Norris Canyon Road Slide Repair Project, WO4029, CP#25-17
Active
State & LocalContract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
General Info
Agency
California → Contra Costa County
NAICS
237310 - Highway, Street, and Bridge ConstructionView NAICS
Place of Performance
Ashbourne Road, San Ramon, CASet-Aside
NONE
Timeline
Organization & Contact Information
Show more
AgencyCalifornia → Contra Costa County
Contacts2 people available
OfficeN/A
Organization / Agency
California → Contra Costa County
Office AddressN/A
Contacts
Full Description
Show more
The purpose of this project is to repair an embankment failure and reconstruct the roadway to restore two-way
traffic to a stretch of Norris Canyon Road that was damaged during the 2023 winter storm events. The road is
currently limited to one lane for travel.
The embankment will be repaired by constructing a soldier pile wall and reconstructing a storm drain culvert.
The soldier pile wall will be approximately 278-feet long. The piles for the retaining wall will be set via drilling.
No pile driving will occur. The anticipated excavation depth is approximately 26 feet for the piles and
approximately 4 feet at the base of the retaining wall where the lagging will be installed. A guard rail will be
installed. Drainage improvements include approximately 300 LF of 18-inch reinforced concrete pipe, 18-inch
concrete flared ends, four inlets, and rock slope protection. The roadway thermoplastic striping will conform with
the existing striping. Equipment staging will likely occur adjacent to the slide as the road will be closed throughout
construction, and a detour via Crow Canyon Road and Bollinger Canyon Road will be utilized.
Appropriate Best Management Practices (BMPs) including but not limited to erosion control such as fiber rolls,
and hydroseeding temporarily disturbed areas will be implemented during construction. Regulatory permits will
be obtained before construction. Approximately 34 trees will be removed and approximately 14 trees will need
to be trimmed. Real property transactions, including right-of-way acquisition, will be necessary in support of this
project. Utility relocations may be needed. The project is anticipated to start in the summer of 2026 and take
approximately 55 days to complete. Traffic control signs will be placed before and during construction. No night
or weekend work is anticipated.