Airfield Electrical and Pavement Rehabilitation Upgrades_Moses Lake Auxiliary Field

Active
W912DW26X1CHYFederal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The U.S. Army Corps of Engineers, Seattle District, has issued a Sources Sought notice to conduct market research for upcoming airfield electrical and pavement rehabilitation upgrades at the Moses Lake Auxiliary Field in Washington. This is not a request for proposals, but a search for qualified business concerns under NAICS code 237310 to determine technical capabilities and interest. The anticipated project exceeds 10 million dollars and involves pavement demolition and repaving, installation of new in-pavement lighting, and a complete overhaul of remote military operations vault equipment. The project is subject to strict operational constraints, including a maximum 60-day airfield closure window between April and September, with specific phases requiring completion within 14 to 21 days to minimize disruption to commercial runways. The government is seeking industry feedback on the feasibility of this schedule and staffing plan. Interested firms, including both large and small businesses, must submit a capabilities narrative and project examples to the designated contract specialist by the specified deadline.

General Info

US Army Corps seeks qualified firms for Moses Lake airfield electrical and pavement upgrades.

Agency

Department Of Defense → W071 Endist SeattleView Agency

NAICS

237310 - Highway, Street, and Bridge ConstructionView NAICS

Place of Performance

WA, 98837, USA

Set-Aside

NONE

Documents

(0)

No documents available

AI Contract Breakdown

Uniform Contract Format

No contract breakdown available.

Cannot generate Contract Breakdown because no documents were found from this contract's source.

Timeline

PhaseSources Sought
Posted

Sources Sought

Response Deadline

Submission deadline

Response Deadline

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyDepartment Of Defense → W071 Endist Seattle
Contacts2 people available
OfficeSEATTLE, WA, 98134-2329, USA
Organization / Agency
Department Of Defense → W071 Endist Seattle
View Agency Profile
Office AddressSEATTLE, WA, 98134-2329, USA

Full Description

Show more

The U.S. Army Corps of Engineers, Seattle District (NWS), Special Projects Branch at Joint Base Lewis-McChord (JBLM), WA has issued this Sources Sought notice for market research purposes.  The responses to this notice will be used to develop the Acquisition Strategy for an upcoming Request For Proposal (RFP) to perform airfield electrical and pavement rehabilitation upgrades at the Moses Lake Auxiliary Field.



This is not a pre-solicitation announcement, nor an RFP. No proposals are being requested or accepted with this Sources Sought and no contract shall be awarded from this Sources Sought. No reimbursement will be made for any costs associated with providing information in response to this Sources Sought or any follow up information requests. After review of the responses to this notice, and if the Government still plans to proceed with the acquisition, a separate synopsis may be published in the US Government System for Award Management (SAM) Contract Opportunities website at https://www.sam.gov.



The purpose of this Sources Sought is to determine the availability, interest, and technical capability of qualified business concerns who demonstrated capabilities in meeting the project description listed below and to receive critical feedback from industry experts regarding the feasibility of the proposed schedule, staffing, and technical requirements.



The proposed work is to be performed under the following North American Industry Classification (NAICS) code: 237310 — Highway, Street, and Bridge Construction.



Both large and small business firms are encouraged to respond to this Sources Sought notice. However, if sufficient numbers of small business firms demonstrate interest, capabilities, and qualifications, the Government may choose to set-aside the acquisition for small businesses. For the purposes of this procurement, a firm is a small business if its annual average gross revenue, taken the last 3 fiscal years, does not exceed $45,000,000.00. For more information concerning NAICS and a SBA size standards, go to http://www.sba.gov.



The following information is tentative and meant to provide interested firms with an idea of the general nature of the anticipated work. The Government reserves the right to update this information as project planning documentation is updated. The information below represents the most current information available and may be superseded upon publication of the preliminary planning information, which may be provided by the Government in the subsequent synopsis.  



Overview of Anticipated Contract: The Seattle District Corps of Engineers, under FAR Part 36 procurement procedures, anticipates issuing a Request For Proposal (RFP) and subsequent award for Construction Services to perform airfield electrical and pavement rehabilitation upgrades at the Moses Lake Auxiliary Field.



The magnitude of construction for this project is estimated to be more than $10,000,000.



Background & Scope of Work:



The project involves the Maintenance and Rehabilitation (M&R) of airfield pavements and critical electrical systems on Runway 09/27 and Taxiway Foxtrot at the Moses Lake Auxiliary Field, located at Grant County International Airport (GCIA) in Moses Lake, WA. This airfield serves active U.S. Air Force tenant operations.



Core Project Components:



  • Pavement Rehabilitation: Demolition, grading, re-paving of Asphaltic Concrete (AC) and Portland Cement Concrete (PCC) pavements, crack repairs, joint sealing, and spall/patching repairs.


  • Airfield Lighting Upgrades: Installation of new in-pavement light fixtures, augering light base locations, setting cans, pouring rapid-set concrete collars, laying new distribution paths, and pulling new #8 5kV conductors.


  • Vault Equipment Upgrades: Complete overhaul of the remote military operations runway vault equipment, including rigging and mounting new Constant Current Regulators (CCRs), installing airfield lighting control and monitoring system (ALCMS) panels, and integrating Pilot Controlled Lighting (PCL) systems.


SCHEDULE & CRITICAL PHASING CONSTRAINTS



A key challenge of this procurement is the execution schedule. The Statement of Work (SOW) dictates strict operational constraints to minimize disruption to both military operations and GCIA’s active commercial runways:



  1. Airfield Closure Limit: The total airfield closure window is restricted to a maximum of 60 calendar days between April 1st and September 30th in a single construction season. Final cleanup and site turnover must be completed within this 60-day window.


  1. Phase 1 (West Taxiway F) Restriction: Must be completed within a 14-to-21-day maximum to minimize temporary closures of the adjacent active commercial Runway 04/22.


  1. Phase 2 (East Taxiway F) Restriction: Must be completed within a 14-to-21-day maximum to minimize temporary closures of the adjacent active commercial Runway 14L/32R.


  1. Standard Working Hours: Restricted to Monday through Friday, 7:00 a.m. to 4:00 p.m. However, 24/7 operations and overtime are authorized upon pre-approval and joint planning with GCIA and the Contracting Officer’s Representative (COR).


Proposed 58-Day Electrical Milestones:



The Government has developed a tentative 58-day electrical schedule within the 60-day closure window:



  • Phase 1: Demo & Make-Safe (6 Days) — Isolate circuits, remove runway/taxiway fixtures, and demolish legacy vault equipment (ACE2, ALCMS).


  • Phase 2: Trenching & Ductbanks (9 Days) — Trench RWY 9-27 distribution paths, lay conduit, and pour localized concrete encasements.


  • Phase 3: Vault Equipment Install (10 Days, concurrent with Phase 2) — Rig/mount new CCRs, install ALCMS panels, prep terminal blocks.


  • Phase 4: Pull Cans & Cabling (10 Days) — Set new pull cans with concrete collars; pull new #8 5kV conductors.


  • Phase 5: In-Pavement Fixtures (8 Days) — Auger light base locations, set cans, and pour rapid-set concrete collars via on-site batch plant.


  • Phase 6: Joint Sealing & Testing (5 Days) — Sawcut/seal concrete joints around light cans and perform Megger testing on all loops.


  • Phase 7: System Commissioning (4 Days) — ALCMS integration, operational burn-in testing, and final turnover punch walks.


STANDARD GOVERNMENT CREW ESTIMATES



The Government's schedule assumes the deployment of three specialized, dedicated crews:.



  • Crew A: Airfield Electrical (6 Personnel) — 1 Foreperson, 2 Journeymen, 2 Labors, 1 Equipment Operator. (Focus: Field demo, conduit laying, cable pulling, setting light bases).


  • Crew B: Vault & Controls (3 Personnel) — 1 Lead Controls Electrician, 1 Labor, 1 Testing Tech. (Focus: Vault regulators, ALCMS, and systems commissioning).


  • Crew C: Targeted Concrete/Civil (4 Personnel) — 1 Batch Plant Operator, 1 Equipment Operator, 2 Concrete Placers/Finishers. (Focus: On-site batch plant operations, ductbank encasements, pull can pads, light can grouting, joint sealing).


A complete and final Statement Of Work (SOW) for the construction services required will be issued with the RFP.



SUBMISSION REQUIREMENTS:



Response to this Sources Sought shall be limited to no more than five (5) pages and shall as a minimum include the following information:



• Name, addresses, point of contact, phone number, e-mail address and small business classification under NAICS Code 237310.



• A brief capabilities narrative describing the interested firm's ability to meet anticipated contract requirements as described within this Sources Sought. In your narrative, ensure to include any specialized knowledge, expertise and past experience that would significantly benefit the Government.



• Statement of Capability to perform a contract of this magnitude and complexity. Provide up to 3 examples of projects performed. Your firm shall identify whether the work was independently completed as a prime contractor or affiliated with another contract (joint venture or as a subcontractor.) If your role was as a subcontractor, describe the specific airfield electrical and pavement services your company provided. For each project listed, please provide a brief description of the project, customer name, date of performance, and dollar value of the project.



FEASIBILITY AND FEEDBACK QUESTIONNAIRE



USACE Seattle District is seeking critical feedback from industry experts regarding the feasibility of the proposed schedule, staffing, and technical requirements. Please provide detailed answers to the following questions:



Schedule Feasibility & Phasing



  1. 60-Day Window: Is a 60-calendar-day closure window realistic and achievable to complete the entirety of the airfield electrical, vault, lighting, and associated civil upgrades? If not, what is a more realistic duration, and what specific activities are the primary drivers of schedule risk?


  1. Paving and Electrical: Please provide input on whether it would be best to do the electrical upgrades within the same contract as the remaining work, or as a separate contract action? Provide the Pro’s and Con’s for both.


Submission of your interest is not a prerequisite to any potential future offerings, but participation will assist NWS in identifying sources with required capabilities. If a solicitation is later released, it may be synopsized in SAM Contract Opportunities at https://www.sam.gov.



Interested parties shall respond to this Sources Sought no later than the date / time specified in this sources sought announcement. Email responses to: Mr. Robert Blair, Contract Specialist, CENWS-CT-D, Seattle District, Special Projects Branch Email address: robert.j.blair@usace.army.mil.  Email will be the only method when responding to this Sources Sought.



**PLEASE NOTE: NO PHONE CALLS WILL BE ACCEPTED, CORRESPONDENCE MUST BE IN THE FORM OF EMAIL WITH SUBJECT: "Sources Sought_Firm Name_ (CE0869) Rpr Moses Lake Runway”**

Similar Contracts

Same NAICS industry code

NAICS: 237310
New
Pier B On-Dock Rail Support Facility West Expansion and Pier B Street Realignment
Solicitation # HD-S3135
Kiewit Infrastructure West Co. is seeking quotes from qualified Small Business Enterprises (SBE) and Veteran-Owned Small Business Enterprises (VSBE) to serve as subcontractors, material contractors, and suppliers for the Pier B On-Dock Rail Support Facility West Expansion and Pier B Street Realignment project in Long Beach, California. The extensive scope of work includes site preparation, asbestos abatement, tunneling, boring, jacking, and the installation of various underground piping and electrical systems, as well as asphalt and concrete paving, curb and gutter work, and landscaping. Bidders must possess a valid California Contractor’s license, provide acceptable insurance, and may be required to provide bonding for 100% of their contract value, with bond premiums reimbursed by Kiewit. SBE and VSBE firms must provide certification evidence from the Department of General Services (DGS) and the Port of Long Beach PlanetBids portal. The project is subject to a Project Labor Agreement, prevailing wage rates, and the California Labor Code, requiring onsite firms to be signatory to collective bargaining agreements with specific trades including carpenters, laborers, and ironworkers. Funding is provided through multiple grants, including FHWA, LACMTA, the State of California Transportation Agency, and the U.S. DOT MARAD 2021 Port Infrastructure Development Program, making the project subject to DBE Program requirements. Interested firms must contact the Lead Estimator, Cassandra Shore, to receive an Invitation to Bid via the BuildingConnected system. The deadline for bid submissions is September 15, 2026.
Kiewit Infrastructure West Co.

POSTED

about 13 hours ago

DEADLINE

in 12 days
View Details

More opportunities from Department Of Defense → W071 Endist Seattle

Same awarding agency

NAICS: 238910
New
Federal
MMD and HAHD Woody Debris Chipping Service (Equipment w/ Operator)
Solicitation # W912DW26QA091
Solicitation W912DW26QA091 is a 100% small business set-aside invitation for bid issued by the USACE Seattle District to provide all labor, tools, and equipment for gathering and chipping woody debris at the Mud Mountain Dam and Howard A. Hanson Dam storage fields in Washington. The contractor is required to utilize excavators, dozers, and chippers to process debris, with operations scheduled for 10-hour days from Monday through Saturday between 0700 and 1730. The period of performance is 90 calendar days from the receipt of the Notice to Proceed. Award will be granted to the lowest priced responsible quoter whose submission conforms to the solicitation requirements. Key requirements include strict adherence to the Performance Work Statement, OSHA regulations, and the US Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1). Contractors must provide bid guarantees and furnish performance and payment bonds. Payment will be processed electronically through the Wide Area WorkFlow system. Submissions must include signed Standard Forms 1449 and 30, completed representations and certifications, and a detailed pricing schedule for the specified CLINs, including options for laborers with chainsaws and heavy equipment such as track-mounted hydraulic excavators and tub grinders. All quotes must be submitted via email to the designated point of contact by September 8, 2026.
Site Preparation Contractors

POSTED

1 day ago

DEADLINE

in 5 days
View Details
NAICS: 561730
New
Federal
MMD Invasive Species Control and Mitigation
Solicitation # W912DW26QA090
Solicitation W912DW26QA090 is a firm fixed price, non-personnel services contract issued by the USACE Seattle District for invasive species control and mitigation at Mud Mountain Dam in Enumclaw, Washington. This small business set-aside requires a certified licensed applicator to provide all personnel, equipment, and materials necessary to manage invasive and undesirable plant species across the dam location, recreation area, River Trail, and Rim Trail. The contract structure includes a base year running from October 1, 2026, through September 31, 2027, with four subsequent option years. Award will be granted to the lowest priced, responsible quoter who is registered in the System for Award Management. The contractor must adhere to OSHA standards and EM 385-1-1 safety requirements and provide a contract manager with full operational authority. Key deliverables include the selection and application of appropriate herbicides, the provision of product labels and Safety Data Sheets, and the placement of required signage for at least 24 hours following treatment. A comprehensive Quality Control Plan must be delivered within 30 days of award. Performance will be monitored by a Government Quality Assurance Representative according to a Quality Assurance Surveillance Plan. Quotes are due by September 8, 2026, at 11:00 AM Pacific Time.
Landscaping Services

POSTED

3 days ago

DEADLINE

in 5 days
View Details
NAICS: 561621
New
Federal
Albeni Falls Dam (AFD) Electronic Security System Servers and Workstations Upgrade
Solicitation # W912DW26QA089
Solicitation W912DW26QA089 is a total small business set-aside for the acquisition and upgrade of servers and workstations for the Albeni Falls Dam Electronic Security System in Oldtown, Idaho. The project involves upgrading the Closed-Circuit Television and Access Control Systems, which operate on an air-gapped local network. The scope of work includes the procurement of CCTV and ACS servers and operator workstations, on-site installation, commissioning, and the implementation of Department of Defense cybersecurity controls, including STIG/SRG hardening, Secure Boot, and malware protection. The contractor must ensure compatibility with Milestone XProtect Professional Plus and Identiv Hirsch Velocity software. Key deliverables include cybersecurity testing, inventory reports, network diagrams, and the provision of encrypted external hard drives with bare-metal recovery images. The contract also requires eight hours of training for up to six government personnel and a one-year warranty with a 14-day turnaround for repairs. Award will be granted to the lowest priced responsible quoter. All deliveries and services must be completed by September 14, 2026, with final acceptance occurring at the Chief Joseph Dam location in Bridgeport, Washington. Payment will be processed electronically through the Wide Area WorkFlow system.
Security Systems Services (except Locksmiths)

POSTED

3 days ago

DEADLINE

in 1 day
View Details
NAICS: 236220
Federal
$300M Indefinite Delivery / Indefinite Quantity (IDIQ) Multiple Award Task Order Contract (MATOC) for Facilities Sustainment, Restoration, and Modernization (FSRM) Program at Joint Base Lewis-McChord (JBLM)
Solicitation # W912DW27RA011
The U.S. Army Corps of Engineers Seattle District is conducting market research via a Sources Sought Notice to establish a Multiple Award Task Order Contract (MATOC) for Facilities Sustainment, Restoration, and Modernization (FSRM) at Joint Base Lewis-McChord and its sub-installations. This potential procurement has an estimated aggregate value of 300 million dollars and aims to support general construction activities, including renovations, repairs, environmental abatement, and utility infrastructure work. The intended contract structure consists of a five-year base period with a single two-year option, with individual task orders expected to range from 250,000 to 25 million dollars. This notice is for planning purposes only and does not constitute a formal solicitation or a commitment to award a contract. Interested firms are requested to submit a response via an online questionnaire and a capabilities statement not exceeding five pages by September 20, 2026. The government intends to use this information to determine the availability of qualified contractors and evaluate whether a small business or socio-economic set-aside is appropriate. An Industry Day is tentatively planned for October 15, 2026.
Commercial and Institutional Building Construction

POSTED

8 days ago

DEADLINE

in 17 days
View Details