This Solicitation opportunity from Government of Canada was posted on June 5, 2025. The submission period has ended. Browse the details below for market research, or find similar active opportunities.
Stage 2 - Rogers Pass Discovery Center Stabilization, Glacier National Park.
Closed
5P468-24-0228/ACanadaSubmission Closed
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
General Info
Agency
Government of Canada → Parks Canada AgencyView Agency
NAICS
N/A
Place of Performance
*British Columbia, CANSet-Aside
NONE
Documents
(0)AI Contract Breakdown
Uniform Contract FormatNo contract breakdown available.
Cannot generate Contract Breakdown because no documents were found from this contract's source.
Timeline
1 update
PhaseClosed
Submission Closed
Organization & Contact Information
Show more
AgencyGovernment of Canada → Parks Canada Agency
Contacts1 person available
OfficeN/A
Office AddressN/A
Contacts
Full Description
Show more
5P468-24-0228/A Stage 2 - Rogers Pass Discovery Center Stabilization, Glacier National Park.
REQUIREMENT
Mount Revelstoke and Glacier National Parks requires a Contractor to execute a structural stabilization and envelope repair on the Rogers Pass Discovery Centre (RPDC).
The RPDC was completed in 1981 and has provided services adjacent to the summit of Rogers Pass between Revelstoke and Golden since opening. Structural deficiencies in the building threaten the structure and is required to be remediated to meet current structural code.
This scope of work will include the following general sequence of activities:
• Remove the existing green roof system and replace with a lighter weight SBS roof system.
• Complete structural upgrades to address lateral load instabilities, including improving load
pathway design by re-enforcing shear walls and roof diaphragm.
• Remove and repair damaged wood column bases that are rotten.
• Install borate rods as a decay prevention measure on wood columns with minor water damage
that are not being replaced.
• Remove the cladding on the rear exterior wall and repair water damaged / wood rot areas and
install a new water proofing membrane, weeping tile / drainage mat and new cladding.
• Regrade around the exterior of the building to improve drainage away from the base of the
building to mitigate water damage to exterior cladding.
• Remove 2 existing customer service desks and replace with a single more functional and barrier
TWO STAGE SELECTION PROCESS
This posting is the Stage Two of a two-stage solicitation process: the first stage was to evaluate the qualifications of all interested suppliers. The second stage (Stage Two) is to invite the qualified suppliers to provide a financial bid on the project based on the specifications and drawings.
Only qualified suppliers have been invited to bid.