2025-26 Hilliard Darby High School Retention Basin Rehabilitation Project (ST-27)
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
Active Opportunities Like This One
AI Contract Overview
The 2025-26 Darby High School Retention Basin Rehabilitation Project involves restoring the stormwater retention basin located east of Hilliard Darby High School and adjacent to Merchant Park near Downtown Hilliard. The scope includes rehabilitating the basin and removing sediment dredged from three city stormwater basins in 2025, which is currently stored on-site for drying. The project has an engineer's estimate of $918,198, and bids exceeding this amount by more than 10% will not be accepted. Tree removal activities are restricted to the period between November 1, 2025, and February 28, 2026, while the rehabilitation work around the basin is scheduled to start after June 1, 2026, with a final completion deadline of August 15, 2026. Funding for the project is provided through local sources, and state prevailing wages apply, with no Disadvantaged Business Enterprise (DBE) goal set. The project solicitation was posted on August 21, 2025, with a response deadline of September 11, 2025, and is managed by the City of Hilliard, Ohio.
General Info
Agency
Place of Performance
OH, USASet-Aside
Documents
0AI Contract Breakdown
Uniform Contract FormatNo documents to break down
The breakdown needs solicitation documents. None were found from this contract's source.
Timeline
Submission Closed
Organization & Contact Information
Full Description
The Engineer's Estimate for this project is $918,198.00. No bid will be accepted if it exceeds the City Engineer's estimate on the base bid by more than ten percent (10%).
Tree removal dates are limited to November 1, 2025 through February 28, 2026. Rehabilitation work around the basin shall commence after June 1,2026. The Final Completion Date is August 15, 2026.
This project is being funded through local funds. State prevailing wage applies to this project. There is no DBE goal.
Please review the
Earlier notices in this NAICS code
Posted before this notice, open and closed
Find Active Opportunities Like This
Get AI-powered intelligence on the opportunities still open
Every page of the solicitation package shredded into a compliance breakdown
AI-powered matching based on your capabilities and past performance
Competitor and incumbent history on the requirement
Automated alerts on amendments, Q&A deadlines, and award
Join 750+ contractors already using CLEATUS