Reclamation District 108 Slope Stability Flood System Repair Program Sites Project

Active
State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The Reclamation District 108 Slope Stability Flood System Repair Program Sites Project is a forecast initiative managed by Reclamation District 108 in California. The project focuses on the repair of two critical levee slip sites along the Colusa Basin Drainage Canal East Levee in Colusa County. Specifically, the scope of work includes a 650-foot segment at Site A, located between Tule Road and White Road at Levee Mile 17.2, and a 150-foot segment at Site B, located between Yolo County Line Road and White Road at Levee Mile 12.7. The Central Valley Water Board has issued a 401 Water Quality Certification and approved the project as of September 30, 2025. Under the California Environmental Quality Act, a Negative Declaration was prepared, determining that the project will not have a significant environmental effect, and consequently, no mitigation measures or monitoring plans were adopted. The project is categorized under NAICS code 237990, with primary coordination handled by Meegan Nagy and Peter Minkel.

General Info

Reclamation District 108 repairs 800 feet of levee in Colusa County with environmental permits and no contract details yet.

Agency

California → Reclamation District 108

NAICS

237990 - Other Heavy and Civil Engineering ConstructionView NAICS

Place of Performance

CA

Set-Aside

NONE

Documents

(1)

Notice of Determination for RD 108 Flood Repair Program

PDFnotice-of-determination

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

Posted

forecast

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia → Reclamation District 108
Contacts2 people available
OfficeN/A
Organization / Agency
California → Reclamation District 108
Office AddressN/A
Contacts
Peter MinkelEngineering Geologist
Meegan NagyDeputy Manager

Full Description

Show more
The Central Valley Water Board is issuing a 401 Water Quality Certification for the Project. The Project is intended to repair two critical levee slip sites. Repairs will occur along two segments of the Colusa Basin Drainage Canal East Levee: a 650-foot-longsegment between Tule Road and White Road at Levee Mile 17.2 (Site A), and a 150-foot-long segment between Yolo County Line Road and White Road at Levee Mile 12.7 (Site B).

Similar Contracts

Same NAICS industry code

NAICS: 237990
New
Haleiwa Small Boat Harbor Maintenance Dredging and Revetted Mole Repair
Solicitation # W9128A26BA002
The U.S. Army Corps of Engineers Honolulu District is soliciting sealed bids for a firm-fixed-price contract to perform maintenance dredging and revetted mole repair at the Haleiwa Small Boat Harbor in Oahu, Hawaii. The project scope includes the dredging and ocean disposal of approximately 4,260 cubic yards of material, with disposal at an approved offshore site south of Oahu. Additionally, the contractor will perform revetted mole repairs involving clearing and grubbing, vegetation and root removal, stone rework, and filling voids with additional stone. The estimated value of the work ranges from 1 million to 5 million dollars, with a performance period of 200 calendar days from the receipt of the Notice to Proceed. This solicitation is set aside for HUBZone small businesses, who receive a 10 percent price evaluation preference. Bidders must provide a bid guarantee and are required to furnish performance and payment bonds upon award. Key deliverables include pre- and post-dredge multi-beam surveys conducted by a third-party qualified surveyor and the submission of an operations plan within 30 days of the Notice to Proceed. The contract mandates strict adherence to USACE accuracy standards and quality control measures, including a punch-out inspection and final acceptance inspection. Liquidated damages for delays are set at 2,297 dollars per calendar day. Bids must be submitted in sealed envelopes to the Fort Shafter office, as electronic submissions are not permitted.
Healy Tibbitts Builders, Inc.

POSTED

about 13 hours ago

DEADLINE

in 14 days
View Details
NAICS: 237990
New
SLED
NPDES Oak Ridge Park East Stream Restoration
Solicitation # 27-009
Solicitation 27-009 is a request for sealed bids from the Charles County Government for the NPDES Oak Ridge Park East Stream Restoration project in Hughesville, Maryland. The project is designed to meet Maryland Department of the Environment and National Pollution Discharge Elimination System permit requirements by obtaining impervious area and nutrient reduction credits. The scope of work includes installing a stormwater detention facility, restoring approximately 1,400 linear feet of an eroding unnamed tributary to Gilbert Run using in-stream and bank stabilization structures, and stabilizing 120 linear feet of an eroding outfall channel. The contract will be awarded to the lowest responsive and responsible bidder who has been a legal entity in the field for at least five years. The project requires strict adherence to technical specifications, including a mandatory Critical Path Method schedule and compliance with Maryland State Highway Administration and Charles County construction standards. Key contractual obligations include a five percent bid bond, the use of Maryland prevailing wage rates, and the provision of performance and labor bonds. Upon completion, the contractor must provide a one-year warranty and ensure an 85 percent survivability rate for planted trees and shrubs over three years. Final payment is subject to a five percent retainage, which may be replaced by a maintenance bond, and is contingent upon the submission of as-built drawings and geotechnical inspection reports. Bids must be submitted electronically by October 13, 2026.
DPW - Capital Project Management

POSTED

1 day ago

DEADLINE

in 28 days
View Details

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 650+ contractors already using CLEATUS