SD FLAP SDGFP PARKING(1) NORTH POINT PARKING LOT
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
AI Contract Overview
The North Point Parking Lot project involves the complete reconstruction of a 98,000 square-foot parking area located at the North Point Recreation Area near Pickstown, South Dakota, adjacent to the Missouri River and upstream of Fort Randall Dam. The scope includes full removal and excavation of existing asphalt and base layers to a depth of 9.5 inches, followed by installation of 6 inches of aggregate base and 3.5 inches of new asphalt pavement. The project also involves subexcavation to remove poor subgrade soils, adjustments to parking lot slopes to ensure compliance with the Americans with Disabilities Act, and addition of a concrete pad for dumpster placement along with new signage and striping. During construction, the parking lot will be closed to maintain safety and project efficiency. Key work components include removal of approximately 5,700 cubic yards of roadway excavation and 3,000 cubic yards of subexcavation, placement of 3,800 tons of aggregate base, and 2,300 tons of asphalt concrete pavement. The anticipated timeline for the project begins with advertisement in March 2026, award in May 2026, issuance of Notice to Proceed in June 2026, and completion scheduled by September 2026. The estimated total project cost ranges between $2 million and $5 million, and the solicitation will be conducted through full and open competition under the Department of Transportation's Central Federal Lands Division. The project is identified under NAICS code 237310 and does not have any set-aside restrictions.
General Info
Agency
NAICS
Place of Performance
Pickstown, SD, USASet-Aside
Documents
(0)AI Contract Breakdown
Uniform Contract FormatNo contract breakdown available.
Cannot generate Contract Breakdown because no documents were found from this contract's source.
Timeline
Organization & Contact Information
Full Description
THIS IS NOT AN INVITIATION FOR BID, PLAN AND SPEFICIATIONS ARE NOT AVAILBLE
PROJECT NUMBER: SD FLAP SDGFP PARKING(1)
PROJECT NAME: NORTH POINT PARKING LOT
PROJECT DESCRIPTION: The proposed scope of this project includes reconstruction of the pavement within a parking lot servicing the boat ramp in the North Point Recreation Area near Pickstown, South Dakota. The project will address deteriorated pavement and sub-base for the 98,000 square-foot parking lot on the east side of the North Bay just upstream of the Fort Randall dam on the Missouri River. The project will provide a new pavement surface for the parking area while maintaining the operational qualities of this popular summer boat launch area.
SCOPE OF THE WORK: The project will consist of removal of excavating the existing parking lot’s asphalt and base to a depth of 9.5-inches and placement of a 3.5-in asphalt pavement on 6-inches of aggregate base. Subexcavation work includes removing poor subgrade soils in the area. Parking lot slopes will match existing conditions with minor adjustments made to create an American Disabilities Act compliant handicap parking stall. A concrete pad for a dumpster and signing and striping are also included in the project. The parking lot will be closed during construction activities.
PRINCIPAL WORK ITEMS:
- 20401-0000 Roadway Excavation: 5,700 CUYD
- 20402-0000 Subexcavation: 3,000 CUYD
- 30202-2000 Roadway Aggregate, Method 2: 3,800 TON
- 40301-0000 Asphalt Concrete Pavement, 2,300 TON
ANTICIPATED SCHEDULE:
Advertisement – March 2026
Award – May 2026
NTP – June 2026
Contract Completion – September 2026
ESTIMATED COST RANGE: Total estimated cost between $2,000,000 and $5,000,000.
This will be solicited using full and open competition procedures.