TSB/Bid Ops

Active
Paul Todd AML Reclamation Project IA-343State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The Paul Todd AML Reclamation Project (Bid No. IA-343) is a coal mine reclamation effort located in Marion County, Iowa. Managed by the Iowa Department of Agriculture and Land Stewardship, the project involves extensive site work including 351,000 cubic yards of excavation, 36 acres of clearing and grubbing, terrace construction, tiling, and seeding. The estimated construction cost is between 1.2 and 1.3 million dollars, and all work must comply with Davis-Bacon Wage Requirements. Sealed bids must be submitted via the IMPACS electronic system by 2:00 p.m. on September 8, 2026, and must include a bid security equal to 10 percent of the total bid amount. A non-mandatory pre-bid conference is scheduled for August 28, 2026, in Knoxville, Iowa. Once the Notice-to-Proceed is issued, work must begin within 14 days and be completed by December 31, 2027.

General Info

Coal mine reclamation in Marion County, Iowa, costing 1.2-1.3 million dollars by 2027.

Agency

Iowa → Agriculture and Land StewardshipView Agency

NAICS

237990 - Other Heavy and Civil Engineering ConstructionView NAICS

Place of Performance

Marion County, IA, USA

Set-Aside

NONE

Documents

(0)

No documents available

AI Contract Breakdown

Uniform Contract Format

No contract breakdown available.

Cannot generate Contract Breakdown because no documents were found from this contract's source.

Timeline

PhaseSolicitation
Posted

Solicitation

Response Deadline

Submission deadline

Response Deadline

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyIowa → Agriculture and Land Stewardship
Contacts1 person available
OfficeDes Moines, IA, 50319, USA
Organization / Agency
Iowa → Agriculture and Land Stewardship
View Agency Profile
Office AddressDes Moines, IA, 50319, USA

Full Description

Show more
PAUL TODD AML RECLAMATION PROJECT SECTION 27, TOWNSHIP 74 NORTH, RANGE 18 WEST, MARION COUNTY, IOWA BID NO. IA-343
Sealed bids will be received by the Iowa Department of Agriculture and Land Stewardship, Division of Soil Conservation and Water Quality (Division), via the Iowa Management of Procurement and Contracts System (IMPACS) electronic procurement system, until 2:00 p.m. local time, on September 8, 2026. The bid opening, which is open to the public, will be held through IMPACS beginning 2:00 p.m. local time, when bids will be read outloud. Interested parties may call in to hear the bid opening using the Microsoft Teams call-in number: +1 469-998-7627, code 817435939#.
The bid shall be accompanied by a bid security as set forth in Document B, Instructions to Bidders, in the amount of 10% to the total bid amount. Bids must be submitted on the appropriate forms provided in IMPACS.
A pre-bid conference will be held on August 28, 2026 at 10:45 a.m., Marion County Extension Office, 210 North Iowa Street, Knoxville, Iowa, 50138, telephone: 641-842-2014. Attendance at the pre-bid conference by prospective bidders is not mandatory but is encouraged.
In general, the work involves but is not limited to: clearing and grubbing, debris removal, excavation, terrace construction, tiling, rip rap placement, soil amendments, erosion stabilization, and seeding. The project includes the following approximate quantities of work: 36 acres of clearing and grubbing, 351,000 cubic yards of excavation, 970 tons of Class E Revetment, 6,300 feet of terraces, 1,900 feet of drain pipe, 34 acres of seeding, and other appurtenant work normally associated with a coal mine reclamation project. The cost of construction for this project is estimated at $1.2 to $1.3 million.
The Plans and Construction Specifications governing the construction of the proposed improvements have been prepared by Shive-Hattery, Inc. and are hereby made a part of this notice by reference and the proposed Contract shall be executed in compliance therewith. This project shall comply with Davis-Bacon Wage Requirements.
THE CONTRACT DOCUMENTS, INCLUDING PLANS, CONSTRUCTION SPECIFICATIONS, AND BID PACKAGE, ARE ONLY AVAILABLE THROUGH THE IDALS WEBSITE LINK https://iowaagriculture.gov/dscwq/requests-proposals.
The work under the proposed contract shall commence within fourteen (14) days after Notice-to-Proceed is received and shall be completed no later than December 31 2027.
In order to be included on the plan holders list, which is required to receive meeting minutes, addenda and an updated plan holders list, interested bidders must make a written or verbal request to Michael Otten, P.E., Shive-Hattery, Inc., 515-223-8104 or motten@shive-hattery.com.
Questions concerning the Plans and Construction Specifications should be addressed to Michael Otten, P.E., 515-223-8104. All other questions concerning other Contract Documents should be addressed to Matt McDonald, Project Coordinator, 515-619-2641 or matt.mcdonald@iowaagriculture.gov. In order to be considered in a final addendum, written questions must be received no later than September 2, 2026.
The Division reserves the right to reject any and all proposals and to waive technicalities and irregularities:
IMPACS BIDDER LOGIN: - https://solutions.sciquest.com/apps/Router/SupplierLogin?CustOrg=DASIowa

Similar Contracts

Same NAICS industry code

NAICS: 237990
New
Sanitary Sewer & Recycled Water Project in CA
Solicitation # sanitary-sewer-recycled-water-project-ca
The Sanitary Sewer and Recycled Water Project in Colusa, California, involves the installation of approximately 13,000 linear feet of new sewer gravity mains, recycled water mains, and sewer force mains. The scope of work also includes the construction of sewer manholes and necessary surface restoration through pavement grinding and overlay. Garney Pacific, Inc. is acting as the contracting entity for this project, which is owned by the City of Colusa. The solicitation, categorized under NAICS code 237990 for heavy and civil engineering construction, is specifically designed to solicit subcontractor quotes and emphasizes participation from various small and disadvantaged business enterprises, including WOSB, HUBZone, VOSB, and SDVOSB firms. Subcontractors interested in bidding must submit their quotes electronically through the Garney Pacific website by the deadline of September 1, 2026, at 3:00 PM PT. Key contractual requirements include the mandatory use of union labor and the provision of 100% payment and performance bonds from a U.S. Department of the Treasury Circular 570 listed surety company, though the prime contractor has agreed to reimburse bond premiums. Bidders are required to use Garney’s standard purchase order and subcontract forms, with the option to submit redlines for review. While specific evaluation factors and total contract value are not disclosed in the solicitation, the project places a strong emphasis on meeting or exceeding Disadvantaged Business Enterprise (DBE) participation goals.
Garney Pacific, Inc.

POSTED

about 11 hours ago

DEADLINE

in 9 days
View Details
NAICS: 237990
New
Haleiwa Small Boat Harbor Maintenance Dredging and Revetted Mole Repair
Solicitation # W9128A26BA002
The Haleiwa Small Boat Harbor Maintenance Dredging and Revetted Mole Repair project is a firm-fixed-price solicitation issued by the U.S. Army Corps of Engineers Honolulu District. The scope of work includes mobilization and demobilization, dredging and ocean disposal of approximately 4,260 cubic yards of material, and repairs to the revetted mole involving clearing, grubbing, stone rework, and the installation of new stone. The project is located in Haleiwa, Oahu, Hawaii, and has an estimated contract value between $1,000,000 and $5,000,000. The performance period is set for 200 calendar days from the date of the Notice to Proceed. This solicitation is a sealed bid process intended for small businesses, including various set-asides such as Small Disadvantaged Business, Women-Owned Small Business, HUBZone, and Veteran-Owned Small Business. Contractors are required to provide several key personnel, including a Project Manager, Project Superintendent, Quality Control System Manager, and Site Safety and Health Officer, all of whom are subject to government approval. Strict adherence to safety standards, specifically USACE EM 385-1-1, is mandatory, and contractors must submit an Accident Prevention Plan and monthly exposure reports. Quality control is managed through a three-phase inspection process, and materials like stone must meet specific ASTM international standards. Additionally, bidders must furnish a bid guarantee and provide performance and payment bonds. The contract is subject to the Davis-Bacon Act regarding prevailing wages, and liquidated damages are set at $2,297 for each calendar day of delay.
Healy Tibbitts Builders, Inc.

POSTED

about 11 hours ago

DEADLINE

in about 1 month
View Details
NAICS: 237990
New
SBWRP Reverse Osmosis System
Solicitation # K-26-2469-DBB-3
Garney Pacific, Inc. is soliciting subcontractor bids for the SBWRP Reverse Osmosis System project located in San Diego, California. The project, owned by the City of San Diego, involves the design and removal of existing trailer-mounted Electrodialysis Reversal (EDR), slab-mounted Membrane Filtration (MF), and Reverse Osmosis (RO) units. These will be replaced with new slab-mounted MF and RO units to create a demineralization facility at the South Bay Water Reclamation Plant, specifically aimed at reducing the total dissolved solids in reclaimed water. The estimated bid value for this project is $19,300,000.00. Garney Pacific is seeking quotes for a wide range of trades, including HVAC, plumbing, electrical, concrete, pumping, crane services, aggregate, landscaping, painting, piping insulation, and demolition. As a general contractor, Garney Pacific, Inc. is actively seeking participation from SLBE and ELBE firms, including those with DBE, MBE, WBE, or SBE certifications. The solicitation includes various set-aside categories such as Small Business, Women-Owned Small Business, and Veteran-Owned Small Business. All selected subcontractors are required to utilize union labor and must be prepared to provide a 100% Payment and Performance Bond from a US Treasury listed Surety Company. While Garney will reimburse subcontractors for required bond premiums, bidders must provide their bond rate at the time of their quote. The basis of contracting will be the Garney Standard Purchase Order and Subcontract forms. The deadline for bid submissions is August 27, 2026, by 2:00 PM PT.
Garney Pacific, Inc.

POSTED

about 11 hours ago

DEADLINE

in 4 days
View Details

More opportunities from Iowa → Agriculture and Land Stewardship

Same awarding agency

NAICS: 237990
SLED
26-09 Har892022C (Hardin)
Solicitation # HAR892022C
The contract pertains to the construction of a nutrient reduction wetland project in Hardin County, Iowa, identified as Har892022C under Contract No. 26-09, managed by the Iowa Department of Agriculture and Land Stewardship. Scope of work includes selective clearing, drain tile investigation and removal, excavation, grading, installation of reinforced concrete pipe (RCP), dual-wall high-density polyethylene (HDPE) piping systems ranging from 6-inch to 12-inch diameters, CMP tile outlets, a 4’x4’ concrete water control structure, stop log storage, riprap placement, topsoiling, earthfill, and seeding as specified in IA CS-006. The project involves approximately 904 cubic yards of excavation, over 14,000 linear feet of HDPE pipe, more than 10,000 cubic yards of earthfill, and 5,591 cubic yards of topsoil, with seeding divided into buffer (June 30, 2027 deadline) and structural (September 15, 2027 deadline) phases. Estimated construction cost ranges between $200,000 and $300,000, with payment based on unit prices submitted in bids, evaluated against estimated quantities, and disbursed monthly via signed Application and Certificate for Payment (Document SS). The contract does not use standard FAR clauses but instead relies on a comprehensive set of General Conditions (Document FF) and Special Conditions (Document GG) governing performance, inspection, changes, delays, and payment. The contractor must furnish a 10% bid bond, a performance and payment bond equal to 100% of the contract amount, and comply with strict insurance requirements including $1 million general liability, $500,000 auto liability, and $1 million umbrella coverage, all with 30-day notice provisions for cancellation. Seeding must adhere to seasonal guidelines, and all materials must be delivered and stored per manufacturer specifications in undamaged, labeled, weather-protected conditions. Work must conform to OSHA safety standards and IA CS specifications, with inspections coordinated through the Engineer, Shive-Hattery, Inc., and the Division. The project is subject to liquidated damages for delays and must be completed by June 15, 2027, with final acceptance contingent on written certification by the Engineer and the Division’s issuance of final payment.
Other Heavy and Civil Engineering Construction

POSTED

18 days ago

DEADLINE

in 3 days
View Details