This Sources Sought opportunity from Department Of Defense was posted on November 20, 2025. The submission period has ended. Browse the details below for market research, or find similar active opportunities.

Relocate Schofield Barracks Deep Wells Above Ground, Bldg 1580, Schofield Barracks, Oahu, Hawaii

Closed
W9128A26Z0002Federal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

Active Opportunities Like This One

NAICS: 237110
New
Morgans Branch Force Main and Pump Station Improvements
Solicitation # SRP-W-134-0290
The Morgans Branch Force Main and Pump Station Improvements project, solicitation number SRP-W-134-0290, is a construction contract for the City of Belmont, North Carolina, with an estimated value of 16,690,000 dollars. The scope of work involves the construction of 16,435 linear feet of new 20-inch ductile iron force main and comprehensive upgrades to the Morgans Branch Pumping Station. Key infrastructure improvements include the installation of a new wet well, valve vault, and associated appurtenances, as well as the demolition of existing pumps and piping. The contractor is responsible for delivering a fully operational facility, including the installation of pumps, a generator, odor control equipment, new gravity sewers, and manholes, while managing by-pass pumping, testing, and commissioning. The contract will be awarded to the responsible bidder submitting the lowest responsive bid, with a strong emphasis on MWBE compliance through the submission of Good Faith Efforts and Table A documentation. Bids are due by November 12, 2026, and must be submitted using the EJCDC C-410 Bid Form. The project is governed by EJCDC standard general and supplementary conditions, requiring performance and payment bonds and proof of insurance. Technical standards include AWWA Specification C-600 for pipelines, NEMA MG1 for motors, and AWS D1.2 for aluminum welding. Project administration is managed by the City of Belmont with Willis Engineers serving as the project engineer. Payment is processed via Applications for Payment, with terms set at 30 days after presentation to the owner.
Don Moorhead Construction, Inc.

POSTED

about 7 hours ago

DEADLINE

in 20 days

General Info

NAICS

237110 - Water and Sewer Line and Related Structures Construction

Place of Performance

Schofield Barracks, HI, USA

Set-Aside

NONE

Documents

0

No documents available

Documents will appear here when they are available.

AI Contract Breakdown

Uniform Contract Format

No documents to break down

The breakdown needs solicitation documents. None were found from this contract's source.

Timeline

PhaseClosed
Posted

Sources Sought

Response Deadline

Deadline has passed

Submission Closed

Find active opportunities like this

Start your free trial to discover similar active contracts, track opportunities, and build proposals with AI assistance.

Organization & Contact Information

Show more
AgencyDepartment Of Defense → W2SN Endist Honolulu
Contacts2 people available
OfficeFORT SHAFTER, HI, 96858-5440, USA
Office AddressFORT SHAFTER, HI, 96858-5440, USA
Contacts

Full Description

Show more

THIS SOURCES SOUGHT NOTICE is for informational purposes only.  THE SOURCES SOUGHT NOTICE IS NOT A REQUEST FOR PROPOSAL, QUOTATION OR INVITATION FOR BID.


The U.S. Army Corps of Engineers, Honolulu District, requests letters of interest from PRIME CONTRACTORS interested in performing work on a potential design-bid-build construction solicitation for the Relocate Schofield Barracks Deep Wells Above Ground, Bldg 1580, Schofield Barracks, Oahu, Hawaii. NO SOLICITATION IS CURRENTLY AVAILABLE.   


Project Description:


Drill four wells – estimated to be approximately 800 feet deep and 24 inches in diameter (exact depths and dimensions to be determined by design). Existing wells and pumps located below ground and are to remain on-line until new wells can manage peak demand of Schofield in June – September with consideration for the largest pump to be on stand-by. Motors to be located above ground. Each well, pump, motor sized to deliver a minimum of 2,000 gallons per minute. Roof structure (overhead cover/canopy only) required to protect the motors from the elements.


Magnitude is $50M - $100M


Interested PRIME CONTRACTORS should submit the following:


  1. Narrative demonstrating experience in constructing drilled potable water wells greater than 500 feet deep at a remote location with a limited footprint. If the construction experience from was not in a remote location with a limited footprint, provide construction experience working at a location comparable in setting to Schofield Barracks, Oahu, Hawaii. 
  2. Narrative demonstrating capability of constructing on an active water treatment facility site or similar active site conditions.
  3. Narrative demonstrating experience working with compressed construction schedules.
  4. Narrative demonstrating the capability of having access to drilling equipment that is readily available on island for projects of similar size and scope.
  5. Bonding capability for a single contract action of at least $50M and aggregate of at least $100M by the interested prime contractor.
  6. UEI and CAGE CODE, Expiration date in SAM.GOV.
  7. Indicate whether your firm is a large business or small business. If your firm is a small business specify all applicable socio-economic categories per FAR PART 19.

Interested Small Business Subcontractors should submit the following:


  1. Identify interested areas of work and provide a narrative demonstrating the experience that are similar in size, scope, complexity, and/or magnitude of the work performed.
  2. The size of the crew(s) available to perform work.
  3. Identify applicable socioeconomic category of HUBZone, Women Owned Small Business, Service Disabled Veteran Owned Small Business, or Small Disadvantaged Business
  4. UEI and CAGE CODE, Expiration date in SAM.GOV.

Narratives shall be no longer than two (2) pages.


The following anticipated small business subcontracting goals have been established and are considered reasonable and achievable for the performance of this requirement.  Please advise whether these goals are not achievable. If so, please specify any factors that may prevent from achieving these goals.  


  • 20% of the subcontracted amount with small businesses;
  • 5% with small disadvantaged businesses;
  • 2% with woman-owned small businesses;
  • 3% with HUBZone small businesses;
  • 2% with veteran-owned small businesses;
  • 2% with service-disabled veteran-owned small businesses;

Email responses are required.  Responses are to be sent via email to christie.s.lee@usace.army.mil and jennifer.i.ko@usace.army.mil no later than January 5th, 2026, 2:00 p.m. Hawaii Standard Time.


Responses to this sources sought announcement will be used by the Government to make appropriate acquisition decisions. NO SOLICITATION IS CURRENTLY AVAILABLE.  It is a market research tool being utilized to determine the availability of potential qualified contractors before determining the method of acquisition. Please note that it is required that your company be registered in the System for Award Management (SAM), please see https://www.sam.gov for additional information. In addition, this sources sought is not to be construed as a commitment by the government, nor will the government pay for any information solicited or delivered.

More opportunities from Department Of Defense → W2SN Endist Honolulu

Same awarding agency

NAICS: 236220
New
Federal
FY29 PN108808 Nonorganizational Vehicle Parking Garage at Tripler Army Medical Center on Oahu, Hawaii
Solicitation # W9128A279A001
The U.S. Army Corps of Engineers is seeking a qualified partner for the design and construction of a Nonorganizational Vehicle Parking Garage at Tripler Army Medical Center in Oahu, Hawaii. This project is intended to partially mitigate a parking shortfall of 2,161 spaces and will be executed using a Progressive Design-Build approach under Other Transaction Authority. The scope of work encompasses the full design and construction of the facility, including comprehensive site improvements such as grading, utilities, storm drainage, roadway connections, pedestrian sidewalks, landscaping, and exterior lighting. The resulting facility must be designed for a minimum lifespan of 40 years and adhere to DoD Unified Facilities Criteria regarding energy efficiency, building envelope, and integrated systems performance. The acquisition will utilize a streamlined two-step competitive selection process. In the first step, interested offerors will submit a Statement of Qualifications in the form of a White Paper, from which the government intends to down-select three of the best-qualified offerors. These selected firms will then be invited to provide Pitch Presentations as the final evaluation phase. The resulting agreement will be Firm-Fixed-Price, with costs for successive design and construction milestones agreed upon as the design progresses. The project is divided into two phases: the first focusing on design and pre-construction services, and the second covering final design and construction. An Industry Day is scheduled for November 17, 2026, with a target award date anticipated between April and May 2027.
Commercial and Institutional Building Construction

POSTED

4 days ago

DEADLINE

in 24 days
View Details
NAICS: 531120
Federal
Military Recruiting Lease for office space 5,300 to 5,800 SF required
Solicitation # DACA455270014200
The U.S. Army Corps of Engineers, Honolulu District, is soliciting proposals for a full-service, turnkey lease of 5,300 to 5,800 gross rentable square feet of office space for Armed Forces Recruiting purposes in Honolulu, Hawaii. The required space must be located within a delineated area bounded by River Street to the north, Ward Avenue to the south, Ala Moana Boulevard to the east, and South Vinyard Boulevard to the west. The lease term is four years and eleven months, with the government maintaining termination rights. Key facility requirements include 24-hour unrestricted access, comprehensive communications infrastructure, a secondary exterior exit, and lighted parking for approximately twelve government vehicles, with additional private vehicle parking available within a four-block radius. The award will be based on the best value, weighing price and technical factors, such as location and neighborhood quality, equally. All construction and safety enhancements must be treated as tenant improvements with no government reimbursement. The lessor is responsible for all operating costs, real estate taxes, and insurance, including a public liability limit of at least 1 million dollars. Compliance with ADA/ABAAS accessibility standards and specific seismic safety objectives is mandatory. Interested offerors must be registered in the System for Award Management and submit their electronic proposals to the designated point of contact by November 15, 2026.
Lessors of Nonresidential Buildings (except Miniwarehouses)

POSTED

14 days ago

DEADLINE

in 25 days
View Details

Find Active Opportunities Like This

Get AI-powered intelligence on the opportunities still open

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS