Upper Baker Installing Trailer Pads and Utilities

Active
1240LT26Q0126Federal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

This contract involves the installation of electrical, water, and sewer utilities along with connections to existing infrastructure and trailer pads at a site in Monticello, Utah, under the jurisdiction of the Manti-Lasal National Forest. The work includes connecting a new 2-inch HDPE blue poly water line to the existing 2-inch poly line between the meter and bunkhouse, with a stop and waste valve installed within five feet of the connection. The sewer line will connect to the existing system at the bunkhouse using 6-inch main line with 6-inch to 3-inch wye connections for trailers, maintaining a drainage slope between 1/8 inch and 1/4 inch per foot to comply with state code. Electrical work requires coordination with Empire Electric to install a transformer and drop-down meter, followed by conduit and wiring to the trailer pads, with the contractor responsible for determining proper sizing in accordance with state regulations. All utilities must be spaced at least ten feet apart, and work must adhere to State and San Juan County codes. The contractor is responsible for securing all permits, communicating with utility providers, and handling materials and coordination throughout the project. Option items include trenching to a minimum depth of 36 inches to meet frost line requirements, backfilling, and the provision and spreading of Grade G Road Base crushed aggregate for trailer pads and roadways. An asphalt apron is also an optional component. The solicitation, numbered 1240LT26Q0126, is a total small business set-aside under NAICS code 237110, with responses due by August 10, 2026. The point of contact for inquiries is Derrick A Dodson, with additional support available through Jaren McCourt, both affiliated with the U.S. Department of Agriculture. The work will be performed at the designated location in Monticello, Utah, with all activities governed by federal and local utility standards.

General Info

Install electrical, water, sewer utilities and trailer pads in Monticello, Utah, per state and federal codes.

Agency

Department Of Agriculture → Manti-Lasal National ForestView Agency

NAICS

237110 - Water and Sewer Line and Related Structures ConstructionView NAICS

Place of Performance

Monticello, UT, 84535, USA

Set-Aside

SBA

Documents

(9)

Wage Determination UT20260075 for San Juan County Utah

PDFwage-determination

USDA Forest Service Upper Baker Site Development Specifications

DOCXspecifications

RFQ 1240LT26Q0126 Utility Lines Installation and Site Development

DOCXrfq

C04+water+details+1240LT26Q0126.pdf

PDF

C04+trailer+pad+1240LT26Q0126.pdf

PDF

Solicitation 1240LT26Q0126 - Construction Trailer Pads and Utilities

PDFifb

C04+Utility+Plan+1240LT26Q0126.pdf

PDF

SOW Upper Baker Site Development 1240LT26Q0126

DOCXsow

C04+Project+Map+1240LT26Q0126.pdf

PDF

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

PhaseCombined Synopsis
Posted

Combined Synopsis

Response Deadline

Submission deadline

Response Deadline

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyDepartment Of Agriculture → Manti-Lasal National Forest
Contacts2 people available
OfficePRICE, UT, 84501, USA
Organization / Agency
Department Of Agriculture → Manti-Lasal National Forest
View Agency Profile
Office AddressPRICE, UT, 84501, USA
Contacts
Derrick A Dodson
Jaren McCourt

Full Description

Show more

This contract is comprised of installing utility lines, connections to existing lines and connections to trailer pads. Utilities included are electrical, water and sewer. Option items included are trenching, providing and spreading gravel and installation of an asphalt apron. Water and Sewer lines and connections must be kept 10ft apart. Contractor must work with and is responsible for all communications, supplies and permits with utility companies associated. All utilities will be installed in compliance with State and/or San Juan County code.



Utilities –


Water - The new water line will be connected to the existing water line between the meter and bunkhouse. Main water line will remain same size as existing line. Existing line is a 2” poly line. New water line will be a 2” HDPE blue Poly and connect to existing. One stop and waste to be installed within 5ft of new and existing line connection.



Sewer – The new sewer line will be connected to the existing sewer line at the bunkhouse. Main line will be 6” with trailer connections being 6” to 3” Wye’s. Drainage must remain between 1/8” – ¼” per ft across the entirety of the line. Must meet state code.



Electrical – A transformer and drop-down meter will need to be coordinated and installed with Empire Electric and conduit and wiring ran from meter to the trailer pads. Contractor will be responsible for determining sizing of conduit and wiring. Must meet state code.



Option Items –


Trenching and Backfilling – Trenching will need to be 36” deep to meet frost line requirements.


                      Crushed Aggregate – Grade G Road Base for the trailer pads and roadway

Similar Contracts

Same NAICS industry code

NAICS: 237110
New
SLED
1947 Watermain - North Bound Airport Expressway PreservationThe Port of Seattle’s Aviation Project Management Group is forecasting the restoration of a 1947 water main located along the northbound Airport Expressway using cured-in-place pipe (CIPP) technology under a Design-Bid-Build procurement model. The project aims to preserve the integrity of the aging infrastructure without excavation, leveraging modern rehabilitation methods to extend service life and enhance system reliability. The work will involve lining the existing pipeline with a resin-saturated fabric liner that is inverted and cured in place, minimizing disruption to adjacent roadways and surrounding facilities. The contract falls under NAICS code 237110, indicating it is classified as Water and Sewer Line and Related Structures Construction. Moraa Omwega serves as the primary point of contact for inquiries, with Ray Moreno designated as Project Manager. The solicitation was posted on July 31, 2026, and while no set-aside designation or bid deadline has been specified, interested parties are directed to the official Port of Seattle portal for updates and detailed technical requirements. The place of performance is tied to the Airport Expressway, although exact geographic coordinates are not provided, and all work must be coordinated with ongoing airport operations to ensure safety and minimize impact to airfield access and logistics.
Aviation Project Management Group

POSTED

about 10 hours ago

DEADLINE

N/A
View Details
NAICS: 237110
New
SLED
Bid #EAJA2627-1 Locate and Identify Water Service Lines
Solicitation # Bid #EAJA2627-1
The Ephrata Area Joint Authority is soliciting sealed bids for the locating and identifying of approximately 1,000 existing water service lines through excavation, material identification, documentation, and full restoration of all disturbed areas, under Bid #EAJA2627-1. Bids must be submitted electronically via the PennBid platform by 10:00 AM local time on Thursday, August 27, 2026, with bid results publicly displayed immediately after the online opening. All contract documents are available free of charge on the same platform, and any questions must be submitted in writing through PennBid no later than 12:00 PM on Wednesday, August 19, 2026. Each bid must include a bid bond equal to 10 percent of the total base bid, secured by certified check, letter of credit, or other acceptable form, and no bid may be withdrawn for 60 calendar days after the submission deadline unless permitted by law. The contractor is required to provide performance and payment bonds, comply with the Pennsylvania Prevailing Wage Act, adhere to Federal OSHA safety standards, and meet the requirements of PA Act 127 by submitting E-Verify enrollment verification for all employees and subcontractors prior to work commencement. The authority will award the contract to the lowest responsive and responsible bidder, reserving the right to reject any or all bids. All employment practices must comply with non-discrimination laws, including the Pennsylvania Human Relations Act, prohibiting discrimination based on race, color, creed, disability, religion, age, sex, or national origin. The work will be performed in Lancaster County, Pennsylvania, and compliance with all regulatory and contractual conditions is mandatory for contract award and execution.
Lancaster County

POSTED

1 day ago

DEADLINE

in 25 days
View Details
NAICS: 237110
New
SLED
Waterline Replacement – West Main St & Cold Storage Rd.
Solicitation # Bloomfield Borough Water Authority, Perry County
The Bloomfield Borough Water Authority is seeking bids for the replacement and extension of approximately 2,100 linear feet of 8-inch ductile iron water main along West Main Street and Cold Storage Road in Bloomfield Borough and Centre Township, Perry County, Pennsylvania, including all necessary appurtenances and site restoration. Bids must be submitted electronically through PennBid by 1 PM on Wednesday, September 9, 2026, and will be publicly opened on Tuesday, September 15, 2026, at 5 PM local time at the Authority’s building in New Bloomfield. All bidding documents are available exclusively through the PennBid website, and prospective bidders are required to register as plan holders to receive updates, addenda, and official communications; no responsibility is accepted for documents obtained from unauthorized sources. A pre-bid conference is scheduled for August 19, 2026, at the Bloomfield Borough Building, though attendance is optional. Bids must remain valid for at least 60 days after opening, extending to 120 days if award delays occur due to governmental approvals, bond requirements, or grant processing. Awards will be made only to responsible bidders evaluated on integrity, past performance, financial and technical capacity, and compliance with public policy, with the Authority retaining the right to reject any or all bids and waive irregularities as it deems in its best interest.
Perry County

POSTED

1 day ago

DEADLINE

in about 1 month
View Details

More opportunities from Department Of Agriculture → Manti-Lasal National Forest

Same awarding agency