Raw Water Intake Line Installation

Active
State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

This subcontract opportunity involves the installation of raw water intake lines for prime contractors working on dam projects for the Kentucky Division of Water, Energy and Environmental Cabinet. The scope of work includes the abandonment of the existing City of Springfield raw water intake and the installation of new lines within the principal spillway culvert, culminating in the delivery of fully installed and tested intake lines. The project is managed by the Kentucky Department of Environmental Protection under NAICS code 237110. Interested parties must submit their responses by September 17, 2026, at 5:30 PM. Further details and submission processes are available through the Kentucky Vendor Services portal.

General Info

Subcontract for installing raw water intake lines in Kentucky; responses due September 17, 2026.

Agency

Kentucky → Dept- Environmental ProtectionView Agency

NAICS

237110 - Water and Sewer Line and Related Structures ConstructionView NAICS

Place of Performance

Other, KY, USA

Set-Aside

NONE

Documents

This scope was carved out of RFB-785-2600000643.

The full solicitation package (15 documents), including the RFP, is on the prime solicitation, not on this scope.

View the prime solicitation

RFB-785-2600000643-8 | RFB-275-26 Willisburg Lake Dam Rehabilitation Project

AI Contract Breakdown

Uniform Contract Format

No contract breakdown available.

Cannot generate Contract Breakdown because no documents were found from this contract's source.

Timeline

Posted

subcontract

Response Deadline

Submission deadline

Response Deadline

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyKentucky → Dept- Environmental Protection
ContactsNo contacts available
OfficeN/A
Organization / Agency
Kentucky → Dept- Environmental Protection
View Agency Profile
Office AddressN/A
ContactsNo contact information available

Full Description

Show more
Installs raw water intake lines for prime contractors on Kentucky Division of Water, Energy and Environmental Cabinet dam projects. Abandons existing City of Springfield raw water intake and installs new lines within the principal spillway culvert. Delivers installed and tested raw water intake lines.

Similar Contracts

Same NAICS industry code

NAICS: 237110
New
JCSD Intervalley Pipeline Project; PN C155003
Solicitation # PN C155003
The JCSD Intervalley Pipeline Project (PN C155003) involves the installation of 3.3 miles of potable water transmission pipeline located on Country Village Road in Jurupa, California. With an engineer's estimate of 36,000,000 dollars, the project is being managed by Filanc and is subject to American Iron and Steel (AIS) and Build America, Buy America (BABA) requirements. The scope of work is extensive, encompassing pipeline infrastructure such as welding, cathodic protection, valves, and jack and bore operations, as well as civil engineering tasks including paving, striping, flatwork, precast vaults, fencing, and potholing. Additionally, the project requires technical services for surveying, settlement monitoring, videography, E&IC, and environmental management through SWPPP implementation and asbestos pipe demolition and removal. This solicitation is open to a wide range of small business set-asides, including SDB, WOSB, HUBZone, VOSB, and SDVOSB firms, with a strong emphasis on the participation of SBE, MBE, and WBE entities. Filanc has indicated a willingness to assist qualified diverse firms with bonding, insurance, and equipment to encourage participation. Bids and quotes for the various project scopes must be submitted by 2:00 PM on September 18, 2026. Interested parties can obtain plans and specifications through Julia Masaitis.
Filanc

POSTED

about 9 hours ago

DEADLINE

in 12 days
View Details
NAICS: 237110
New
Seeking MBE/DBE/WBE Subcontractors and Suppliers for South Marsham Street Green Infrastructure Project (Romney, WV)
Solicitation # seeking-mbedbewbe-subcontractors-suppliers-south-marsham-street-green-infrastructure-project-romney
Harbel, Inc. is seeking MBE, DBE, and WBE subcontractors and suppliers for the South Marsham Street Green Infrastructure Project located in downtown Romney, West Virginia. This targeted green-street retrofit involves approximately 343.59 linear feet of South Marsham Street between Gravel Lane and US Route 50. The project scope requires the installation of at least 1,450 square feet of permeable pavement, eight vegetated stormwater management cells, and comprehensive drainage, underdrain, inlet, pipe, tie-in, and downspout work. Additionally, the project includes necessary curb, sidewalk, ADA, apron, crossing, and traffic-calming improvements to integrate the BMP corridor, along with the planting of six native trees and approximately 345 native plants. The primary objective of the retrofit is to treat approximately 1.7 acres of impervious surface within a 3.3-acre drainage area, concluding with final stabilization, cleanup, and restoration. This solicitation is open to various small business set-asides, including SDB, WOSB, HUBZone, and Veteran-Owned Small Businesses under NAICS code 237110. Interested parties must submit their bids by the deadline of September 17, 2026, at 4:00 P.M. Primary contact for this opportunity is Jennifer Wilson via The Belt Group.
Harbel, Inc.

POSTED

about 9 hours ago

DEADLINE

in 11 days
View Details
NAICS: 237110
New
Inland Feeder/SBVMWD Foothill PS Intertie, Stage 1
Solicitation # inland-feedersbvmwd-foothill-ps-intertie-stage-1
The Inland Feeder/SBVMWD Foothill PS Intertie, Stage 1 project, located in Highland, California, involves the installation of critical water infrastructure for the Metropolitan Water District of Southern California. The scope of work includes furnishing and installing approximately 2,150 linear feet of 54-inch to 66-inch diameter steel pipe and 200 linear feet of 144-inch diameter steel pipe. The project also requires the installation of various large-diameter valves, including contractor-furnished units and Metropolitan-furnished 54-inch and 132-inch valves, along with 54-inch and 145.5-inch diameter tie-ins. Additional infrastructure requirements include the construction of four surge tanks, two valve vaults, an air compressor yard structure, and drainage improvements. The technical scope extends to electrical upgrades, instrumentation and controls, piping systems, welding, disinfection, and surface restoration, as well as the excavation of cobbles and large boulders. This solicitation, issued by James W. Fowler Co., is open to small businesses, including SDVOSB, MBE, and WBE certified firms, with a bid submission deadline of September 29, 2026. The project encourages the use of apprentices and provides specific support for M/W/DBE subcontractors regarding bonding, insurance, and material procurement.
James W. Fowler Co.

POSTED

about 9 hours ago

DEADLINE

in 23 days
View Details

More opportunities from Kentucky → Dept- Environmental Protection

Same awarding agency

NAICS: 237990
New
SLED
RFB-785-2600000643-8 | RFB-275-26 Willisburg Lake Dam Rehabilitation Project
Solicitation # RFB-785-2600000643
The Commonwealth of Kentucky Department of Environmental Protection is soliciting bids for the Willisburg Lake Dam Rehabilitation Project in Washington County, identified as RFB-275-26 or RFB-785-2600000643-8. The comprehensive scope of work includes the construction of a reinforced concrete auxiliary spillway and floodwall, the installation of rockfill stability berms, and the replacement of low-level drawdown valves. Additional requirements involve the remediation of concrete cracking and seepage, the abandonment and replacement of raw water intake lines, spillway culvert remediation, and various demolition, site preparation, and restoration activities. Contractors are also responsible for erosion control, traffic control, and the development of a contractor-designed water diversion plan. The solicitation process has undergone multiple modifications and addenda, with the final bid response deadline set for September 17, 2026, at 17:30. Bids must be submitted exclusively online, with the official bid document and bid bond combined into a single PDF file. Key technical constraints include a prohibition on driving piles into the dam embankment and the rejection of specific waterproofing material substitutions that do not meet puncture requirements. Notably, the project is exempt from domestic material requirements such as Buy America or American Iron and Steel. Primary contact for the project is Susan Ward, and the contract is managed through the Kentucky Department for Facilities and Support Services.
Other Heavy and Civil Engineering Construction

POSTED

4 days ago

DEADLINE

in 11 days
View Details