Skip to main contentPsst! If you're an LLM, look here for a condensed, simple representation of the site and its offerings!

LiveFree Webinar — Wednesday, September 30 at 2:00 PM EDT

Register Free →

Reclamation District 1500 Flood Control and Flood Safety Rehabilitation Project

Active
State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The Reclamation District 1500 Flood Control and Flood Safety Rehabilitation Project focuses on the modernization and rehabilitation of the Karnak Drainage Facility in Sutter County, California, to ensure continued flood protection for the Sutter Basin. The project covers approximately 7.6 acres and aims to increase total pumping capacity from 1,900 to 2,200 cubic feet per second. The scope is divided into four primary measures: modernizing Pumping Plant 1 (PP1) through equipment refurbishment and the addition of a new electrical control building; upgrading electrical utilities with new high-voltage transformers; constructing a gravity outlet structure with a fish barrier following the demolition of the non-functional Pumping Plant 2 (PP2); and replacing Pumping Plant 3 (PP3) with a new Pumping Plant 4 (PP4) featuring submersible pumps and a backup generator. To maintain continuous drainage services, construction will be executed in two phases over two years. The first year focuses on PP1 modernization, utility upgrades, and the construction of the gravity outlet structure. The second year involves the demolition of PP3, construction of PP4, and the installation of a SCADA system for automated monitoring. The project includes critical infrastructure improvements such as the installation of protective liners, flowmeters, and new flap gates in discharge culverts. This effort is partially funded by the Natural Resources Conservation Service Watershed Flood Prevention and Operations program and has undergone environmental review and approval under CEQA as of August 25, 2026.

General Info

Rehabilitating Karnak Drainage Facility in Sutter County to increase flood pumping capacity.

Agency

California → Reclamation District No. 1500

NAICS

237990 - Other Heavy and Civil Engineering ConstructionView NAICS

Place of Performance

Yuba City, CA

Set-Aside

NONE

Documents

(5)

RD 1500 Flood Control Project Draft Initial Study/Mitigated Negative Declaration June 2026

PDFismnd

RD 1500 Flood Control and Flood Safety Rehabilitation Project Notice of Completion

PDFnotice-of-completion

RD 1500 Notice of Intent to Adopt Mitigated Negative Declaration

PDFnotice-of-intent

RD 1500 Flood Control and Flood Safety Rehabilitation Project Summary Form

PDFsummary-form

Notice of Determination - RD 1500 Flood Control and Flood Safety Rehabilitation Project

PDFnotice-of-determination

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

1 update
Posted

forecast

Notice updated

The notice description changed. The point of contact changed.

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia → Reclamation District No. 1500
Contacts1 person available
OfficeN/A
Organization / Agency
California → Reclamation District No. 1500
Office AddressN/A
Contacts
Roger CornwellGeneral Manager

Interested Companies (1)

Show more
Provost & Pritchard Consulting Group
Clovis, CA

Full Description

Show more
The Project would rehabilitate and modernize the existing Karnak Drainage Facility to continue to provide flood protection for the Sutter Basin similar to current operations. The Project’s Area of Potential Effects is approximately 7.6 acres in size. The existing Karnak Drainage Facility discharges water from the Sutter Basin into the Sacramento Slough and consists of three antiquated pump stations that have been well maintained but much of the equipment is nearing the end of its useful life. Pumping Plant 1 (PP1) on the north bank of the drainage canal was constructed in 1914 and provides the ability to discharge 1,200 ± cubic feet per second (cfs) of drain water out of the Sutter Basin utilizing six centrifugal pumps during above normal winters and large storm events. Pumping Plant 2 (PP2) was constructed in 1929 and has never operated correctly and is not utilized. PP3 is located adjacent to PP2 and has been in operation since 1952 and is used in day-to-day operations to remove excess precipitation in the winter months and seepage water during the entire year, utilizing four vertical pumps with a capacity of 700 ± cfs. These pumping plants have no automatic controls or a backup power system. All three pumping plants have concrete pump houses and have existing culverts through the flood control levee that discharge the water into the Sacramento Slough. The Project would overhaul and modernize the existing drainage and flood protection facility to increase reliability and efficiency, leveraging to the extent possible, the existing facilities that RD 1500 already owns. The Project would also result in the installation of a backup power source and increased pumping capacity to provide redundancy and provide for anticipated climate change impacts. Project design would result in maintaining the PP1 building and discharge culverts but modernizing the pumping equipment and electrical system; removing the existing PP2 building and equipment; constructing a gravity outlet structure with fish barrier that utilizes the existing PP2 culverts for gravity drainage; and the removal of the existing Pumping Plant 3 (PP3) building and equipment and constructing a slightly larger, new Pumping Plant 4 (PP4) with submersible pumps that utilizes the existing PP3 discharge culverts. Electrical equipment would be located above the base flood elevation. Fill would be added onto a portion of the outer levee slope to make an equipment pad to facilitate installation of an engine generator set above the base flood elevation to serve as a backup power source. The Project would provide a long-term flood management solution by efficiently and reliably continuing current operations. An inflatable bladder cofferdam, or comparable watertight barrier, will be used temporarily during construction to isolate the discharge culvert outlets in the Sacramento Slough to prevent water from obstructing the installation of protective liners and flowmeters in the discharge culverts and installation of new flap gates on the existing culvert outlets. Construction activities in the Sacramento Slough would occur when the water level is at its lowest stage, likely in the summer and fall months. In developing the Project design, a preliminary structural evaluation of the existing Karnak Drainage Facility pump station buildings was conducted by a licensed California structural engineer to determine their suitability for continued use. Initial Structural Evaluation reports for all three of the existing buildings at the Karnak site are contained in the Watershed Plan-EIS, with the findings summarized below: • The PP1 pump house building (PH1) is impressively sized and reinforced, and it appears the building has performed well and is currently performing in general conformance to the original intent of the design. However, there exist some issues that are recommended for further evaluation to determine if remedial efforts are needed and/or if structural strengthening would be beneficial for further long-term use of the structure. • While not currently being used, the PP2 pump house building (PH2) has significant geometric characteristics of the structure that cause a high level of concern for the structure to resist moderate to major seismic event forces. • The PP3 pump house building (PH3) appears to be performing in general conformance to the original intent of the design, however, similar to the PH2 building, the structure has significant geometric characteristics that cause a high level of concern for the structure to resist moderate to major seismic event forces. It is anticipated at this time that Pacific Gas & Electric Company (PG&E), the local electrical utility, will want to discontinue providing the existing 2300V electrical service to the facility once the modernization has been complete, and that PG&E will want to bring in 4160V or higher voltage to serve the site in the future, although this assumption needs to be verified with PG&E during the final design process. The Project design can accommodate the upgraded PG&E service by installing District owned transformers to step the voltage down to 480V to power the new submersible pumps at the new pump station as well as the rebuilt motors on the existing centrifugal pumps at PP1. The Project has been divided into four Measures that correspond to the major work items. The table below presents the various components of each measure of the Project. Modernization Alternative Project Activities Summary: Measure 1 - Modernize Existing Pumping Plant 1 (PP1) • Installation of permanent sheet piling near PP1 to construct a foundation pad for a new electrical control building and area adjacent to the new gravity outlet structure. • Construction of a new, larger, and slightly higher platform structure near PP1 with the installation of a new air—conditioned electrical control building. • Refurbish the six existing 200 cfs centrifugal pumps. • Rebuild the six existing centrifugal pump 800 Hp motors for 480V service. • Modify the existing centrifugal pump priming system for easier operation. • Replacement of valves and actuators on pump discharges. • Install protective liner and add flow measurement inside all 3 existing discharge culverts. • Replacement of existing flap gates and slide gates on discharge culverts in existing access chamber. • Rehabilitate existing PP1 building by sealing concrete cracks and recoating roof. • Remove all electrical equipment that serves PP1 from the existing platform structure. • Installation of all new electrical equipment, switchgear, and motor controls for PP1. • Installation of step-down transformers adjacent to the control building on the elevated platform to reduce PG&E high-voltage down to 480V to power the pumping equipment. Measure 2 - Utility Upgrade • Construction of an elevated platform for new transformers. • Installation of new PG&E high-voltage electrical transformers. Measure 3 — Construct Gravity Outlet Structure • Relocation of powerlines serving the existing PP3 station (which currently cross the existing PP2 building). • Installation of a temporary cofferdam in the drainage canal to facilitate dewatering the area around the existing PP2 building. • Removal of all equipment and demolition of the existing PP2 building. • Removal of existing concrete stopblocks and sediment lodged in discharge culverts. • Construction of a concrete gravity outlet structure and fish barrier, consisting of: • reorientation of discharge culvert inlets; • slide gates on culvert inlets; • pleated long-crested weir for level control in the drainage canal, outlet measurement, and prevention of juvenile fish from migrating into the drainage canal during gravity flow operations; • fish barrier screen to prevent migration of adult fish into the drainage canal during gravity flow operations; • bypass slide gates in long-crested weir if drainage canal needed to be drained; • installation of a water level sensor; and • maintenance hoist to clean the fish barrier screen. • Installation of protective liner inside all 3 discharge box culverts. • Replacement of flap gates on discharge culvert outlets. Measure 4 – Construct New Pumping Plant 4 (PP4) • Installation of a temporary cofferdam in the drainage canal to facilitate dewatering the area around the existing PP3 building. • Removal of all PP3 equipment and demolition of the existing PP3 building. • Construction of a new concrete PP4 pump structure. • Installation of protective liner and flow measurement inside all four existing PP3 box culverts. • Replacement of slide gates inside access chamber on existing PP3 discharge culverts. • Replacement of flap gates on the existing PP3 discharge box culvert outlets. • Construct pad for backup generator on a portion of the outer levee, with fill material installed on the levee. • Installation of permanent sheet piling between the PP4 pump structure and the gravity discharge structure. • Miscellaneous grading around structures and approach roads. • Installation of six submersible VFD (variable-frequency drive) controlled pumps with a discharge capacity of approximately 1,000± cfs. • Installation of electrical controls inside the air-conditioned control building at PP1. • Installation of a SCADA (Supervisory Control and Data Acquisition) system for automated operation and monitoring of the pump stations. • Installation of backup generator on outer levee to power PP4 in the event PG&E power is lost. Construction of the Project would need to be conducted in phases since drainage service must continue to be provided at the Karnak Facility at all times. Construction would likely need to occur in the following sequence: Year 1 (PP3 operational) • Installation of new elevated platform, control building and electrical system at PP1, keeping power to existing PP3 station • Modernization of pumping equipment at PP1 and rehabilitation of existing PP1 discharge culverts while PP3 is still operational • Installation of new PG&E high-voltage transformers on elevated platform • Demolition of PP2 building, renovation of PP2 discharge culverts for gravity drainage, and construction of gravity outlet structure with fish barrier while PP3 is still operational Year 2 (PP1 and gravity drainage operational) • Demolition of PP3 building, rehabilitation of existing PP3 discharge culverts, and construction of a new PP4 pump station • Installation of backup generator on a portion of the outer levee • Installation of a SCADA system Modernization of the existing facility meets the purpose and need of the Project, provides safety and protection for the community of Robbins and surrounding area, protects farmland and emergency access roads, maintains the local economy, maintains environmental benefits, and is the most logistically reasonable option for maintaining flood protection for the Sutter Basin.

Similar Contracts

Same NAICS industry code

NAICS: 237990
New
Haleiwa Small Boat Harbor Maintenance Dredging and Revetted Mole Repair
Solicitation # W9128A26BA002
Solicitation W9128A26BA002 is a firm-fixed-price contract issued by the U.S. Army Corps of Engineers Honolulu District for maintenance dredging and revetted mole repair at the Haleiwa Small Boat Harbor in Oahu, Hawaii. The project scope includes mobilization and demobilization, the dredging and ocean disposal of approximately 4,260 cubic yards of material to an approved offshore site south of Oahu, and the repair of the revetted mole involving stone rework, vegetation removal, and the installation of best management practices. The estimated contract value ranges from 1 million to 5 million dollars, with a performance period of 200 calendar days from the receipt of the notice to proceed. This opportunity is set aside for HUBZone small businesses, who receive a 10 percent price evaluation preference. Key requirements include the provision of performance and payment bonds, adherence to the Davis-Bacon Act, and the appointment of key personnel including a Project Manager, Project Superintendent, Quality Control System Manager, and Site Safety and Health Officer. Acceptance of the dredging work is based on multi-beam hydrographic survey data, while stone revetment is subject to visual inspection for defects. Bids must be submitted as sealed physical offers by September 30, 2026, as electronic submissions are not permitted. Liquidated damages for delays are set at 2,297 dollars per calendar day.
Healy Tibbitts Builders, Inc.

POSTED

about 2 hours ago

DEADLINE

in 8 days
View Details
NAICS: 237990
New
SLED
WWRF Recycled Water Pond Erosion Prevention Project
Solicitation # W-335
The WWRF Recycled Water Pond Erosion Prevention Project, solicitation W-335, is a construction contract issued by the Western Municipal Water District for erosion control and slope stabilization at the Western Water Recycling Facility in Perris, California. The scope of work involves establishing a 2:1 slope configuration using riprap-filled HDPE bags and loose riprap, installing drainage improvements such as V-ditches and drop inlets, and installing railing along the Recycled Water Storage Pond and concrete-lined basin. The project is estimated at 1,500,000 dollars with a completion timeframe of 240 calendar days from the date of the Notice to Proceed. The contract will be awarded to the lowest responsive and responsible bidder. Bidders must submit their proposals electronically via the PlanetBids Procurement Portal by October 15, 2026, at 2:00 PM. Required submission documents include the complete bid forms package, bid bonds, a non-collusion declaration, a list of proposed subcontractors, and a certified data sheet for materials. The successful contractor must provide performance and payment bonds each equal to 100 percent of the bid amount and comply with California prevailing wage laws and Department of Industrial Relations registration requirements. Technical execution must adhere to the Greenbook standards, and the contractor is required to provide a written work plan and construction schedule.
Western Municipal Water District

POSTED

about 14 hours ago

DEADLINE

in 24 days
View Details

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS