Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

Documents

This scope was carved out of DFW21311.

The full solicitation package (2 documents), including the RFP, is on the prime solicitation, not on this scope.

View the prime solicitation

EF-South Control Panel Relocation

AI Contract Breakdown

Uniform Contract Format

No documents to break down

The breakdown needs solicitation documents. None were found from this contract's source.

Timeline

Posted

subcontract

Response Deadline

Submission deadline

Response Deadline

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyTexas → Dfw International Airport
ContactsNo contacts available
OfficeN/A
Office AddressN/A
ContactsNo contact information available

Full Description

Show more
Performs electrical relocation of the E/F-South Sump Pump Control Panel for prime contractors on DFW International Airport Board facility projects. De-energizes, labels, and disconnects circuits; mounts panel at upper-level location; extends and reroutes raceways; performs splicing and conductor sizing. Work must comply with NEC and DFW Airport facility standards. Delivers a fully operational relocated control panel and circuit test reports.

Similar Contracts

Same NAICS industry code

NAICS: 238210
New
SLED
26-169
Solicitation # SJPC-26-169
The Balzano Lift Truck project, solicitation SJPC-26-169, is a public works procurement by the South Jersey Port Corporation for the installation of electric vehicle charging infrastructure at the Balzano Marine Terminal in Camden, New Jersey. The primary objective is to establish charging facilities for two Taylor ZLC-995 top loader trucks and five Ford Lightning work trucks. The technical scope includes the installation of a 1MVA transformer, a 1200A main disconnect, a 480V panel, two 200kW chargers, a 112.5kVA transformer, a 208V panel, and five 11.5kW chargers. The contractor is responsible for all labor, materials, and supervision, including the installation of underground conduits, ground rings, and precast transformer pads, all performed in accordance with NEC 2020, NFPA 70E, and OSHA standards. The contract is subject to stringent regulatory and compliance requirements, including New Jersey State prevailing wage laws, Executive Order 151 regarding equal employment opportunity, and the Build America, Buy America (BABA) act for the 200kW charging stations. Bidders must provide performance and payment bonds, a consent of surety, and disclose political contributions via the NJ ELEC affidavit. The project emphasizes small business participation, with a 25 percent set-aside goal for certified Small Business Enterprises. Award evaluation is based on proposal completeness, with specific rules for resolving discrepancies in favor of unit prices and written words. Final deliverables include a complete set of redline drawings submitted to the owner's engineer upon project completion.
South Jersey Ports

POSTED

about 6 hours ago

DEADLINE

in 4 days
View Details

More opportunities from Texas → Dfw International Airport

Same awarding agency

NAICS: 238210
New
SLED
EF-South Control Panel Relocation
Solicitation # DFW21311
The Dallas-Fort Worth International Airport Board is soliciting quotes under solicitation number DFW21311 for the relocation of the E/F-South Sump Pump Control Panel to a new upper-level location at the E/F-South Vault within the Energy Plaza/Central Utility Plant. The scope of work includes the safe de-energization, labeling, and disconnection of electrical circuits, as well as the mounting of the panel and the extension of raceways, feeders, and conductors. The contractor is responsible for providing all necessary hardware, fittings, and grounding and bonding in strict accordance with current National Electrical Code (NEC) standards, facility standards, and manufacturer recommendations. A fully operational system and reported test results for all terminations and circuits are required for final acceptance. Quotes must be submitted exclusively through the Bonfire hub portal by 2:00 PM Central Time on October 15, 2026, and must remain valid for 60 days. Pricing must be F.O.B. destination, freight prepaid and allowed, to the Energy Plaza/Central Utility Plant, with deliveries scheduled between 8:00 AM and 4:00 PM, Monday through Friday. The contract will be awarded as a purchase order to the lowest responsive and responsible bidder, with the Board reserving the right to split the award. Awardees must comply with Executive Order No. 11246 regarding nondiscrimination, provide a full warranty statement with their quote, and adhere to OSHA regulations for the labeling and documentation of any hazardous chemicals used.
Electrical Contractors and Other Wiring Installation Contractors

POSTED

about 23 hours ago

DEADLINE

in 6 days
View Details
NAICS: 541613
SLED
In-Country Mexico Sales and Commercial Services
Solicitation # PA2237
Dallas Fort Worth International Airport is soliciting proposals for a Mexico-based contractor to provide in-country sales and commercial services for a five-year term with no renewal options. Operating under the direction of Air Service Development, the contractor will execute a strategic plan to increase international passenger growth to and from Mexico, specifically targeting volumes between Mexico and key Asian markets. The scope of work includes conducting monthly sales calls with airlines and travel agencies, penetrating corporate markets through global travel management companies, and supporting cargo priorities in the automotive, aerospace, pharma, and medical device sectors. The contract utilizes a pricing structure consisting of a monthly retainer and a reimbursable contingency of 150,000 dollars per year, with a total estimated value of 750,000 dollars excluding retainer costs. Proposals will be evaluated based on technical approach, management capability, quality assurance, implementation plans, and financial capability. Key compliance requirements include strict adherence to the U.S. Foreign Corrupt Practices Act and anti-corruption laws, as well as nondiscrimination and safety standards. While the Small Business Enterprise goal is 0 percent, SBE+ certification is required to meet this goal. The procurement timeline began with a posting on September 28, 2026, with a response deadline of October 27, 2026, and an estimated award date in February 2027.
Marketing Consulting Services

POSTED

11 days ago

DEADLINE

in 18 days
View Details
NAICS: 541910
SLED
Mystery Shopper Services TBU
Solicitation # PA2255
DFW International Airport is soliciting proposals for Mystery Shopper Services to support its Transportation and Business Unit under solicitation number PA2255. This three-year contract requires a qualified agency to provide specialized evaluation services, with a Small Business Enterprise (SBE) participation goal of 15%. To meet this goal, participating firms must be SBE+ certified by an approved agency, such as the North Central Texas Regional Certification Agency, and maintain a physical place of business within the airport's designated market area across several North Texas counties. The procurement process involves rigorous compliance and documentation requirements. Proposers must submit a Business Disclosure Form, a Commitment to SBE Participation, and a Final Schedule of Subcontractors via the Bonfire portal. Mandatory insurance coverages include Texas Workers Compensation, Commercial General Liability with severability of interests, and Business Automobile Liability. Contract administration requires that all payments be reported online through the B2Gnow Compliance Management System, and contractors must maintain payment records for at least three years for potential on-site or records inspections. Failure to adhere to SBE program policies or severe breaches of contract may result in suspension or debarment from future airport solicitations.
Marketing Research and Public Opinion Polling

POSTED

22 days ago

DEADLINE

in 7 days
View Details
NAICS: 562991
SLED
Grease Interceptor Inspection & Cleaning Services
Solicitation # PA2266
DFW International Airport is soliciting bids for solicitation PA2266 to provide grease interceptor inspection and cleaning services across multiple airport locations, including Terminals A through F, the Grand Hyatt, and Corporate Aviation. The contract spans a five-year term from FY27 through FY31 with no options to renew. The scope of work requires monthly inspections using an Environmental Biotech Dipstick-Pro or approved equal to measure grease and sludge thickness, as well as the vacuum removal of waste grease and pressure washing of lines. All waste must be disposed of at approved facilities in compliance with Texas Commission on Environmental Quality regulations, and contractors must provide detailed manifests and maintain interceptor log forms. Emergency response is required within two hours. The contract will be awarded to the lowest responsive and responsible bidder based on unit prices. Bidders must submit all proposals electronically via the Bonfire portal by October 13, 2026. Mandatory submission requirements include a business disclosure form, an endorsement form, and comprehensive insurance certificates covering Workers Compensation, Commercial General Liability, and Business Automobile Liability. While the Small Business Enterprise goal is 0 percent, the airport strongly encourages SBE participation and requires specific documentation, such as a Schedule of Subcontractors and Intent to Perform forms, to receive credit. Performance in secure areas requires AOA access permits and adherence to strict security and environmental spill response protocols.
Septic Tank and Related Services

POSTED

24 days ago

DEADLINE

in 4 days
View Details

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS