This Solicitation opportunity from Texas was posted on August 14, 2026. The submission period has ended. Browse the details below for market research, or find similar active opportunities.

26RFCSP61 Inner Loop Annex Dehumidification Solicitation

Closed
26RFCSP61State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

Active Opportunities Like This One

NAICS: 238220
New
SLED
Install Pier D High Pressure Air System, NSBREM-724-A
Solicitation # N4425527RB003
Solicitation N4425527RB003 is a design-build project for the installation of a permanent high pressure air (HPA) system at Pier D, B724A of Naval Base Kitsap in Bremerton, Washington. The scope of work includes the design, construction, and commissioning of the system, specifically incorporating the existing HPA cross connection into a system supplied by compressors on the south end of Pier D. The project requires the installation of HPA shore risers at five specific locations: East bollards 11, 59, and 101, and West bollards 47 and 59. All new piping must be installed under service grates with valves located topside, adhering to Unified Facilities Criteria (UFC), ASME, and MIL-STD101C color coding standards. This effort is a 100% set-aside for 8(a) businesses located within SBA Region X, with an estimated construction magnitude between 1 million and 5 million dollars. The contract is a firm-fixed-price task order under the 8(a) Multiple Award Construction Contract (MACC), with a period of performance of 538 calendar days. Award is based on price and MACC past performance. Key requirements include strict adherence to EM 385-1-1 safety standards, DBIDS installation access security protocols, and the provision of comprehensive operation and maintenance data. The contractor is responsible for providing a Designer of Record to ensure all stakeholder requirements and professional engineering standards are met.
Bristol Alliance of Companies

POSTED

about 4 hours ago

DEADLINE

in 15 days
NAICS: 238220
New
CBP#9772 HVAC Air Handling Unit (AHU) and Ductwork Cleaning Services
Solicitation # CBP#9772
Management & Training Corporation (MTC) is soliciting bids for solicitation CBP#9772 to provide comprehensive HVAC Air Handling Unit (AHU) and ductwork cleaning services at the Edison Job Corps Center in Edison, New Jersey. This fixed-price, single lump sum subcontracting opportunity, with an estimated value between $100,000 and $250,000, involves the cleaning of twelve AHUs and twenty-eight heating and cooling coils serving the Kilmer and Edison dormitories. The scope of work includes removing accumulated contaminants to restore airflow and efficiency, installing permanent access panels, restoring affected building finishes, and replacing filters. The awarded contractor must complete all work within 90 consecutive business days following a written Notice to Proceed. Bids are due by November 17, 2026, and must be submitted via email using the MTC Bid for Lump Sum Contract form along with a detailed cost breakout on company letterhead. A physical site visit and signature on the attendance roster are mandatory prerequisites for bid submission. For bids equal to or exceeding $25,000, a bid bond of 20% of the base bid is required, and the successful awardee must provide performance and payment bonds from a surety company with at least an A- rating. The project is set aside for small businesses, including VOSB, SDVOSB, WOSB, and HUBZone certifications. Compliance with Davis-Bacon prevailing wage determinations for Middlesex County and various FAR clauses regarding small business utilization, security, and privacy is required. Final acceptance is contingent upon a Center inspection and the submission of a completion report featuring post-cleaning photographs and operational verification records.
Edison Job Corps

POSTED

about 4 hours ago

DEADLINE

in 1 day
NAICS: 238220
New
CBP7787 ED1 RM 123 HVAC Compressor Replacement
Solicitation # CBP7787 ED1 RM 123
Management & Training Corporation (MTC) is seeking bids for a fixed-price, single lump sum subcontract to replace a failed HVAC/refrigeration compressor at the Sierra Nevada Job Corps Center in Reno, Nevada. The project, identified as CBP7787 ED1 RM 123, has an estimated value between 0 and 25,000 dollars. The scope of work is divided into four phases: preparation and environmental safety, including refrigerant recovery per EPA Section 608 regulations; demolition and removal of the failed unit; installation of an OEM-specified compressor and associated components; and system testing and commissioning. Bids are due by November 17, 2026, and require a mandatory physical site visit and signature on the attendance roster prior to submission. Award will be based on overall best value, with MTC serving as the sole judge of responsiveness. Bidders must provide a detailed cost breakout on their own letterhead. While bid bonds are not required for projects under 25,000 dollars, any bid equal to or exceeding that amount requires a bid bond guarantee of 20 percent from a surety company with at least an A- rating. Contractors must maintain general liability insurance of at least 1,000,000 dollars and worker's compensation with employer's liability limits of 500,000 dollars. Compliance with Washoe County wage determinations and various FAR clauses regarding safety, overtime, and small business representations is required. Final payment is contingent upon a successful final inspection and the submission of closeout documentation, including a certified payroll report and a certificate of release of liens.
Sierra Nevada Job Corps Center

POSTED

about 4 hours ago

DEADLINE

in 1 day
NAICS: 238220
New
MJCC Multiple HVAC Replacement System
Solicitation # mjcc-multiple-hvac-replacement-system
Education & Training Resources is seeking quotes for a turnkey subcontracting opportunity to replace multiple HVAC systems at the Montgomery Job Corps Center in Montgomery, Alabama. The scope of work involves the removal of existing equipment and the installation of new systems across several buildings, including units ranging from 3.5 to 10 tons. Technical specifications for certain units require Energy Star certification, a minimum EER rating of 16, 90 percent efficiency furnaces, and the use of R-454B refrigerant. All work must comply with the National Electrical Code, NFPA Standard No. 101 Life Safety Code, and OSHA regulations. The project requires a 5 to 10 year warranty on equipment parts and a 2 year warranty on workmanship. Interested bidders must be registered in SAM.gov with a Unique Entity ID and provide Alabama business licenses, a W-9, FFATA form, and certificates of insurance. Submissions must include a completed bid sheet with a detailed cost breakdown, a proposed performance schedule, and an anti-lobbying certification. The Davis-Bacon Act applies, requiring the payment of prevailing wages and submission of certified payroll. Bonding requirements are tiered based on project value, with 100 percent payment bonds required for projects over 35,000 dollars and additional performance bonds required for those exceeding 150,000 dollars. Bids are due by November 27, 2026, at 12:00 PM CST, and award selection is at the sole discretion of ETR.
Montgomery Job Corps Center

POSTED

about 4 hours ago

DEADLINE

in 11 days
NAICS: 238220
New
Joliet Job Corps-Request for Quote HVAC Replacement Female Dormitory
Solicitation # joliet-job-corps-request-quote-hvac-replacement-female-dormitory
Management and Training Corporation is seeking bids for a fixed-price, single lump sum subcontract to replace the HVAC system at the Joliet Job Corps Center female dormitory in Illinois. The project scope includes the removal and disposal of existing equipment and the installation of ten new Carrier furnace and air conditioning systems, along with the integration of a Pelican Building Automation System across eleven units. The estimated contract value ranges from $250,000 to $500,000. Bids must be submitted to Frances McGraw by November 23, 2026, and must include a detailed cost breakout on company letterhead, a signed MTC Bid for Lump Sum Contract form, and a completed supplier self-certification packet. Award will be based on overall best value, with mandatory requirements including a physical site visit and a bid bond of at least 20 percent for bids exceeding $25,000. Awarded contractors must provide performance and payment bonds from a surety company with at least an A- rating and maintain general liability insurance of $1,000,000 per occurrence and worker's compensation with employer liability of $500,000. This contract is subject to the Davis-Bacon Act, requiring compliance with specific Illinois prevailing wage rates and the submission of weekly certified payroll reports. Performance dates will be established during a pre-construction meeting following the issuance of a Notice to Proceed.
Joliet Job Corps

POSTED

about 4 hours ago

DEADLINE

in 7 days
NAICS: 238220
New
Centennial Dry Sprinkler System & Compressor Replacement Services
Solicitation # centennial-dry-sprinkler-system-compressor-replacement-services
Management & Training Corporation is soliciting bids for a fixed-price, single lump sum subcontract to provide dry-type sprinkler system and compressor replacement services at the Centennial Job Corps Center in Nampa, Idaho. The project focuses on eliminating severe piping leaks and replacing failing infrastructure in the Men's Dormitory (Building CM), Women's Dormitory (Building CW), and Recreation Building (Building D). The scope of work includes the demolition and removal of existing distribution piping and compressors, followed by the installation of new systems in accordance with NFPA 25 (2023 Edition) and OEM specifications. The awarded contractor must complete all work within 30 consecutive business days following the written Notice to Proceed. Bids are due by December 1, 2026, and must be based on a mandatory physical site visit. Evaluation is based on overall best value, responsiveness, and the submission of required documentation, including a detailed cost breakout and proof of insurance. For bids equal to or greater than $25,000, a bid bond of 20% of the base bid is required at submission, and performance and payment bonds of 100% of the contract price must be provided upon intent to award. This opportunity is set aside for HUBZone, Woman-owned, and Service-Disabled Veteran-owned small businesses. The contract is subject to strict federal regulations, including prevailing wage rates per Wage Determination ID20250106 and various FAR clauses regarding security, whistleblower rights, and anti-kickback procedures. Contractors must provide a 12-digit Unique Entity ID (UEI) and, for subcontracts exceeding $45,000, disclose debarment status per FAR 52.209-6. Final payment is contingent upon a joint substantial completion inspection, the submission of a final certified payroll report, a certificate of release of liens, and the delivery of two complete sets of operation and maintenance manuals.
Management & Training Corporation/Centennial Job Corps Center

POSTED

about 4 hours ago

DEADLINE

in 15 days
NAICS: 238220
New
Inland Empire Job Corps-Request for Quote HVAC Replacement Cafeteria & OA CTS
Solicitation # inland-empire-job-corps-request-quote-hvac-replacement-cafeteria-oa-cts
Management and Training Corporation (MTC) is seeking bids for a fixed-price, single lump sum subcontract to replace packaged HVAC units with gas heating at the Inland Empire Job Corps Center in San Bernardino, California. The project focuses on the Cafeteria and OA/CTS areas and includes the removal of existing units, EPA-compliant refrigerant recovery, installation of new high-efficiency units, and necessary modifications to gas piping, ductwork, and electrical disconnects. The estimated contract value ranges from $25,000 to $100,000, with a performance period of 60 consecutive business days following the Notice to Proceed. Bids are due by November 23, 2026, and must be submitted via email to Fran McGraw. Requirements for submission include the MTC Bid for Lump Sum Contract form, a detailed cost breakout on company letterhead, and proof of a mandatory site visit. For bids of $25,000 or more, a bid bond of 20% is required, and the awarded contractor must provide performance and payment bonds from a surety company with at least an A- rating. The opportunity is set aside for small businesses, including VOSB, SDVOSB, WOSB, and HUBZone certified firms. Compliance with Construction Wage Rate Requirements (CWPR) is mandatory, requiring the payment of prevailing wages and fringe benefits as specified in General Decision CA20260026. Contractors must also adhere to OSHA 30-hour safety standards, provide necessary personal protective equipment, and submit a Certificate of Insurance. Required onboarding documentation includes a W-9, MTC Supplier Self-Certification, and a Unique Entity ID (UEI). Award decisions will be based on overall best value, with MTC serving as the sole judge of responsiveness.
Inland Empire Job Corps

POSTED

about 4 hours ago

DEADLINE

in 7 days
NAICS: 238220
New
CBP7792 Cafeteria Hot Water Heater Replacement
Solicitation # CBP7792
Management & Training Corporation (MTC) is soliciting bids for a fixed-price, single lump sum subcontract to replace the cafeteria hot water heater at the Sierra Nevada Job Corps Center in Reno, Nevada. The project requires a licensed plumbing contractor to isolate, remove, and dispose of an existing failing commercial natural gas-fired water heater and install a new commercial-grade 125-gallon natural gas-fired unit. The estimated contract value ranges from $25,000 to $100,000. Award decisions will be based on overall best value, evaluating price, quality, delivery schedule, and relevant experience. Bidders must submit a signed MTC Bid for Lump Sum Contract form along with a detailed cost breakout on company letterhead, including itemized labor, materials, and equipment specifications. For bids equal to or exceeding $25,000, a bid bond of 20% is required, and the awarded contractor must provide performance and payment bonds from an A-rated surety. Compliance with federal standards is mandatory, including the Davis-Bacon Act prevailing wage rates for Washoe County, Buy American requirements, and FAR regulations regarding trafficking in persons and business category representations. The contractor is responsible for all installation, testing, and commissioning, as well as obtaining all necessary inspections and approvals. Final deliverables include two sets of operation and maintenance manuals, manufacturer and installer warranties, and a final walkthrough with facility staff. Payment will be processed via pay applications using AIA G702 and G703 forms, with a requirement that invoices be presented and paid within ten days of receipt. First-tier subcontractors with awards exceeding $45,000 must provide specific disclosures regarding federal debarment and suspension.
Sierra Nevada Job Corps Center

POSTED

about 4 hours ago

DEADLINE

in 9 days
NAICS: 238220
New
CBP#10027 Replace Cafeteria Waste Line & Floor Restoration
Solicitation # CBP#10027
Management & Training Corporation (MTC) is seeking bids for a fixed-price, single lump sum subcontracting opportunity at the Edison Job Corps Center in Edison, New Jersey. The project, identified as CBP#10027, involves the replacement of compromised underground waste piping serving the cafeteria food line and subsequent floor restoration. The scope of work includes saw-cutting the existing floor around 3-inch drains, removing and replacing piping, backfilling, and ensuring the final system is functional and code-compliant. The estimated price range for this project is up to 25,000 dollars, with a required performance period of 30 consecutive business days following a written Notice to Proceed. Bids are due by November 16, 2026, and must be submitted to Wendy Lawrence. A mandatory physical site visit and signature on the attendance roster are required prior to bid submission. Required documentation includes the MTC Bid for Lump Sum Contract form, a detailed cost breakout on company letterhead, and the MTC Supplier Packet. For bids equal to or greater than 25,000 dollars, a bid bond of 20 percent of the base bid is required, along with performance and payment bonds from a surety company with at least an A- rating. This opportunity is open to small businesses, including certified VOSB, SDVOSB, WOSB, and HUBZone entities. The project is subject to Construction Wage Rate Requirements, necessitating compliance with prevailing wage and fringe benefit rates for Middlesex County. Award decisions will be based on overall best value, with MTC serving as the sole judge of responsiveness. Failure to complete work by the agreed date may result in liquidated damages of 100 dollars per consecutive calendar day.
Edison Job Corps

POSTED

about 4 hours ago

DEADLINE

in 20 days

AI Contract Overview

Show more

Williamson County is seeking proposals for the Inner Loop Annex Dehumidification Project under solicitation 26RFCSP61. This project involves upgrading the HVAC system by replacing five packaged rooftop units and one outside air unit with equipment featuring DX cooling, natural gas heating, and hot gas reheat for dehumidification. The scope of work includes integrating the new equipment into the existing Automated Logic building automation system, making minor ductwork modifications to meet current codes, and handling all necessary power and natural gas reconnections. Additional requirements include modifying roof openings and installing new structural steel framing to support the replacement equipment. This is a one-step selection process with a response deadline of September 17, 2026. Interested qualified contractors should direct inquiries to the primary point of contact, Michelle McKinney, via the provided agency channels.

General Info

Williamson County seeks proposals for HVAC and dehumidification upgrades by September 17, 2026.

Place of Performance

TX, USA

Set-Aside

NONE

Documents

7
PDF, High priority: read this first27 pages · contract-document
High
PDF, High priority: read this first1 page · pricing-sheet
High
PDF, High priority: read this first7 pages · specifications
High
PDF, High priority: read this first7 pages · specifications
High
PDF, High priority: read this first27 pages · contract-document
High
DOCX, High priority: read this first2 pages · sow
High
DOCX3 pages

Read all 7 documents

Every page of every file, in your free workspace.

Read the documents

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

View Full Breakdown

This one is closed. Find the next one like it.

Open contracts like this one, right now:

  • Install Pier D High Pressure Air System, NSBREM-724-AOpen now, due in 16 days
  • Water Pump ReplacementOpen now, due in 14 days
See open contracts like this

Ask CLEATUS

I've read this contract. Ask me anything.

Timeline

PhaseClosed
Posted

Solicitation

Response Deadline

Deadline has passed

Submission Closed

Find active opportunities like this

Get full access to discover similar active contracts, track opportunities, and build proposals with AI assistance.

Organization & Contact Information

Show more
AgencyTexas → Wilco
Contacts1 person available
OfficeTX, USA
Organization / AgencyTexas → Wilco
Office AddressTX, USA

Interested Companies (53)

5F Mechanical Group
Air Integrity HVAC
Airco

See All 53 Interested Companies

Get full access to view all interested companies, their contact details, and full contractor profiles.

Get full access

Full Description

Show more
Pursuant to Chapter 2269 Subchapter D of the Texas Government Code, Williamson County (County) is seeking written proposals from qualified contractors to provide Competitive Sealed Proposals for Inner Loop Annex (ILA) Dehumidification Project. County intends to utilize the one-step selection process for this solicitation and award. This project shall consist of upgrades to the HVAC system at Williamson County’s Inner Loop Annex (ILA). The project includes the replacement of five (5) existing packaged rooftop units and one (1) 100% outside air unit with similar equipment having DX cooling, natural gas heating, and hot gas reheat for dehumidification. Replacement equipment shall be tied into the existing building automation system by Automated Logic. Minor ductwork modifications shall be made to account for the increased minimum outside air requirements presented in today’s codes. Both power and natural gas shall be disconnected from the existing-to-be-demolished equipment and reconnected to the replacement equipment. Structural work will include modification of existing roof openings to suit the replacement RTU sizes and ducts as needed. New structural steel framing shall be added to support the new mechanical equipment as needed.

More opportunities from Texas → Wilco

Same awarding agency

NAICS: 237990
New
SLED
26RFCSP85 Brushy Creek Trail Retaining Wall
Solicitation # 26RFCSP85
Williamson County is soliciting competitive sealed proposals for the Brushy Creek Trail Retaining Wall project in Cedar Park, Texas. The project aims to stabilize approximately 170 feet of existing retaining wall and pedestrian railing located downstream of the Upper Brushy Creek Water Control and Improvement District Dam No. 7. The scope of work focuses on addressing cracking in the wall face and localized erosion and washout at the base. Key deliverables include compaction grouting, special excavation, embankment with density control, the installation of dry common stone riprap and filter fabric, revegetation via hydro mulch seed and plant materials, and the replacement of Type C wire fencing. The project has a construction budget of 200,000 dollars and a required completion timeline of 90 days. The selection process is based on a 100-point scoring system evaluating project manager qualifications, experience, government performance history, and pricing. Mandatory requirements include a pre-solicitation conference and site walk on November 9, 2026, with final proposals due by November 23, 2026. Awarded contractors must comply with Texas Prevailing Wage Law and provide comprehensive insurance coverage, including Workers Compensation, General Liability, and Umbrella policies. Additionally, payment and performance bonds are required for public works contracts exceeding 25,000 dollars and 100,000 dollars, respectively, while a 5 percent bid bond is required for solicitations over 100,000 dollars. Contractors must also certify compliance with Texas anti-boycott policies regarding Israel, energy companies, and firearm entities.
Other Heavy and Civil Engineering Construction

POSTED

about 5 hours ago

DEADLINE

in 7 days
View Details

Find Active Opportunities Like This

Get AI-powered intelligence on the opportunities still open

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS