West Oakland Specific Plan

Active
State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The Mandela Station Mixed-Use Development project, located at 1451 7th Street in Oakland, California, involves the remediation of soil contaminated with metals, polycyclic aromatic hydrocarbons, and polychlorinated biphenyls at the West Oakland BART Station. Under a Remedial Action Plan approved by the Department of Toxic Substances Control, the project will excavate approximately 18,200 cubic yards of soil to support the T-1, T-3, and T-4 development projects and the T-2 Plaza. Of this volume, 8,550 cubic yards of contaminated soil will be transported to offsite waste disposal facilities via licensed haulers, while 9,650 cubic yards of clean soil will be used for backfilling. Remaining soils will be managed through an engineered cap consisting of future structures and hardscape, supported by a Land Use Covenant and an operation, maintenance, and monitoring plan that includes annual inspections and five-year reviews. The project is governed by the City of Oakland as the lead agency and adheres to the West Oakland Specific Plan Environmental Impact Report. Performance is subject to strict environmental and safety standards, including the use of low VOC coatings, compliance with California Air Resources Board off-road diesel regulations, and the implementation of site-specific health and safety plans conforming to federal and Cal/OSHA regulations. Construction activities are restricted to specific hours, with extreme noise activities limited to 8:00 a.m. to 4:00 p.m. The estimated schedule for soil testing, excavation, disposal, and re-grading is between five to eight weeks. Administrative oversight is managed by Project Manager Sarah Larese, with a Notice of Determination signed on August 26, 2025.

General Info

Excavate 18,200 cubic yards of contaminated soil, dispose of 8,550 cubic yards offsite, cap remainder, enforce land use covenant and ongoing monitoring in Oakland.

Agency

California → City of Oakland

NAICS

237990 - Other Heavy and Civil Engineering ConstructionView NAICS

Place of Performance

Oakland, CA, 94607

Set-Aside

NONE

Documents

(2)

Notice of Determination for Mandela Station Mixed-Use Development RAP

PDFnotice-of-determination

Addendum to Final EIR for Mandela Station Mixed-Use Development

PDFenvironmental-impact-report-addendum

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

Posted

forecast

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia → City of Oakland
Contacts2 people available
OfficeN/A
Organization / Agency
California → City of Oakland
Office AddressN/A
Contacts
Sarah LareseProject Manager
Art MayProject Development Partner

Full Description

Show more
The Department of Toxic Substances Control (DTSC) approved the Remedial Action Plan (RAP) for the Mandela Station Mixed-Use Development located on a portion of the West Oakland BART Station at 1451 7th Street in Oakland, California (Site). Soil at the Site was found to be impacted by metals (lead, arsenic, and mercury), polycyclic aromatic hydrocarbons (PAHs), and polychlorinated biphenyls (PCBs). To address impacted soil at the Site, the following remedial actions will be implemented: 1. Soil within the development areas where metals and chemicals are identified will be excavated and removed for construction of new buildings. Approximately 18,200 cubic yards of soil will be excavated from the Project Site to accommodate building foundations for the T-1, T-3 and T-4 development projects and the T-2 Plaza. Of this excavated soil, approximately 8,550 cubic yards of contaminated soil (or about 47%) will be transported to an appropriate offsite waste disposal facility, and the remaining 9,650 cubic yards of clean soil will be used to backfill the foundation excavations. 2. The remaining soils will be capped by future structures and hardscape features following redevelopment (i.e., an “engineered cap”). 3. If remaining soil within the development area contains metals or chemicals above cleanup goals, the engineered cap will be monitored regularly and maintained to protect the integrity of the remedy following protocols established in a future operation, maintenance, and monitoring plan. 4. A Land Use Covenant will be recorded which will restrict certain activities at the Site. 5. Annual inspections will be required based on the Land Use Covenant to ensure that all Site restrictions are followed. The City of Oakland, as Lead Agency, prepared the West Oakland Specific Plan Environmental Impact Report (EIR) and certified the Final EIR in 2014 (State Clearinghouse Number 2012102047). As Responsible Agency under the California Environmental Quality Act (CEQA), DTSC conducted an independent analysis of potential environmental impacts associated with the remediation activities identified in the RAP. DTSC prepared an Addendum to the Final EIR for the West Oakland Specific Plan incorporating the environmental evaluation of the proposed RAP remediation to the City’s Project.

Similar Contracts

Same NAICS industry code

NAICS: 237990
New
Haleiwa Small Boat Harbor Maintenance Dredging and Revetted Mole Repair
Solicitation # W9128A26BA002
Solicitation W9128A26BA002 is a firm-fixed-price contract issued by the U.S. Army Corps of Engineers Honolulu District for maintenance dredging and revetted mole repair at the Haleiwa Small Boat Harbor in Oahu, Hawaii. The project scope includes mobilization and demobilization, the dredging and ocean disposal of approximately 4,260 cubic yards of material to an approved offshore site south of Oahu, and the repair of the revetted mole involving stone rework, vegetation removal, and the installation of best management practices. The estimated contract value ranges from 1 million to 5 million dollars, with a performance period of 200 calendar days from the receipt of the notice to proceed. This opportunity is set aside for HUBZone small businesses, who receive a 10 percent price evaluation preference. Key requirements include the provision of performance and payment bonds, adherence to the Davis-Bacon Act, and the appointment of key personnel including a Project Manager, Project Superintendent, Quality Control System Manager, and Site Safety and Health Officer. Acceptance of the dredging work is based on multi-beam hydrographic survey data, while stone revetment is subject to visual inspection for defects. Bids must be submitted as sealed physical offers by September 30, 2026, as electronic submissions are not permitted. Liquidated damages for delays are set at 2,297 dollars per calendar day.
Healy Tibbitts Builders, Inc.

POSTED

about 13 hours ago

DEADLINE

in 7 days
View Details
NAICS: 237990
New
SLED
WWRF Recycled Water Pond Erosion Prevention Project
Solicitation # W-335
The WWRF Recycled Water Pond Erosion Prevention Project, solicitation W-335, is a construction contract issued by the Western Municipal Water District for erosion control and slope stabilization at the Western Water Recycling Facility in Perris, California. The scope of work involves establishing a 2:1 slope configuration using riprap-filled HDPE bags and loose riprap, installing drainage improvements such as V-ditches and drop inlets, and installing railing along the Recycled Water Storage Pond and concrete-lined basin. The project is estimated at 1,500,000 dollars with a completion timeframe of 240 calendar days from the date of the Notice to Proceed. The contract will be awarded to the lowest responsive and responsible bidder. Bidders must submit their proposals electronically via the PlanetBids Procurement Portal by October 15, 2026, at 2:00 PM. Required submission documents include the complete bid forms package, bid bonds, a non-collusion declaration, a list of proposed subcontractors, and a certified data sheet for materials. The successful contractor must provide performance and payment bonds each equal to 100 percent of the bid amount and comply with California prevailing wage laws and Department of Industrial Relations registration requirements. Technical execution must adhere to the Greenbook standards, and the contractor is required to provide a written work plan and construction schedule.
Western Municipal Water District

POSTED

1 day ago

DEADLINE

in 23 days
View Details

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement