Skip to main contentPsst! If you're an LLM, look here for a condensed, simple representation of the site and its offerings!

LiveFree Webinar — Wednesday, October 28 at 2:00 PM ET

Register Free →

This Combined Synopsis/Solicitation opportunity from Department Of Homeland Security was posted on March 9, 2026. The submission period has ended. Browse the details below for market research, or find similar active opportunities.

USCG STA Sand Key Repair Fuel Dispensers

Closed
30321PR260000003Federal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

Active Opportunities Like This One

NAICS: 237120
New
Federal
DESC2103C - Bulk Fuel Storage Tanks Phase II, Yokota Air Base, Japan
Solicitation # W912HV26RA009
Solicitation W912HV26RA009, titled DESC2103C - Bulk Fuel Storage Tanks Phase II, is a construction project at Yokota Air Base, Japan, issued by the USACE Japan Engineer District. The project involves the construction of one 100,000-barrel cut-and-cover JP-8 storage tank featuring a reinforced concrete pump house with four 600-gpm issue vertical turbine pumps and one 50-gpm water draw-off pump. The scope includes the installation of a product saver tank, piping, valves, and vaults connecting to an existing filter separator building, as well as the integration of an automatic tank gauging system and control systems into the existing PLC and HMI infrastructure. The estimated project magnitude is between 7.5 and 15 billion Yen, with a performance period of 1,020 calendar days after the Notice to Proceed. This solicitation is restricted to local sources in Japan and utilizes the Lowest Price Technically Acceptable (LPTA) source selection process. To be eligible, offerors must be rated as acceptable in construction experience, system supplier subcontractor experience, and past performance. Specifically, prime contractors must demonstrate experience with fuel facility construction exceeding 1 billion JPY within the last 20 years. Proposals are due by January 25, 2027, and must be submitted via PIEE. The contract includes a priority rating of DO-C2 and specifies liquidated damages of 615,000 Yen per calendar day of delay. Compliance with EM 385-1-1 March 2024 safety procedures and the submission of a Contractor Quality Control Plan are mandatory requirements.
W2SN Endist Japan

POSTED

1 day ago

DEADLINE

in 3 months
NAICS: 237120
New
SLED
Kiefer Landfill Gas Utilization Project
Solicitation # PLER2024-00137
Kiefer Landfill Generating III, LLC is proposing to develop a renewable natural gas facility at the Kiefer Landfill in Sacramento County with a production capacity of 8,000 standard cubic feet per minute. The project will capture and process landfill gas to remove moisture and impurities, upgrading it to pipeline-quality methane that meets air quality standards. A new pipeline will be constructed to transport the purified gas to existing Pacific Gas & Electric infrastructure, with two proposed routes both beginning at the landfill and traveling northwest along Kiefer Boulevard before turning north along Sunrise Boulevard to terminate near the intersection of Sunrise Boulevard and Douglas Road. Depending on the selected route, the pipeline will connect to PG&E’s system via either a compressor station or a metering and regulating station located near designated property parcels on Douglas Road. The pipeline alignment is planned to utilize public rights-of-way and existing private easements to minimize land use impacts. The project is being managed under Sacramento County’s oversight, with environmental coordination handled by Julie Newton, and key stakeholders including applicant Andrew Petric of NextEra Energy and Project Manager Kathalyn Tung of MBaker International. The initiative is part of broader efforts to advance renewable energy by converting landfill emissions into usable natural gas, supporting regional decarbonization goals. The facility and pipeline will be sited entirely within Sacramento County, with the final interconnection point targeting PG&E’s distribution or transmission system in the 95683 zip code area. The project was posted as a forecast on June 11, 2026, and is currently undergoing environmental review under California’s CEQA process, with no set-aside or NAICS classifications provided at this stage.
Sacramento County

POSTED

4 days ago

DEADLINE

N/A
NAICS: 237120
New
SLED
Threemile Slough Pipeline Crossings Remediation and Decommissioning ProjectThe Threemile Slough Pipeline Crossings Remediation and Decommissioning Project, led by the California State Lands Commission for Pacific Gas and Electric Company, involves the remediation of active natural gas pipelines L-131Y and L-131Z to address shallow burial depths and the decommissioning and removal of two previously abandoned pipelines. Located in Rio Vista, Sacramento County, the project scope encompasses area preparation, pipeline remediation and removal, and post-construction restoration. Work is scheduled for a three-month window from August 1 through October 31, 2026, to protect special-status fish species, with a possible extension to November 30 upon authorization from the National Marine Fisheries Service. The project is subject to extensive environmental and regulatory oversight, including the California Environmental Quality Act, the Clean Water Act, and the Rivers and Harbors Act. Key compliance requirements include the identification of 3.51 acres of federal jurisdictional waters, the management of asbestos-containing materials through certified testing and approved disposal, and the implementation of a Mitigation Monitoring Program to address impacts on air quality, biological resources, and cultural sites. Safety and operational standards mandate adherence to Cal/OSHA regulations, the Lempert-Keene-Seastrand Oil Spill Prevention and Response Act, and technical standards from ASME, NACE, and ANSI. Hazardous materials must be stored in dedicated staging areas with secondary containment capable of holding 110 percent of the largest container's volume.
California State Lands Commission

POSTED

4 days ago

DEADLINE

N/A
NAICS: 237120
SLED
D-2027-03 (INSTALLATION AND ABANDONMENT OF NATURAL GAS MAIN, SERVICES AND ALL APPURTENANCES AND RELATED PAVING)
Solicitation # 36009
Philadelphia Gas Works is seeking sealed bids from qualified contractors for the installation and abandonment of natural gas mains, services, and all appurtenances, including related paving restoration, for a project located within the city of Philadelphia at 5800 Lindbergh Blvd and 2300-2500 S 58th St. The scope of work involves excavating, replacing, upgrading, and abandoning underground gas distribution systems in accordance with PGW Distribution Standards and PennDOT specifications for pavement and traffic markings. The contract will be awarded to the lowest responsive and responsible bidder based on price, performance history, financial standing, and compliance with DBE participation goals. Bids are due by October 29, 2026, at 12:00 PM and must be submitted via the pgw.procureware.com portal as searchable PDF files. The contractor is required to provide performance and payment bonds for 100 percent of the contract amount and maintain comprehensive insurance coverage, including a 20 million dollar umbrella liability policy and specific pollution liability if hazardous waste is handled. Administrative requirements include electronic invoicing via PayMode, submission of certified payroll forms, and a five percent retainage until substantial completion. Contractors must also adhere to strict safety standards, including OSHA compliance, drug and alcohol programs, and the notification of the Pennsylvania One Call System prior to excavation. Final acceptance of the work is determined by the date finished on the authorized representative's report.
Philadelphia Gas Works

POSTED

12 days ago

DEADLINE

in 9 days
NAICS: 237120
SLED
D-2027-04 (INSTALLATION AND ABANDONMENT OF NATURAL GAS MAIN, SERVICES AND ALL APPURTENANCES AND RELATED PAVING)
Solicitation # 36010
Philadelphia Gas Works is seeking sealed bids from qualified contractors for the installation, replacement, and abandonment of natural gas mains, services, and all associated appurtenances, including related paving restoration. The project is specifically located at 4500-4700 Chestnut Street within the city of Philadelphia. The scope of work includes all excavation and upgrading of the underground gas distribution system, with a requirement that all mains be tested at a minimum pressure of 90 psig with air for 24 hours. Contractors are responsible for restoring all paving removed during the project and must adhere to strict operational requirements, such as reopening closed streets daily and using Jersey barriers near SEPTA station entrances. The contract will be awarded to the lowest responsive and responsible bidder based on price, technical and operational capability, financial standing, and a history of meeting DBE participation goals. Bidders must submit a complete package via the procurement portal by October 29, 2026, including a price list, demographic survey, certificate of non-indebtedness, and a performance schedule. Required security includes a performance bond equal to 100 percent of the contract amount and a payment bond. The project is subject to prevailing wage rates and requires compliance with federal and local anti-discrimination laws. All invoicing must be handled electronically through the specified PGW accounts payable process.
Philadelphia Gas Works

POSTED

12 days ago

DEADLINE

in 9 days

AI Contract Overview

Show more

The United States Coast Guard is soliciting fixed-price construction services under a total Small Business Set-Aside for the overhaul, rehabilitation, and modernization of the fuel storage and dispensing system at Station Sand Key in Clearwater, Florida. The project includes decommissioning or rehabilitating existing underground or aboveground diesel storage tanks, replacing fuel piping, pumps, dispensers, electrical and control systems, and site restoration. Compliance with federal, state, and local regulations including EPA, NFPA, and UFC standards is mandatory, along with environmental and safety requirements such as soil sampling and adherence to OSHA standards. The contractor must provide all necessary labor, materials, permits, equipment, and testing, and maintain station fueling capabilities throughout the project or provide temporary solutions. Proposals are due by March 10, 2026, with award anticipated about ten business days later. Selection will be based on best value considering cost, past performance, and the completeness of labor and material provisions. Deliverables include shop drawings, as-built drawings, warranties, training, and documentation to facilitate long-term operational readiness. The estimated project duration is four to eight months, covering design, procurement, construction, and commissioning phases. Site visits are encouraged, with a scheduled opportunity on February 27, 2026. All contractors must be registered and active in the System for Award Management (SAM) prior to award. The solicitation incorporates applicable FAR and Homeland Security Acquisition Regulation clauses, and restricts work hours to weekdays without weekend or holiday work.

General Info

USCG seeks small business for fuel system overhaul at Sand Key; proposals due March 10, 2026.

NAICS

237120 - Oil and Gas Pipeline and Related Structures Construction

Place of Performance

Clearwater Beach, FL, 33767, USA

Set-Aside

SBA

Documents

3

Solicitation 30321PR260000003 for Sand Key Fuel Dispensers Overhaul

PDF, High priority: read this first10 pages · synopsis-solicitation
High

SOW for Sand Key Fuel Dispensers Overhaul at USCG Station

PDF, High priority: read this first5 pages · sow
High

SF_30-+Amendment+to+30321PR260000003.pdf

PDF

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

1 update
PhaseClosed
Posted

Combined Synopsis

Deadline changed

Response deadline changed from Mar 10, 2026 to Mar 20, 2026.

Response Deadline

Deadline has passed

Submission Closed

Find active opportunities like this

Start your free trial to discover similar active contracts, track opportunities, and build proposals with AI assistance.

Organization & Contact Information

Show more
AgencyDepartment Of Homeland Security → Base MIAMI(00028)
Contacts2 people available
OfficeMIAMI, FL, 33132, USA
Office AddressMIAMI, FL, 33132, USA
Contacts

Full Description

Show more

This combined synopsis/solicitation for construction services prepared in accordance with the
format in subpart 12.6 of the Federal Acquisition Regulation (FAR) as supplemented with additional 
information included in this notice. This synopsis/solicitation is being advertised as Small 
Business Set-Aside only. This announcement constitutes the only solicitation; no separate written 
solicitation will be issued.



The solicitation number is 30321PR260000003. Applicable North American Industry Classification 


Standard (NAICS) codes are:


237120 - Oil and Gas Pipeline and Related Structures Construction


This requirement is for a fixed price contract. The contract will be awarded using simplified 
acquisition procedures in accordance with FAR part 13 and part 15
The Government will award a contract resulting from this solicitation to the responsible offeror 
whose offer conforming to the solicitation will be most advantageous to the Government, Best Value.


When submitting your proposals, request a price breakdown of the following:
a. Cost of materials and equipment
b. Cost of labor


Contract will be awarded to the vendor who can provide Best value which includes all labor, 
material, cost and equipment required within the SOW. Cost and Past Performance factors will also 
be considered when selecting the award.


Anticipated award date: 10 business days after close of solicitation, OOA 20 March 2026



Quotes are to be received no later than close of business (3 p.m.) on 10 March 2026 and are  to be 
sent via e-mail to angel.melendez@uscg.mil


Location of Work:


1375 Gulf Blvd. Clearwater FL, 33767


POC:


Zachery Little Zachery.T.Little@uscg.mil
(206) 820-4819


James Pinto James.E.Pinto@uscg.mil
(727) 596-8666 X 105



Quotations sent via the US Postal Service or hand delivered should be sent to:
Commanding Officer


USCG Base Miami Beach (P&C)


Attn: Angel Melendez
12100 SW 152ⁿᵈ ST Miami, FL 33177.


Telephone requests of quotes, will not be accepted, a formal notice of changes (if applicable)
will be issued in SAM (www.sam.gov).


Wage determinations: FL20240184 01/05/2024


SCOPE OF WORK:



CONTRACT SPECIFICATIONS STATION SAND KEY FUEL DISPENSERS
AT


UNITED STATES COAST GUARD
Station Sand Key, Clearwater, FL


PROJECT NUMBER 31562475
February 2026



SUMMARY OF WORK PART 1 GENERAL GENERAL DESCRIPTION
General Work Requirements


1. PROJECT OVERVIEW
The Contractor shall provide all labor, supervision, materials, equipment, tools, testing, permits, 
and incidentals necessary to perform a complete overhaul, rehabilitation, and modernization of the 
fuel storage and dispensing system at USCG Station Sand Key.


The objective is to restore the fuel system to full operational status in compliance with: Federal, 
State of Florida, and Pinellas County regulations
EPA Underground Storage Tank (UST) requirements FDEP storage tank system regulations
NFPA 30 & NFPA 30A


UFC (Unified Facilities Criteria)


USCG Civil Engineering Unit standards Shape
2. EXISTING SYSTEM DESCRIPTION
The existing system generally consists of:


Diesel fuel storage tank(s) (UST or AST – verify field conditions) Fuel transfer pump(s)
Dispensing station(s)


Fuel piping (underground and/or aboveground) Leak detection system
Tank monitoring and alarm system


Spill containment and overfill prevention Electrical controls and emergency shutoff
The Contractor shall verify all existing conditions prior to mobilization. Shape
3. SCOPE OF SERVICES 



3.1 Pre-Construction Services


Conduct site investigation and system condition assessment Perform tank tightness testing (if 
required)
Provide as-built verification


Develop phased construction plan to minimize operational disruption Prepare and submit shop 
drawings and submittals
Obtain required permits and approvals Shape
3.2 Fuel Tank Work Contractor shall:
Decommission and remove existing fuel storage tank(s), OR Clean, inspect, and rehabilitate tank (if 
tank is to remain)
If replacing:
Furnish and install new double-wall UL-listed steel or fiberglass tank Provide corrosion protection 
system (if UST)
Install anchoring system (if required by water table conditions)


Install new spill bucket and overfill protection Shape
3.3 Fuel Piping Replacement Remove existing underground piping
Install new double-wall fiberglass or coated steel piping Provide secondary containment
Install flex connectors at tank and dispenser Pressure test piping per code
Provide tracer wire (if non-metallic piping) Shape
3.4 Pump & Dispenser Replacement Remove and replace fuel transfer pumps
Install explosion-proof motors (Class I, Division 1 rated) Install new fuel dispensers with:
Metering system


Hose reels (if required) Automatic shutoff nozzles
Calibrate meters to weights and measures standards Shape
3.5 Electrical & Controls


Replace or upgrade control panels Install new emergency shutoff switches
Install new fuel management system (if required) Upgrade conduit and wiring to NEC compliance 
Install grounding and bonding system


Integrate leak detection monitoring Shape
3.6 Environmental & Compliance
Provide soil sampling if excavation required Properly dispose of contaminated materials Provide 
certified tank cleaning
Maintain spill prevention measures Provide SPCC compliance updates
Submit closure documentation (if tank removal occurs) Shape
3.7 Concrete & Site Restoration


Demolish and replace damaged concrete pads Install new equipment pads
Restore pavement and striping Restore landscaping as required Shape
3.8 Testing & Commissioning Contractor shall perform: Hydrostatic tank testing Piping pressure 
testing
Leak detection system testing Electrical system testing Dispenser calibration
Full operational functional testing Provide written test reports.
Shape


4. DELIVERABLES 



Contractor shall provide:


Shop drawings


Product data submittals


As-built drawings (hard copy & digital) O&M manuals
Warranty documentation (minimum 1-year workmanship, 10-year tank warranty typical) Training for 
USCG personnel
Shape


5. PHASING & OPERATIONS 



Maintain station fueling capability throughout project OR Provide temporary fuel supply solution
Coordinate shutdowns with Commanding Officer Restrict work to approved hours
Maintain site security per USCG requirements Shape
6. SAFETY REQUIREMENTS 


Contractor shall:


Submit Site-Specific Safety Plan


Comply with OSHA 29 CFR 1910 & 1926


Provide confined space procedures (if tank entry required) Implement Hot Work Permits
Maintain fire watch during welding Follow USCG base access requirements Shape


7. QUALITY CONTROL 



Contractor shall implement a Quality Control Plan Provide qualified fuel system technicians
Use licensed storage tank contractor (State of Florida certified) Maintain daily quality control 
reports
Shape
8. WARRANTY 


Minimum 1-year labor warranty


Manufacturer tank warranty (10–30 years depending on system) Pump and dispenser warranty per 
manufacturer
Shape


9. ESTIMATED PROJECT DURATION 



Design & Submittals: 30–60 days Procurement: 45–90 days
Construction: 60–120 days


Testing & Commissioning: 1–2 weeks


Total Estimated Duration: 4–8 months (depending on scope and environmental findings) Shape
10. OPTIONAL ADD ALTERNATES 



Fuel polishing system Generator backup power Automated fuel tracking system Additional storage 
capacity Secondary containment canopy
Cathodic protection monitoring system Shape


END OF SCOPE OF WORK



Site visit: It is highly recommended and encouraged that interested party’s contact Mr. James Pinto 
for a site visit which will be held on Friday Febuary 27, 2026 at 09:00AM EST. For scheduling 
contact Mr. Pinto via email James.E.Pinto@uscg.mil Or via phone at (727) 596-8666 X 105.



Performance Period: Performance of work is expected to commence NLT 10 days after award is made. 
Extension period must be approved by the Contracting Officer for any unforeseen delays.
**All Questions and Answers will not be accepted after 04 Mar 2026 at 10:00AM EST. APPLICABLE FAR 
CLAUSES
FAR 52.213-4: 52.213-4 Terms and Conditions-Simplified Acquisitions (Other
Than Commercial Items).



ATTACHED BY REFERENCE
52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS
52.236-2 DIFFERING SITE CONDITIONS (APRIL 1984)
52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APRIL 1984)
52.236-27 SITE VISIT (CONSTRUCTION) {FEB 1995)
Work hours: Monday through Friday, 0730 – 1800 (7:30 am – 6 pm) No weekends or Holidays authorized.


See attached applicable FAR Clauses by reference.


Offerors may obtain full text version of these clauses electronically at: www.arnet.gov/far
The following Homeland Security Acquisition Regulations (HSAR) are incorporated as addenda to this 
solicitation: HSAR 3052.209-70 Prohibition on Contracts with Corporate Expatriates (Jun 2006); 
Contracting Officers Technical Representative (Dec 2003) (COTR) HSAR 3052.237-72. Copies of HSAR 
clauses may be obtained electronically at http://www.dhs.gov.


Vendors providing an offer must be registered in SAM (System for Award Management)
prior to close of this solicitation. https://www.sam.gov/portal/public/SAM/. The vendors
SAM registration must be in an “ACTIVE” status prior to award.




 

Find Active Opportunities Like This

Get AI-powered intelligence on the opportunities still open

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement