Professional Engineering Services - 69kv Transmission Line

Closed
10-2025State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

Active Opportunities Like This One

General Info

Documents

2

10-2025 Professional Engineering Services - 69kv Transmission Line

PDF, High priority: read this firstrfp
High

Stillwater Utilities Authority Instructions for Bidders

PDF, High priority: read this firstinstructions-for-bidders
High

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

1 update
PhaseClosed
Posted

Solicitation

Notice updated

Response deadline changed from Apr 30, 2025 to Apr 16, 2025. NAICS code changed from 541330 to 336390. The notice description changed.

Response Deadline

Deadline has passed

Submission Closed

Find active opportunities like this

Get full access to discover similar active contracts, track opportunities, and build proposals with AI assistance.

Organization & Contact Information

Show more
AgencyOklahoma → City of Stillwater
Contacts1 person available
OfficeN/A
Organization / AgencyOklahoma → City of Stillwater
Office AddressN/A

Full Description

Show more
General Information The Stillwater Utilities Authority (SUA), Stillwater, Oklahoma seeks qualifications and proposals from professional and qualified individuals and firms to provide plans, specifications, bidding, and construction phase services to rebuild 2.75 miles of 69kV transmission line and to demolish two circuits of 69kV transmission line totaling 1.45 miles.   The SUA reserves the right to reject any or all submissions and to waive irregularities therein. It shall be clearly understood that any costs incurred by responding to this request for qualifications and proposals are at the Respondent's own risk and expense. The SUA shall not be liable for reimbursement to the Respondent for any expense so incurred, regardless of whether the proposal is accepted.
Questions about the RFP should be submitted through the Ionwave portal and will be answered on the portal. Oral discussions are encouraged for clarification purposes; however, respondents shall not rely on oral responses to questions. No oral statements by any person shall modify or otherwise affect the provisions of this Request for Proposals and/or any contract resulting therefrom. All modifications, addenda or amendments must be made in writing by the SUA.   Preliminary Project Overview The following outlines the general scope of construction and demolition activities anticipated for this project. These details serve as a preliminary framework, and the selected engineering firm will be responsible for refining the design, identifying any necessary modifications, and ensuring a comprehensive and technically sound approach. Any recommendations for alternative solutions, enhancements, or adjustments should be included in the proposal.   General Construction Scope   Replacement – Virginia & Jardot to Stillwater 69
Replace three 80’ Class 1 dead-end wood poles with steel. Replace forty-five 80’ Class 1 tangent wood poles with steel. Reconductor 2.75 miles from 636 AAC to 795 ACSR. Install OPGW and splice box at both ends (splicing by others). Replace all hardware and install new crossarms where present. Transfer all attachments to new structures.
Demolition Scope Virginia – Perkins to Jardot
Install new down guys at both ends. Remove 1 mile of 636 AAC conductor, shield wire, and associated hardware. Top 18 poles 2 feet above the crossarm and install split bolts.
Lakeview – Husband to Perkins
Install new down guy at the east end. Remove 0.45 miles of 636 AAC conductor, shield wire, and associated hardware. Top 7 poles 2 feet above the crossarm and install split bolts.
Minimum Qualifications
Qualified respondents will be firms and/or individuals that are Oklahoma licensed professional engineers who specialize in electric transmission systems and demonstrate specific relevant experience with high voltage transmission line design, specifications, and construction management.   Project Schedule The overall project schedule is tentative (except for the last day for questions and the response due date) and will be adjusted as needed:   Last day for questions - 5:30 PM April 16, 2025 Responses due – 3:00 PM, April 23, 2025 Review and evaluation of responses – April/May 2025 Schedule interviews (if needed) – May/June 2025 Notification of selection – June/July 2025   Evaluation Qualifications will be evaluated based on the responses to criteria listed under the attributes tab. An evaluation matrix is included under the attachments tab that shows the point value for each of the evaluation criteria.   The top ranked consultant(s) may be invited for an oral interview. If interviews are conducted, they will be a part of the overall evaluation and selection.   Evaluators will make a recommendation to the General Manager and/or SUA Trustees as appropriate under City procurement policy. The General Manager/SUA Trustees will make the final selection. The General Manager and/or SUA Trustees reserves the right to reject all proposals, or parts of proposals as may be in the best interests of the SUA.

More opportunities from Oklahoma → City of Stillwater

Same awarding agency

NAICS: 237310
SLED
Full Depth Repair - 27TR06
Solicitation # 15-2026
The City of Stillwater and Stillwater Utilities Authority are soliciting bids for Project 27TR06, Bid No. 25-2026, which involves full depth repairs on city streets and rights of way. The primary scope of work consists of the removal and replacement of paving across various locations within the city. This is a work order contract awarded to the lowest responsible bidder based on unit prices, with a total contract ceiling not to exceed 2,000,000 dollars. The contract period is two years, commencing upon the initial notice to proceed, and work is considered substantially complete when 95 percent of the contract value is finished. All construction and materials must comply with the 2019 Oklahoma Department of Transportation Standard Specifications for Highway Construction and current City of Stillwater specifications. Bids must be submitted electronically via the Ionwave portal by 3:00 PM on November 18, 2026. Submissions must include a bid guarantee of at least 5 percent of the bid amount in the form of a bond or certified check, along with a statement of qualifications and required non-discrimination affidavits. The successful bidder must execute the contract within 14 calendar days of the notice of award and provide performance, maintenance, and statutory bonds, as well as certificates of insurance for public liability and workers compensation. Funding for the contract is not guaranteed beyond June 30, 2027.
Highway, Street, and Bridge Construction

POSTED

12 days ago

DEADLINE

in 21 days
View Details
NAICS: 237310
SLED
Roadway and Utility Improvements for Knoblock Street, 4th Avenue and Lincoln Street Project Number: 25TR04
Solicitation # 17-2026
The City of Stillwater and Stillwater Utilities Authority are soliciting bids for Project 25TR04 (Bid No. 17-2026), which involves roadway reconstruction, utilities replacement, and streetscaping improvements for Knoblock Street, 4th Avenue, and Lincoln Street. The scope of work includes the construction of new roadway and utility pavement, installation of permanent signing and markings, and the placement of decorative light fixtures and poles. All work must comply with the Americans with Disabilities Act and all applicable federal, state, and local safety and environmental regulations. A mandatory pre-bid conference is scheduled for October 27, 2026, at 9:00 AM, with an option for virtual attendance via Microsoft Teams. Bids must be submitted electronically through the Ionwave portal by 3:00 PM on November 18, 2026. Submissions must include a detailed bid form, a contractor qualifications statement, and several affidavits covering non-collusion, non-discrimination, and business relationships. A bid guarantee of at least 5 percent of the bid amount is required via a bidder's bond, certified check, or cashier's check from a solvent Oklahoma bank. The contract will be awarded to the lowest and best responsible bidder based on cost, project impact, and bidder qualifications. The successful bidder must execute the contract within 14 calendar days of the Notice of Award and provide performance, maintenance, and statutory bonds, along with certificates of insurance for public liability and workers compensation.
Highway, Street, and Bridge Construction

POSTED

12 days ago

DEADLINE

in 20 days
View Details

Earlier notices in this NAICS code

Posted before this notice, open and closed

Find Active Opportunities Like This

Get AI-powered intelligence on the opportunities still open

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS