This contract involves the installation of electrical, water, and sewer utilities along with connections to existing infrastructure and trailer pads at a site in Monticello, Utah, under the jurisdiction of the Manti-Lasal National Forest. The work includes connecting a new 2-inch HDPE blue poly water line to the existing 2-inch poly line between the meter and bunkhouse, with a stop and waste valve installed within five feet of the connection. The sewer line will connect to the existing system at the bunkhouse using 6-inch main line with 6-inch to 3-inch wye connections for trailers, maintaining a drainage slope between 1/8 inch and 1/4 inch per foot to comply with state code. Electrical work requires coordination with Empire Electric to install a transformer and drop-down meter, followed by conduit and wiring to the trailer pads, with the contractor responsible for determining proper sizing in accordance with state regulations. All utilities must be spaced at least ten feet apart, and work must adhere to State and San Juan County codes. The contractor is responsible for securing all permits, communicating with utility providers, and handling materials and coordination throughout the project. Option items include trenching to a minimum depth of 36 inches to meet frost line requirements, backfilling, and the provision and spreading of Grade G Road Base crushed aggregate for trailer pads and roadways. An asphalt apron is also an optional component. The solicitation, numbered 1240LT26Q0126, is a total small business set-aside under NAICS code 237110, with responses due by August 10, 2026. The point of contact for inquiries is Derrick A Dodson, with additional support available through Jaren McCourt, both affiliated with the U.S. Department of Agriculture. The work will be performed at the designated location in Monticello, Utah, with all activities governed by federal and local utility standards.
General Info
Agency
NAICS
Place of Performance
Monticello, UT, 84535, USASet-Aside
Timeline
Response Deadline
Organization & Contact Information
Full Description
This contract is comprised of installing utility lines, connections to existing lines and connections to trailer pads. Utilities included are electrical, water and sewer. Option items included are trenching, providing and spreading gravel and installation of an asphalt apron. Water and Sewer lines and connections must be kept 10ft apart. Contractor must work with and is responsible for all communications, supplies and permits with utility companies associated. All utilities will be installed in compliance with State and/or San Juan County code.
Utilities –
Water - The new water line will be connected to the existing water line between the meter and bunkhouse. Main water line will remain same size as existing line. Existing line is a 2” poly line. New water line will be a 2” HDPE blue Poly and connect to existing. One stop and waste to be installed within 5ft of new and existing line connection.
Sewer – The new sewer line will be connected to the existing sewer line at the bunkhouse. Main line will be 6” with trailer connections being 6” to 3” Wye’s. Drainage must remain between 1/8” – ¼” per ft across the entirety of the line. Must meet state code.
Electrical – A transformer and drop-down meter will need to be coordinated and installed with Empire Electric and conduit and wiring ran from meter to the trailer pads. Contractor will be responsible for determining sizing of conduit and wiring. Must meet state code.
Option Items –
Trenching and Backfilling – Trenching will need to be 36” deep to meet frost line requirements.
Crushed Aggregate – Grade G Road Base for the trailer pads and roadway