CRAg01 - Hawk Highwalls
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
Active Opportunities Like This One
AI Contract Overview
The Hawk Highwalls Reclamation Project (CR-Ag-01) is a state initiative managed by the Ohio Department of Natural Resources Division of Mineral Resources Management to remediate a pre-law coal mine site in Augusta Township, Carroll County, Ohio. The project focuses on eliminating safety hazards associated with three dangerous highwalls totaling 3,500 linear feet, 17 acres of spoil, and four hazardous water bodies. The scope of work includes clearing and grubbing, impoundment dewatering, and backfilling highwalls and impoundments with existing spoil to establish safe side slopes and positive drainage. Key deliverables involve the installation of engineered catch basin risers, sediment control structures, and the implementation of a comprehensive revegetation plan. The project will be executed in phases, including a maintenance period requiring the removal of temporary structures and final grading. The estimated project cost is $2,029,473.00, with a construction completion deadline of September 25, 2027. Bidders must attend a mandatory pre-bid meeting on October 22, 2026, and submit sealed proposals via Bid Express by November 5, 2026. Award selection is based on the lowest responsive and responsible bidder, evaluating factors such as experience, financial condition, and past performance. The contract mandates compliance with the Buy America Domestic Procurement Preference, Davis-Bacon prevailing wage rates, and a 5% EDGE business enterprise participation goal. Additionally, the contractor must provide a performance bond of $26,622.50 and adhere to Ohio EPA Construction Site Stormwater General Permit requirements. Payment is processed monthly through the Division's electronic system, with an 8% retainage on labor until the project is 50% complete.
General Info
Place of Performance
OH, USASet-Aside
Documents
5AI Contract Breakdown
Uniform Contract FormatSign up to view the full breakdown with detailed analysis of each section.
View Full BreakdownThis one is closed. Find the next one like it.
Open contracts like this one, right now:
- Request for Quote for The Recharge Master Plan Update at Montclair BasinOpen now, due in 7 days
- Imperial Irrigation District – East Highline ReservoirOpen now, due in 16 days
Ask CLEATUS
I've read this contract. Ask me anything.
Timeline
Submission Closed
Organization & Contact Information
Full Description
Project Name: Hawk Highwalls Project Description: The Hawk Highwalls Reclamation Project is found on a pre-law coal mine site in Augusta Township, Carrol County, Ohio. The project site is found along the north side of State Route 9 between Meadow Road NE and Reef Road NE. The project site does not have a physical address. The project site access is found across from 9306 Kensington Road (SR-9), Kensington, Ohio 44427. The Lat Long for the project site access is: 40.709940, -80.998757.
The project site consists of multiple AML (Abandoned Mine Land) features. In total, there are 3 dangerous highwalls with a combined length of approximately 3,500 linear feet, 17 acres of spoil, and 4 associated hazardous water bodies. The height of the highwalls vary from 30 feet to a maximum height of 58 feet, above the surface of the impoundments. The impoundments have insufficient discharge structures and steep side slopes.
The intent of this reclamation project is to establish a safe and maintainable site by backfilling the highwalls, and the associated impoundments, with existing spoil to eliminate the safety concerns. The proposed construction will also provide positive drainage, safe and maintainable side slopes, and engineered basin discharge structures.
The project site will be accessed via the landowners’ access drive. A construction entrance, access road, and staging area will be constructed. The reclamation work will be performed in phases. A temporary stream crossing will be constructed to access one of the phases.
Perform the earthwork/backfilling of the highwalls after clearing and grubbing, and impoundment dewatering, have been performed. Provide positive drainage by constructing temporary diversions to convey drainage toward the sediment settling structures. For sediment basins, install an engineered catch basin riser with a temporary sediment control structure (skimmer), a 12” Ø outlet pipe, and a plunge pool to regulate the discharge through the earthen embankment. For Sediment traps, install an aggregate outlet and weir at the trap discharge. Once grading has been approved, lime the disturbed areas. Perform standard revegetation on all areas disturbed by construction.
During the maintenance period of the project, dewater the sediment settling structures and remove all accumulated sediment. Remove the plunge pools, outlet pipes, catch basin risers, and temporary sediment control structures. Remove three sediment basins, three sediment traps, and all temporary diversions by backfilling the features. Once grading has been approved, lime, fertilize, seed, and mulch the disturbed area. At the conclusion of the project, remove the temporary stream crossing.
Provide all labor, materials, and equipment necessary to perform the work shown on the Contract Drawings and conforming to the specifications.
Engineer's Estimate: $2,029,473.00
Pre-Bid Meeting (MANDATORY) Location: The project site access is found across from 9306 Kensington Road (SR-9), Kensington, Ohio 44427. The Lat Long for the project site access is: 40.709940, -80.998757.
Project Engineer: Justin Conkle, Sign up to see this detail Project Officer: Jeffrey Clarke, Sign up to see this detail
More opportunities from Ohio → ODNR-Division of Mineral Resources Management
Same awarding agency
Earlier notices in this NAICS code
Posted before this notice, open and closed
Find Active Opportunities Like This
Get AI-powered intelligence on the opportunities still open
Every page of the solicitation package shredded into a compliance breakdown
AI-powered matching based on your capabilities and past performance
Competitor and incumbent history on the requirement
Automated alerts on amendments, Q&A deadlines, and award
Join 750+ contractors already using CLEATUS