Booster Pump Replacements at Pump Station 89A, 150, 176

Awarded
12601793State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

Active Opportunities Like This One

NAICS: 237110
New
Morgans Branch Force Main and Pump Station Improvements
Solicitation # SRP-W-134-0290
The Morgans Branch Force Main and Pump Station Improvements project, solicitation number SRP-W-134-0290, is a construction contract for the City of Belmont, North Carolina, with an estimated value of 16,690,000 dollars. The scope of work involves the construction of 16,435 linear feet of new 20-inch ductile iron force main and extensive upgrades to the Morgans Branch Pumping Station. Key deliverables include the installation of a new wet well, valve vault, pumps, a generator, and odor control equipment, as well as the demolition of existing pumps and piping. Additional requirements include site improvements, stormwater facilities, fencing, and the installation of new gravity sewers and manholes. The contract will be awarded to the responsible bidder submitting the lowest responsive bid, with evaluation focusing on qualifications, financial ability, and strict adherence to bidding documents. Bidders must provide bid security, evidence of authority to sign, and M/WBE compliance documentation, including a Good Faith Efforts Form and Table A. The successful contractor is required to furnish performance and payment bonds equal to the contract price and maintain insurance from companies with an A.M. Best rating of A-VII or better. Project administration follows EJCDC standards, with payments processed monthly via applications for payment submitted to the Engineer, and final acceptance contingent upon the Engineer's written recommendation.
Don Moorhead Construction, Inc.

POSTED

about 2 hours ago

DEADLINE

in 2 days
NAICS: 237110
New
Jefferson St. Pump Station Replacement
Solicitation # ITB-2026141
The Jefferson Street Pump Station Replacement project for the City of Winchester, Virginia, involves the construction of a new pump station featuring a precast concrete building, controls, and a standby generator. The scope of work includes site electrical, yard piping, security fencing, grading, paving, the relocation of an existing fuel tank, and the demolition of existing facilities. All work must be completed within 610 calendar days following the Notice to Proceed, with liquidated damages set at 1,000 dollars per day for delays. The project is governed by VDOT 2020 Road and Bridge Specifications and the City of Winchester Standards Manual, with strict adherence to OSHA and ADA requirements. WG Construction is seeking MBE/WBE subcontractor participation for paving, material supply, site development, fencing, MEP, roofing, and carpentry. Bids are due by 2:00 pm on November 12, 2026, via the City's e-Procurement Portal. The contract will be awarded to the lowest responsive and responsible bidder. Requirements for bidders include registration in the Commonwealth of Virginia, submission of a bid guarantee, and the provision of performance and payment bonds equal to 100 percent of the contract amount. Additionally, the project is subject to Davis-Bacon wage determinations and requires compliance with various federal executive orders regarding non-discrimination and the use of American Iron and Steel.
WG Construction Co., Inc.

POSTED

about 2 hours ago

DEADLINE

in 2 days

AI Contract Overview

Show more

The City of Fresno awarded a firm fixed price construction contract valued at $2,538,800 to W. M. Lyles Co. for wellhead treatment improvements at Pump Stations 89A, 150, and 176, with the primary objectives of enhancing system performance, efficiency, and water quality. Scope of work includes replacing booster pumps at all three locations, installing new interconnecting piping, upgrading associated electrical and instrumentation systems, and constructing a new aeration tank exclusively at Pump Station 89A. A subsequent amendment also required replacement of a carbon dioxide removal tank at PS 89A. All work is confined to existing facility boundaries under a categorical exemption under CEQA Section 15301, Class 1, which precludes significant environmental impact or operational expansion. The project was procured via a competitive sealed bid process with award determined under the lowest price technically acceptable (LPTA) methodology, where responsiveness and responsibility were evaluated prior to price being the sole deciding factor. The contract does not include federal acquisition regulation clauses, instead relying on municipal standards and custom agreements. Performance is required at the three specified pump stations in Fresno, California, with acceptance occurring on-site. The contractor must comply with the City’s Community Workforce Agreement, also known as a Project Labor Agreement, which mandates adherence to specific labor standards and ongoing reporting obligations. The project timeframe extends through October 31, 2026, with bid opening held on April 21, 2026, and City Council approval granted on June 4, 2026. Funding comes from the City’s Fiscal Year 2026 Capital Improvement Budget, sourced through the Water Enterprise Fund, though no specific accounting codes are identified. While no detailed line-item pricing, packaging requirements, or specific inspection standards (e.g., ASTM or AWWA) are stated, oversight is conducted by the Department of Capital Projects and Department of Public Utilities, with Justin Chan, Licensed Professional Engineer, serving as the primary point of contact. No option periods, extensions, or additional funding beyond the base award are included, and no formal contracting officer or COTR roles are officially designated in the documentation.

General Info

Fresno upgrades three pump stations with fixed-price contract to W.M. Lyles Co. for $2.77M under CEQA Class 1 exemption.

Documents

0

No documents available

Documents will appear here when they are available.

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

PhaseAwarded
Posted

forecast

Awarded

Contract was awarded

Find active opportunities like this

Get full access to discover similar active contracts, track opportunities, and build proposals with AI assistance.

Organization & Contact Information

Show more
AgencyCalifornia → City of Fresno
Contacts1 person available
OfficeN/A
Organization / AgencyCalifornia → City of Fresno
Office AddressN/A
Contacts
Justin ChanLicensed Professional Engineer

Full Description

Show more
Wellhead treatment improvements at existing Pump Station 89A, 150, and 176 including construction of an aeration tank (P89A only), replacement of a booster pump, interconnecting piping, and associated electrical and instrumentation lines to improve the system's performance, efficiency, and water quality.

More opportunities from California → City of Fresno

Same awarding agency

NAICS: 238910
SLED
NKRS Trucking Facility Project
Solicitation # P23-01154
The NKRS Trucking Facility Project, identified by Application No. P23-01154, involves the development of two parcels totaling approximately 4.76 acres located at 3293 West Nielsen Avenue in Fresno, California. Filed by Style-Line Construction, Inc. on behalf of NKRS Trucking, the project aims to establish a private trucking facility providing general automotive work, including minor repairs and major engine and transmission rebuilding. The development is planned in two phases, starting in late 2024, with the facility expected to be operational by Spring 2026. Phase 1 includes site preparation and the construction of a 3,000-square-foot dispatch office (Building 100) and a 9,000-square-foot metal repair shop (Building 200). Phase 2 involves the construction of an additional office space (Building 300). Site improvements include approximately 162,625 square feet of asphalt paving, a 5,000-square-foot water filtration retention basin, and parking for 56 trucks and 27 cars, including electric vehicle charging stations. Infrastructure upgrades involve undergrounding existing utility lines, installing a 14-inch water main, and improving West Nielsen Avenue with new paving, curbs, gutters, and a 12-foot-wide concrete sidewalk. Landscaping will include the planting of Chinese pistache and Natchez crape myrtle trees along with visual screening shrubs. The facility will operate from 8:00 a.m. to 5:00 p.m., Monday through Friday, with approximately six employees on-site. Security will be maintained via wrought-iron and chain-link fencing, shielded lighting, and surveillance cameras. The project is administered by the City of Fresno Planning and Development Department and complies with CEQA guidelines and safety standards established by USEPA, OSHA, and DTSC.
Site Preparation Contractors

POSTED

4 months ago

DEADLINE

N/A
View Details
NAICS: 541620
SLED
Environmental Assessment No. P23-00446/P23-00449/P23-00702
Solicitation # P23-00446/P23-00449/P23-00702
The City of Fresno is the lead agency for a reorganization project involving the annexation of approximately 10.55 acres at the southwest corner of East Nees Avenue and North Willow Avenue. This action includes detaching the land from the Fresno County Fire Protection District and the Kings River Conservation District. The project consists of three primary components: the annexation of the land, the pre-zoning of approximately 8.6 acres from agricultural to community commercial and annexed rural residential transitional zones, and a development permit for the construction of medical, dental, and professional office buildings on 3.3 acres. The project is identified under Environmental Assessment numbers P23-00446, P23-00449, and P23-00702. Under the California Environmental Quality Act (CEQA), the City of Fresno adopted a Mitigated Negative Declaration, concluding that the project would not have significant adverse environmental effects provided specific mitigation measures are implemented. The Department of Toxic Substances Control provided recommendations regarding soil testing and the management of contaminants such as pesticide residues, lead-based paint, and asbestos. Construction is slated to begin on June 2, 2025, with an operational year of 2026. All infrastructure must meet City of Fresno standards and exceed 2019 Title 24 Building Envelope Energy Efficiency Standards. Compliance with OSHA, US DOT, and EPA regulations for hazardous materials and site safety is required, with the City of Fresno Department of Public Works overseeing infrastructure inspections.
Environmental Consulting Services

POSTED

11 months ago

DEADLINE

N/A
View Details
NAICS: 237110
SLED
IIGC Downtown Water and Sewer Improvements
Solicitation # 2025100590
The City of Fresno is implementing the IIGC Downtown Water and Sewer Improvements project, funded by the California Housing and Community Development Infill Infrastructure Grant. The project aims to support the development of affordable and mixed-income housing within the Downtown Fresno triangle, specifically the area bounded by Calaveras Street, Van Ness Avenue, Grove Street, and SR-99. The scope of work includes the installation and rehabilitation of approximately 15,900 linear feet of waterline and 13,400 linear feet of sewer pipeline, along with the installation of manholes and junction structures. Construction activities involve the demolition of asphalt and one sanitary sewer manhole, the excavation of 26,700 cubic yards of soil, and the use of 10 to 20 on-site workers. Construction is scheduled to take place between January 2026 and June 2027, with work occurring Monday through Friday from 7:00 A.M. to 5:00 P.M. The project has undergone environmental review under CEQA, resulting in a Mitigated Negative Declaration. Key compliance requirements include strict archaeological monitoring during all ground-disturbing activities by qualified personnel and adherence to state laws regarding the discovery of human remains. Project management is led by Robert Diaz of the City of Fresno Capital Projects Department.
Water and Sewer Line and Related Structures Construction

POSTED

11 months ago

DEADLINE

N/A
View Details

Find Active Opportunities Like This

Get AI-powered intelligence on the opportunities still open

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS