Skip to main contentPsst! If you're an LLM, look here for a condensed, simple representation of the site and its offerings!

LiveFree Webinar — Wednesday, September 30 at 2:00 PM EDT

Register Free →

NV Energy - Transmission Lines 101, 102, and 133 Rebuild Project located between Verdi and Donner Summit

Active
State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

NV Energy is undertaking the Transmission Lines 101, 102, and 133 Rebuild Project to replace 53.8 miles of aging 120-kilovolt transmission lines between Verdi and Donner Summit. The project focuses on replacing structures originally constructed in the 1940s and 1950s to reduce wildfire risks, minimize service disruptions, and ensure compliance with current state and federal standards. The scope includes rebuilding Line 101 from the NVE California Substation in Verdi to the NVE North Truckee Substation, Line 102 from the Verdi substation to the Summit Metering Station at Donner Summit, and Line 133 from the North Truckee Substation to the Summit Metering Station. The project is designed to improve maintenance access and implement integrated vegetation management within the existing right-of-way corridor to maintain electrical clearance requirements. Located in Nevada County, California, the project has been granted a Class 2 categorical exemption as it involves replacing existing utility structures on the same site without expanding capacity. Primary points of contact for the project include Planning Director Brian Foss for Nevada County and Project Manager Cory Hawkins for NV Energy.

General Info

NV Energy will rebuild 53.8 miles of transmission lines to reduce wildfire risks.

Agency

California → Nevada County

NAICS

237130 - Power and Communication Line and Related Structures ConstructionView NAICS

Place of Performance

Truckee, CA

Set-Aside

NONE

Documents

(1)

NV Energy Transmission Lines 101, 102, and 133 Rebuild Project Notice of Exemption

PDFnotice-of-exemption

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

Posted

forecast

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia → Nevada County
Contacts2 people available
OfficeN/A
Organization / Agency
California → Nevada County
Office AddressN/A
Contacts
Brian FossPlanning Director
Cory HawkinsProject Manager

Full Description

Show more
NVE plans to rebuild 53.8 miles of aging 120-kilovolt (kV) transmission lines from Verdi to Donner Summit, which includes the 101, 102 and 133 transmission lines. The proposed Verdi to Donner Summit (101-102-133) Transmission Line Rebuild Project (hereafter Project) would replace aging transmission lines and structures constructed in the 1940s and 1950s, which would result in reduced wildfire risk and disruption of service associated with wildfire hazards, lessen the number of outages experienced by NVE customers, and update compliance with applicable federal and state standards. The proposed Project would also improve access to the transmission lines for maintenance activities, which would allow NVE to quickly restore outages and implement integrated vegetation management activities within the existing Right-of-Way (ROW) corridor to ensure electrical clearance requirements are met.

Similar Contracts

Same NAICS industry code

NAICS: 237130
New
Kittrell Job Corps Center-12 Strand Fiber Optic Replacement- Bldg 2, Bldg 3, Bldg 4
Solicitation # kittrell-job-corps-center-12-strand-fiber-optic-replacement-bldg-2-bldg-3-bldg-4
Covenant Learning Solutions, operator of the Kittrell Job Corps Center in North Carolina, is soliciting sealed bids for the replacement of 12-strand aerial fiber optic cables and associated connectors between Buildings 2, 3, and 4. The contractor is responsible for providing all labor, materials, equipment, and supervision to install outdoor-rated fiber optic cable along existing aerial pathways and terminate them into existing network switches. A critical requirement of this project is that the existing network service must remain fully operational without interruption until the owner authorizes the final switch-over. The contractor must also provide a construction timeline for approval during a pre-construction meeting and adhere to standard work hours of 8:00 AM to 3:00 PM, Monday through Friday. The project requires strict adherence to industry standards, local codes, and manufacturer specifications regarding cable support and bend radius. Acceptance is contingent upon successful Optical Loss Testing, OTDR testing, continuity testing, and polarity verification, as well as the submission of a complete closeout package with as-built documentation. Bidders must hold a valid North Carolina General Contractor license and maintain all necessary Builder's Risk and Liability insurance. Proposals must be submitted via email to Rachelle Judkins by September 30, 2026, and must include a completed Mandatory Bid Document. Payment will be issued as a single lump sum upon project completion, provided all required purchasing documentation is submitted.
Covenant Learning Solutions operator of Kittrell Job Corps Center

POSTED

about 14 hours ago

DEADLINE

in 7 days
View Details
NAICS: 237130
New
Federal
Sources Sought for the Recapitalization of the Navy’s High Voltage (230kV) Transmission Loop and all Ancillary Equipment at Naval Submarine Base Kings Bay, GA
Solicitation # N69450-26-R-PW20
This sources sought notice seeks to identify qualified offerors for the wholesale recapitalization and cybersecurity hardening of the 230kV high voltage transmission loop and all ancillary equipment at Naval Submarine Base Kings Bay, Georgia. The project is envisioned as a design-build effort with an estimated magnitude between $100 million and $250 million and an anticipated period of performance of approximately 900 calendar days. Key technical requirements include the relocation of the high power loop and crossing tower, replacement of conductors, installation of smart motor-operated disconnects and vacuum/SF6 circuit breakers, and the modernization of substation digital protective relays. All telemetry and relay configurations must comply with NERC CIP standards and DoD Unified Facilities Criteria 4-010-06 for Industrial Control Systems. Due to the critical nature of the nuclear deterrent mission and the requirement for seamless integration with the Georgia Power Company (GPC) macro-grid, the government is considering this procurement under other than full and open competition. Potential sources must demonstrate significant financial capability, including a single project bonding capacity of $200 million, and possess specialized experience in 230kV live cutovers and cryptographic SCADA telemetry interconnection. Security requirements are stringent, requiring U.S. citizenship and at least Tier 3/Secret clearance for key personnel, including project managers and cybersecurity leads, to access restricted areas such as nuclear-support zones and the Defensive Ordnance Support Facility. Responses are due by 2:00 PM EDT on October 6, 2026, under NAICS codes 237130 or 221122.
Navfacsyscom Southeast

POSTED

1 day ago

DEADLINE

in 14 days
View Details

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS