Z--DK HEART BUTTE DAM SAFETY MODIFICATION
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
Active Opportunities Like This One
AI Contract Overview
The Bureau of Reclamation's Missouri Basin Regional Office intends to solicit a Request for Proposals for the Heart Butte Dam Safety Modification project near Elgin, North Dakota. The project involves a comprehensive suite of civil, geotechnical, and structural construction activities to enhance the safety and stability of the dam infrastructure. Key components of the scope of work include the installation of dewatering and unwatering systems, construction of temporary cofferdams, foundation void remediation via injection grouting, and the rehabilitation of the outlet works conduit using hydro-demolition and structural shoring. Additional requirements include jet grouting, embankment excavation for new filter and drainage systems, the installation of HDPE toe-drain piping, and the placement of pre-fabricated earth retaining walls. The government intends to award a Firm Fixed Price contract to a single contractor through full and open competition, with an estimated project value exceeding 10 million dollars. Work is anticipated to occur 24 hours a day, six days a week, and the solicitation is expected to be issued around April 10, 2026.
General Info
Contract Value
$53,047,927Place of Performance
Set-Aside
Awardee
NW Construction, IncAward Issued Date
Documents
0No documents available
This contract was awarded without public documents.
AI Contract Breakdown
Uniform Contract FormatNo documents to break down
The breakdown needs solicitation documents. None were found from this contract's source.
This one is closed. Find the next one like it.
Open contracts like this one, right now:
- Imperial Irrigation District – East Highline ReservoirOpen now, due in 13 days
- Imperial Irrigation District – East Highline ReservoirOpen now, due in 13 days
Ask CLEATUS
I've read this contract. Ask me anything.
Timeline
Award Notice
Contract was awarded
Organization & Contact Information
Full Description
PRE - SOLICITATION NOTICE
140R6026R0004
The Bureau of Reclamation (hereinafter referred to as Reclamation) Missouri Basin Regional Office intends to solicit a Request for Proposals (RFP) on or around April 10, 2026, as described in this Pre-Solicitation Notice. The RFP will be issued via the Sam.Gov web page at https://sam.gov Reclamation Dakotas Area Office (DKAO) has a need for a comprehensive suite of civil, geotechnical, and structural construction activities designed to enhance the long-term safety, stability, and performance of the Heart Butte dam infrastructure as described below. The solicitation will be issued under full and open competition.
In accordance with FAR 15.201 Exchanges with Industry Before Receipt of Proposals, the Reclamation Missouri Basin Regional Office previously hosted an Industry Day Event for the Heart Butte Dam Safety of Dams Modification project located near Elgin, North Dakota. Please see special notice number DOIRFB0240024 on sam.gov for additional information regarding the industry day previously held in relation to this pre-solicitation notice.
This procurement will utilize Far Part 15 procedures. The government intends to award a Firm Fixed Price purchase order to one contractor to accomplish this scope of work.
Heart Butte Dam Safety Modification (HBSDM) Project Scope of Work
The scope of work includes, but is not limited to, the following major components:
1. Dewatering and Unwatering Systems
Design, installation, operation, and maintenance of temporary dewatering and unwatering systems to facilitate dry working conditions within the outlet works and adjacent excavation zones.
Systems shall be capable of managing both surface water and groundwater inflows throughout all phases of construction.
2. Cofferdam Works
Engineering design, construction, and subsequent removal of temporary cofferdams to isolate work areas from reservoir and tailwater influences.
Cofferdams shall meet all applicable safety and hydraulic performance criteria and be coordinated with dewatering operations.
3. Foundation Void Remediation
Injection grouting to fill and stabilize voids or discontinuities within the foundation materials, accessed from within the outlet works conduit.
Grouting operations shall be performed using low-mobility or chemical grout, as specified, to ensure compatibility with existing geologic conditions.
4. Outlet Works Conduit Rehabilitation
Selective demolition of deteriorated concrete sections using saw cutting and hydro-demolition techniques.
Installation of temporary structural shoring to support conduit integrity during repair operations.
Reinforcement repair and reconstruction of the conduit to restore structural capacity and hydraulic performance.
5. Jet Grouting Operations
Execution of jet grouting from both interior and exterior access points of the outlet works conduit to improve ground strength and reduce permeability.
Grouting shall be performed in accordance with engineered patterns and quality control protocols to ensure uniform treatment.
6. Embankment Excavation
Controlled excavation of designated portions of the existing dam embankment to facilitate installation of new filter and drainage systems.
Excavation shall be staged and supported to maintain embankment stability and minimize risk to existing structures.
7. Filter and Drainage System Construction
Construction of a new sand filter trench to intercept and manage seepage flows.
Installation of a zoned filter and drain system, including sand filter layers, gravel drainage zones, and protective berms, designed to meet modern dam safety standards.
8. Toe Drain System Installation
Placement of high-density polyethylene (HDPE) toe-drain piping systems, including associated observation wells and cleanouts, to enhance seepage monitoring and control.
All components shall be installed to specified grades and alignments to ensure long-term functionality.
9. Earth Retaining Structures
Furnishing and installation of pre-fabricated earth retaining wall systems to support excavation faces and permanent embankment features.
Retaining walls shall be designed for site-specific loading conditions and integrated with adjacent structures.
10. Outlet Conduit Joint Sealing
Application of chemical grouting techniques to seal joints within the outlet works conduit, preventing internal leakage and mitigating potential piping pathways.
Please see Attachment #1 (00 00 01_Specifications_2.23.26) for a copy of the current Reclamation specifications for more information.
The government intends to award a Firm Fixed Price contract for the forthcoming solicitation with discussions.
The government is seeking a waiver from the requirements for the implementation of a Project Labor Agreement (PLA).
Working hours are anticipated to be 24 hours a day for 6 days a week.
The government is requesting responses to this pre-solicitation announcement no later than March 31, 2026 at 1700MT. Please send all correspondence related to this pre-solicitation announcement to Mitchell Frost at •••••@•••••.•••Sign up to see this detail. It is incumbent upon contractors to monitor the Sam.Gov for RFP release and all subsequent amendments, if applicable.
Effective October 26, 2018, all contractors interested in doing business with the Federal Government must be registered in the System for Award Management (SAM) database when submitting an offer or quotation. Note: Registering in ¿SAM¿ does not constitute an automatic award of any contract or agreement to the registering contractor. SAM is centralized database for consolidating the Central Contractor Registration (CCR), the online Representation and Certifications Application (ORCA), and the Excluded Parties List System (EPLS).
Additionally, the contractors Unique Entity Identifier (UEI) is required for the SAM registration and annual confirmation requirements must be accomplished through the SAM website at https://www.sam.gov. For assistance with registering in SAM, contact the Federal Services Desk at +1 (•••) •••-••••Sign up to see this detail. Training videos are also available on the SAM.gov website under Learning Center; to help users understand the features and functionality of the site.
Payment Requests for the anticipated contract must be submitted electronically through the U.S. Department of the Treasury's Internet Payment Platform (IPP) system. The IPP website is located at https://www.ipp.gov. The contractor must use the IPP website to register access and submit requests for payment. Contractors may obtain assistance by contacting the IPP Production Helpdesk via e-mail •••••@•••••.•••Sign up to see this detail or phone +1 (•••) •••-••••Sign up to see this detail. If the contractor is unable to comply with the requirements to use IPP for invoice submission, the contractor must submit a waiver request in writing to the Contracting Officer with its proposal.
The estimated price of this construction effort is more than $10,000,000.
This pre-solicitation notice is not a RFP and does not in any way authorize vendors to incur costs on behalf of the Government.
More opportunities from Department Of The Interior → Reclamation Contracting Activity
Same awarding agency
Earlier notices in this NAICS code
Posted before this notice, open and closed
Get AI-powered intelligence on the opportunities still open
Every solicitation package arrives shredded into a compliance breakdown and matched to your past performance, with incumbent history and alerts on amendments and award.
Join 900+ contractors already using CLEATUS