Mike Monroney Aeronautical Center (MMAC) Industrial Waste Water Treatment Plant Upgrades (New Single Story PEMB/Demo Old Building)
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
AI Contract Overview
The Federal Aviation Administration (FAA) is conducting a market survey for the planned upgrade of the Industrial Wastewater Treatment Plant (IWTP) at the Mike Monroney Aeronautical Center in Oklahoma City. This project involves demolishing the existing IWTP and constructing a new single-story Pre-Engineered Metal Building (PEMB) of approximately 4,900 gross square feet. The new facility will include industrial waste treatment processing spaces, office areas, an equalization tank, storm shelter restroom, and utility support areas. Additionally, certain lift stations will be replaced with new double-walled fiberglass wet wells to ensure secondary containment, while others will be demolished and covered. The existing concrete containment trench will be removed and replaced with new double-walled CPVC piping installed by direct burial along the same path. The estimated project value ranges from $10 million to $20 million. Respondents to the market survey are asked to provide a capability statement outlining their services, past contract experience of similar scale, years in business, small business status, and current registration on SAM.gov including their UEI. The FAA emphasizes that this is strictly a market survey, not a solicitation for proposals, and no payment will be made for information submitted or costs incurred in preparation. All responses must be submitted via email by June 22, 2026, to the FAA contact, Andre Casiano. This survey aims to assess industry capabilities to support future procurement efforts for the IWTP upgrade.
General Info
Agency
NAICS
Place of Performance
Oklahoma City, OK, 73169, USASet-Aside
Documents
(0)AI Contract Breakdown
Uniform Contract FormatNo contract breakdown available.
Cannot generate Contract Breakdown because no documents were found from this contract's source.
Timeline
Response Deadline
Organization & Contact Information
Full Description
*********************THIS IS A MARKET SURVEY ONLY********************
- This is not a Screening Information Request or Request for Proposals of any kind;
- The FAA is not seeking or accepting unsolicited proposals;
- The FAA will not pay for any information received or costs incurred in preparing the response to the market survey; and
- Any costs associated with the market survey submittal are solely at the interested vendor’s expense. ******************************************************************************
1. This market survey is for Industrial Wastewater Treatment Plant (IWTP) which include demo existing building and construct a new Pre-Engineered Metal Building (PEMB) as identified below.
b. Disclosure of the Size of Construction Projects: This potential project is estimated to be between $10,000,000 and $20,000,000
a. Provide all labor, equipment, and materials to demolish existing Industrial Wastewater Treatment Plant (IWTP) and associated equipment. Replace with a new building located north of the existing plant as well as new lift stations and forcemain piping. The project includes:
- A new single story, Pre-Engineered Metal Building (PEMB) approximately 4,900 Gross Square Feet. Primary space is an industrial waste treatment processing area, with accessory office/work areas, equalization tank/area, storm shelter restroom, and utility support spaces.
- The existing IWTP plant (eIWTP) will be decommissioned and demolished once the new IWTP (nIWTP) plant has been built and flow has been diverted to the nIWTP for processing.
- Lift Stations #1, 3, and 4 will be replaced with new double-walled fiberglass wet wells to ensure full secondary containment. Lift stations #2 and #5 will be demolished and filled in with select fill and covered with sod.
- The existing concrete containment trench that houses the industrial waste force mains from the lift stations to the eIWTP will be demolished in full and removed. New 4-inch inner diameter by 6-inch outer diameter double-walled CPVC piping will be installed via direct bury, along the path of the removed trench.
2. Market Survey Response should include the following:
a. Capability Statement - This document should identify:
- Type of services provided by firm,
- Size and type of services provided on previous government/private sector contracts
- Number of years in business
- Small Business Size Status to include applicable small business socio-economic status
- Current SAM.gov Registration status and SAM.gov UEI
b. Brief information (Agency or Customer/Dollar Amount/Scope/etc) regarding past projects respondent has completed with similar magnitude and work that is identified in this Market Survey
All responses to this market survey must be received by June 22, 2026, 3:00 p.m. CT. All capability statements must be submitted by email to: andre.casiano@faa.gov