum level of detail (e.g., Statement of Need, conceptual site plans, target budget) does your firm require prior to a Phase 1 award (Design/Pre-construction) to feel confident in the project's viability?
Q15.  What collaborative mechanisms (such as joint design charrettes, target-value design workshops, or phased scoping approvals) do you recommend the Government implement in the first 30-90 days to rapidly transition from a "blank page" to a mutually agreed-upon baseline?
Q16. Describe your experience executing Progressive Design-Build, Construction Manager at Risk (CMAR), or other highly collaborative delivery methods where designer and builder worked collaboratively with the owner before locking in a Guaranteed Maximum Price (GMP).
Q17. Which of the following levels of designs would be the lowest level at which you would feel confident negotiating a GMP?


  • Charrette (basic concept, floor plans, little to no engineering review completed)
  • 35% Design (charrette documentation plus design narrative completed, list of projected codes, UFCs, and disciplines, initial site visit completed by engineering team)
  • 65% Design (35% design documentation plus design analysis including investigation report, explanation of major design decisions, list of specifications, engineering data, environmental surveys)
  • 95% Design (65% design brought to 100% design level except for administrative corrections and engineering stamps)
  • 100% Design (100% complete signed and stamped drawings issued for construction)


Feedback on the Acquisition Strategy & Alternatives:
Q18. Does the proposed PDB-OTA strategy incentivize your firm to participate? Why or why not?
Q19. Are there alternative acquisition strategies, commercial phasing arrangements, or risk-sharing terms that the Government has not considered that would yield a higher quality facility, faster delivery, or lower cost?

Bonding Capability:
Q20. Specify your maximum bonding (single and aggregate) as a sole prime contractor and/or as a joint venture.

SUBMISSION INSTRUCTIONS: Please submit your responses by 20 October 2026 at 2:00 PM Pacific Daylight Time (PDT) to Jeffrey Grelck at jeffrey.grelck@spaceforce.mil and Alyson Kolding at alyson.kolding@spaceforce.mil

The Government welcomes candid industry feedback and recommendations regarding commercial practices, agreement terms, project phasing, risk sharing, governance, pricing approaches, and other considerations that could improve successful execution of these projects under 10 U.S.C. § 2808a. Upon completion of industry feedback and market intelligence the Government may or may issue a USSF CSO Area of Interest for one, some, all, or none of the projects.

Interested firms are encouraged to add themselves to the Interested Vendors List associated with this announcement on SAM.gov to receive future updates on thie RFI, however, any subsequent opportunties will be posted separately and not linked to this notice.

Note: Do not submit proprietary trade secrets, protected technologies, or classified information in your response. All feedback received will be handled as public market research to shape the Government's final acquisition approach.

Similar Contracts

Same NAICS industry code

NAICS: 236220
New
SLED
JBLM Construct CHP Building
Solicitation # W912K3-26-R-A0001
Solicitation W912K3-26-R-A0001 is a Small Business Set-Aside for the design-bid-build construction of a 20,000 square foot Pre-Engineered Steel Controlled Humidity Preservation (CHP) Building at Joint Base Lewis McChord, Washington. The project scope includes site preparation, stormwater mitigation via an infiltration pond, the purchase and erection of the steel building, installation of a concrete slab, underground utilities, and a dry pipe fire suppression system. Additionally, the facility will feature specialized dehumidifying equipment and a solar-ready roof zone. The project is estimated between 1 million and 5 million dollars, with a statutory cost limit of 5 million dollars. The contract is a Firm Fixed Price task order to be awarded based on a balanced evaluation of technical capability and price. Technical evaluations will focus on the proposed project schedule, which must show completion within 360 days of the Notice to Proceed, and the qualifications of key personnel. Performance is required to begin within 10 calendar days of the Notice to Proceed, with a total completion deadline of 365 calendar days. The contractor must adhere to strict quality standards, including ISO 9001 and various ASTM and NFPA codes, and comply with Davis-Bacon prevailing wage rates for Pierce County. Administrative requirements include the submission of all invoices via Wide Area Workflow (WAWF) and the provision of performance and payment bonds for awards exceeding 150,000 dollars. Bidders must provide a bid guarantee of 20 percent of the bid price or 3 million dollars, whichever is less. Liquidated damages are established at 576.63 dollars for the first day and 427.99 dollars per day thereafter. All offers are due by 12:00pm PST on October 18, 2026.
Bristol Alliance of Companies

POSTED

about 1 hour ago

DEADLINE

in 6 days
View Details
NAICS: 236220
New
South Concourse Evolution (SCE) Bid Package 3
Solicitation # south-concourse-evolution-sce-bid-package-3
Hensel Phelps, acting as the General Contractor and Construction Manager for the Port of Seattle, is soliciting bids for Bid Package 3 of the South Concourse Evolution project at the Seattle-Tacoma International Airport. This solicitation is set aside for SAM.gov designated Small Disadvantaged Businesses under NAICS code 236220. The scope of work is divided into multiple subsystems, including Phase 1 glass and aluminum systems, vertical transportation for Phase 1 and select Phase 2 areas, and the demolition and installation of passenger loading bridges. Additionally, the package covers various requirements for main electrical rooms, including masonry, drywall, doors, frames, hardware, miscellaneous metals, and paint and epoxy flooring. Budget ranges for these subsystems vary significantly, with glass and aluminum systems estimated between 7.5 million and 10 million dollars and vertical transportation between 6.5 million and 8.5 million dollars. Qualified firms must submit their bids via email using the provided bid forms and include a required bid bond. This is a Project Labor Agreement project, and all subcontractors are required to provide a Workers Compensation Waiver of Subrogation. Successful bidders must furnish all necessary documentation, including Small Business Administration Form ID numbers, and subcontracts will be executed using standard Hensel Phelps forms. The solicitation emphasizes the inclusion of disadvantaged, veteran-owned, and HUBZone businesses. Bids are evaluated based on the total bid items for each subsystem, and interested parties are encouraged to participate in non-mandatory virtual pre-bid meetings and site walks.
Hensel Phelps

POSTED

about 1 hour ago

DEADLINE

in 1 day
View Details
NAICS: 236220
New
CITY OF GREENFIELD WASTEWATER TREATMENT PLANT UPGRADE PROJECT
Solicitation # city-greenfield-wastewater-treatment-plant-upgrade-project
The City of Greenfield Wastewater Treatment Plant Upgrade Project involves the construction of an upgraded 2.0 million gallons per day wastewater treatment plant located at 41901 Walnut Avenue in Greenfield, California. The project is managed by C. Overaa & Co. and has a total duration of 915 calendar days. The scope of work is divided into four distinct phases: site preparation including soil stabilization and facility relocation; construction of the main plant featuring a Membrane Bioreactor system, UV disinfection, and SCADA; decommissioning and demolition of existing facilities; and the completion of finish facilities including the Walnut Avenue extension for various water and sewer services. This solicitation is open to small businesses, including certified veteran, women, and disadvantaged business enterprises, with a specific local hiring goal requiring 50 percent of the construction workforce to reside in Monterey, San Benito, or Santa Cruz counties. Bids are due by October 28, 2026, following a mandatory pre-bid meeting on October 5, 2026. Subcontractors must utilize the Textura electronic invoicing system, adhere to Overaa standard agreements, and provide a 100 percent faithful performance and labor bond if requested. The project requires strict adherence to arcflash compliance and the maintenance of the existing plant's operations throughout the initial construction phases.
C. Overaa & Co.

POSTED

about 1 hour ago

DEADLINE

in 16 days
View Details
NAICS: 236220
New
P1102 Weapons Magazine and Ordnance Operations Facility, Naval Submarine Base New London, Groton, Connecticut
Solicitation # p1102-weapons-magazine-ordnance-operations-facility-naval-submarine-base-new-london-groton
The P1102 Weapons Magazine and Ordnance Operations Facility project at the Naval Submarine Base New London in Groton, Connecticut, is a comprehensive construction effort managed by J & J Contractors, Inc. The scope of work involves the construction of six Containerized Long Weapons Storage units, two Box G magazines, and one Box H earth-covered high-explosive magazine, along with a new Ordnance Operations building, Truck Inspection facility, and Sentry building. Key technical requirements include the installation of overhead cranes, intrusion detection systems, grounding and lightning protection, and specialized foundation work utilizing rigid inclusions and load transfer mats. The project also necessitates the demolition of 18 existing magazines and two buildings, as well as extensive sitework involving rock excavation, grading, and wetland mitigation. The contract spans a duration of 1828 calendar days and encompasses a wide array of trades, including demolition, abatement, structural steel, electrical utilities, and mechanical systems. Infrastructure improvements include the development of access roads, paved loading areas, and telecommunications systems. This solicitation is set aside for various small business categories, including SDB, WOSB, HUBZone, and VOSB. Interested parties must respond by October 31, 2026, and should contact Rahul Maheshwari to obtain the formal bid invitation and project documents.
J & J Contractors, Inc

POSTED

about 1 hour ago

DEADLINE

in 19 days
View Details

More opportunities from Department Of Defense → FA4610 30 Cons Pk

Same awarding agency

NAICS: 561210
New
Federal
Facility Readiness and Maintenance Execution (FRAME) Request for Proposal (RFP) - DRAFT
Solicitation # FA461027R0001
The Facility Readiness and Maintenance Execution (FRAME) contract is a 100% small business set-aside acquisition under NAICS 561210, serving as the follow-on to the Launch Operations Support Contract (LOSC). Managed by the 30th Contracting Squadron at Vandenberg Space Force Base, California, the contract provides non-personal maintenance, repair, modification, and modernization services for over 130 facilities, property, and equipment. The scope includes critical infrastructure such as HVAC, power distribution, water and gas mains, roofing, and the certification of cranes and elevators across Vandenberg SFB and several geographically separated locations, including Pillar Point, Oak Mountain, and Santa Ynez Peak. Notably, the South Vandenberg Power Plant is excluded from this new requirement. The acquisition utilizes a best-value source selection process with a focus on technical capability, past performance, and cost. Technical evaluation is gated by a Mission-Essential Contractor Services Plan, followed by assessments of program management, maintenance and repair, and pressure vessel expertise. The contract structure includes a mix of Firm-Fixed-Price (FFP), Cost-Plus-Incentive-Fee (CPIF), and Cost-Plus-Fixed-Fee (CPFF) CLINs, covering areas such as corrosion control, urgent response, and MDA facility requirements. The tentative schedule indicates a final RFP issuance in January 2027, with proposals due in March 2027, an anticipated award in December 2027, and performance beginning April 1, 2028.
Facilities Support Services

POSTED

4 days ago

DEADLINE

in 4 months
View Details
NAICS: 334515
Federal
Sources Sought - Modular Fiber Optic Test Platform
Solicitation # FA461026SS0001
The 30th Contracting Squadron is conducting market research through Request for Information FA461026SS0001 to identify capable sources for a Modular Fiber Optic Test Platform. This total small business set-aside under NAICS 334515 seeks a portable, ruggedized solution for the installation, maintenance, and troubleshooting of advanced fiber optic networks. The required system must feature a battery-powered mainframe with at least four slots, 128 GB of internal flash memory, and a strict prohibition against integrated Wi-Fi, Bluetooth, or any other RF-transmitting hardware for security compliance. The technical requirements specify two primary optical test modules: a quad-wavelength OTDR capable of testing at 850/1300 nm and 1310/1550 nm with intelligent link mapping for icon-based schematic diagnosis, and a dispersion analyzer for measuring both Chromatic Dispersion and Polarization Mode Dispersion. Additionally, the system must include tool-free modular port interfaces, a fiber optic loopback mirror with a UPC polish connector, and be delivered in a single, hard-sided transit case. Interested vendors must submit their company details, CAGE code, UEI number, and a capability statement not exceeding five pages to the designated points of contact by December 12, 2026, at 3:00 PM PST.
Instrument Manufacturing for Measuring and Testing Electricity and Electrical Signals

POSTED

9 months ago

DEADLINE

in 2 months
View Details

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS