This Government Contract opportunity from Department Of Transportation was posted on April 16, 2015. The submission period has ended. Browse the details below for market research, or find similar active opportunities.

WA NPS MORA 14(8), Nisqually to Paradise, Phase II Utilities

Awarded
DTFH70-14-B-00016Federal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

Active Opportunities Like This One

NAICS: 237130
New
SLED
Installation of Buried Fiber Optic Cable Stanton North Substation to Hoskins Substation
Solicitation # 26085
The Nebraska Public Power District is soliciting bids for Request for Bid No. 26085 to install approximately six miles of underground fiber optic cable between the Stanton North and Hoskins Substations in northeast Nebraska. The scope of work encompasses all labor, materials, and supervision required for staking, material coordination, property owner contacts, and right-of-way restoration. Specifically, the contractor will install 48-strand buried fiber optic cable provided by the contractor and 48-strand all-dielectric fiber provided by the District. The project must adhere to RUS Form 515a and IEEE Standard 1333-1994 for guided boring. Work is expected to be awarded by November 25, 2026, with a final completion deadline of April 15, 2027. Bids are due by November 13, 2026, and must include a completed pricing spreadsheet and current all-inclusive equipment and labor rates. Evaluation factors for the award include quoted price, conformance with specifications, past schedule performance, and the bidder's financial responsibility and experience. To qualify, bidders must certify the completion of at least three similar buried fiber optic installation projects within the last five years. Payment terms specify that 95 percent of the price is paid within 30 days of acceptable performance, with 5 percent retained until final acceptance. An optional pre-bid teleconference is scheduled for November 5, 2026, to review contract specifications.
Nebraska Public Power District

POSTED

about 7 hours ago

DEADLINE

in 15 days
NAICS: 237130
New
Federal
B21 Utilities & Site Improvements, Communications & Electrical Infrastructure, Dyess AFB OT Feasibility & Business Feedback
Solicitation # W9126G27R1CSY
The U.S. Army Corps of Engineers, Fort Worth District, is conducting market research via a Sources Sought notice for the B-21 Utilities and Site Improvements project at Dyess Air Force Base, Texas. This initiative aims to establish high-reliability primary electrical power distribution and dedicated fiber-optic communications infrastructure to support the bed-down of the B-21 weapons system. The scope includes the installation of single-mode fiber optic cables, telephone system expansion, power cabling in concrete encased ducts, pole-mounted conductors, and associated transformers and switchgear. The project also encompasses site improvements such as earthwork, grading, and erosion control. The estimated Construction Cost Limitation is $28,550,000, though an $8 million electric substation and specific end-user network equipment are expressly excluded from this contract. The government is currently evaluating whether to utilize a traditional Federal Acquisition Regulation based contract or an Other Transaction Agreement under 10 U.S.C. section 2808a. If a collaborative procurement framework is chosen, a two-phase selection process will be implemented, focusing first on technical capability, past performance, and collaborative execution history, followed by an evaluation of final technical and price proposals. The project must adhere to strict Department of Defense standards, including UFC 1-200-01 for general building requirements, UFC 4-010-01 for antiterrorism, and UFC 4-010-06 for cybersecurity of facility-related control systems. The anticipated period of performance is 690 calendar days from the notice to proceed, with a required beneficial occupancy date of March 8, 2030.
W076 Endist Ft Worth

POSTED

about 8 hours ago

DEADLINE

in 14 days
NAICS: 237130
New
SLED
De Palma Road Electrical Conduit Installation Project
Solicitation # TLARC-819
The County of Riverside is soliciting bids for the De Palma Road Electrical Conduit Installation Project (Project No. D4-0072) located in the Community of Horsethief Canyon, California. The project involves the excavation and backfill of approximately 1,000 feet of trenching, the installation of 685 feet of 1.5-inch and 350 feet of 3-inch electrical conduit and handholes, and the installation of 6-inch Type D concrete curb per County Standard No. 204. All work must adhere to Southern California Edison plans and be completed within 30 working days from the commencement date specified in the County's written order. The estimated project cost is 209,000 dollars. The contract will be awarded to the lowest responsive and responsible bidder. Bidders must submit their proposals by December 2, 2026, at 1:30 P.M. Pacific Time, including a non-collusion declaration and a bid guarantee of 10 percent of the total bid. The awarded contractor must provide performance and payment bonds, comply with California State Labor Code prevailing wage requirements, and adhere to specific affirmative action plans based on contract value and employee count. Payments will be made monthly, with the Owner paying 90 percent of the value of labor and materials incorporated into the work and 75 percent of materials stored on site, subject to certification by the Architect.
COUNTY OF RIVERSIDE

POSTED

about 13 hours ago

DEADLINE

in about 1 month
NAICS: 237130
New
SLED
Installation Of Street Lighting On Raymond Avenue From Maple Street To North City Limits
Solicitation # 2026-IFB-CIV-0549
The City of Pasadena Department of Public Works is soliciting bids under solicitation number 2026-IFB-CIV-0549 for the installation of a new street lighting system on Raymond Avenue, extending from Maple Street to the North City Limits. The project requires the contractor to furnish and install concrete street lighting standards, foundations, LED luminaires and fixtures, conduits, conductors, pull boxes, and other appurtenant work. Key technical deliverables include 29W or 50W LED replacements, galvanized steel conduits, and 6 foot Type S Scroll Arms. The contractor must provide all necessary labor, materials, and equipment, ensuring compliance with the ADA, CBC, Title 24, and PROWAG accessibility guidelines. Bids must be submitted electronically via the City of Pasadena eProcurement Portal by 2:00 pm on November 17, 2026. Qualified bidders must provide evidence of experience with two similar governmental projects and submit several mandatory documents, including Form AA-1, Form AA-2 for labor exceeding 25,000 dollars, a non-collusion declaration, and a DHS contract disclosure. A bid security of five percent of the total bid price is required, and the successful awardee must provide material and faithful performance bonds for 100 percent of the base bid. Work must commence within 15 calendar days of the Notice to Proceed and be completed within 20 working days. Invoicing is handled through the city's Vendor Invoice Portal, with payments issued on Tuesdays and Thursdays.
City of Pasadena Department of Public Works

POSTED

about 13 hours ago

DEADLINE

in 19 days
NAICS: 237130
New
SLED
115kV Transmission Line 1266 Rebuild Stanton North Substation to Dead-End Structure 79
Solicitation # 26-012
Nebraska Public Power District is soliciting sealed bids for Contract No. 26-012 to rebuild approximately 4.05 miles of the 115kV transmission line 1266, extending from the Stanton North substation to Dead-End Structure 79. The scope of work requires the contractor to provide all labor, supervision, equipment, and miscellaneous materials to replace all structures, conductors, shield wires, and hardware. Key technical deliverables include the installation of 28 wood H-Frame tangent structures and one tubular steel monopole dead-end on a drilled pier, upgrading the conductor to 954 kcmil 45/7 ASCR Rail, and installing 0.551 diameter fiber optic ground wire and EHS steel shield wire. The project also involves tree clearing, site preparation, and the removal of existing structures and conductors. Bids are due by 2:00 p.m. CST on December 2, 2026, and must be submitted as sealed hard copies to the Procurement Department in Columbus, Nebraska. The award will be based on the lowest cost and best bid, with evaluation factors including technical conformance, schedule capability, financial standing, and past performance history. Prospective bidders are encouraged to attend an optional pre-bid teleconference and site visit on November 23, 2026. Required submission documents include a signed proposal page, a completed price quotation table, a W-9 form, and bid security in the form of a certified check, irrevocable letter of credit, or bid bond. The successful contractor must provide a performance bond and maintain workers compensation and commercial general liability insurance.
Nebraska Public Power District

POSTED

about 23 hours ago

DEADLINE

in about 1 month

AI Contract Overview

Show more

This contract involves utility work for the "Nisqually to Paradise, Phase II Utilities" project within Mount Rainier National Park in Pierce County, Washington. The scope includes trenching, conduit placement, vault installation, minor drainage work, and installing power lines in conduit along a project length of approximately 6.52 miles. The contract is scheduled for completion by summer 2015 and is estimated to have a price range between $2 million and $3 million. This solicitation is offered under full and open competition without restrictions, and preliminary plans and additional project details are available electronically through registration on the official federal business opportunities website. The contracting agency is the Western Federal Lands Division of the Department of Transportation, located in Vancouver, Washington, with project performance taking place near Ashford, Washington. Interested vendors can register to receive notifications and access documents when the solicitation is officially posted. The Department of Transportation also highlights a financing option through its Short-Term Lending Program for eligible small businesses, including disadvantaged business enterprises, certified small firms, and service-disabled veteran-owned businesses, although this contract is not reserved exclusively for these groups. The program offers lines of credit up to $750,000 to assist with working capital needs related to transportation contracts.

General Info

Utility work including trenching and power line installation in Mount Rainier, $2-3M, completion summer 2015.

Contract Value

$2,767,185.92

NAICS

237130 - Power and Communication Line and Related Structures Construction

Place of Performance

12 Miles East, ASHFORD, WA, USA

Set-Aside

NONE

Award Issued Date

Documents

4

NPS MORA 14(8) - Nisqually to Paradise Phase II Utilities Preliminary Plans

PDF, High priority: read this firstspecifications
High

Preliminary Utility Plans, Nisqually to Paradise Phase II

PDF, High priority: read this firstspecifications
High

WA NPS MORA 14(8) - Nisqually to Paradise Phase II Utilities

PDF, High priority: read this firstsow
High

DTFH70-14-B-00016 - Nisqually to Paradise Phase II Utilities Notice

PDF, Low prioritypresolicitation
Low

AI Contract Breakdown

Uniform Contract Format

Contract not broken down yet

CLEATUS splits the solicitation into Uniform Contract Format (UCF) sections: scope, pricing, deliverables, and evaluation criteria.

Timeline

4 updates
PhaseAwarded
Posted

Presolicitation

Notice updated

The notice description changed.

Deadline changed

Response deadline added: Mar 26, 2015.

Notice updated

Notice details unchanged. Attachments may have changed.

Notice updated

Notice details unchanged. Attachments may have changed.

Type Changed

Presolicitation → Solicitation

Awarded

Contract was awarded

Submission Closed

Find active opportunities like this

Get full access to discover similar active contracts, track opportunities, and build proposals with AI assistance.

Organization & Contact Information

Show more
AgencyDepartment Of Transportation → 690567 Western Federal Lands Division
Contacts1 person available
OfficeVANCOUVER, WA, 98661, USA
Office AddressVANCOUVER, WA, 98661, USA
Contacts
Contracts G. OfficeWestern Federal Lands Highway Division

Full Description

Show more
************** 3/20/15 - Contractors that have already requested a physical data CD, with be sent a new CD with the physical data added by A003. ************** WA NPS MORA 14(8), Nisqually to Paradise, Phase II Utilities, Mount Rainier National Park, Pierce County, Washington The work consists of trenching, conduit placement, vault installation, minor drainage, installing power line in conduit and other small items of work. Project length: 6.52 Miles Tentative Fixed Completion Date: Summer 2015 (Once solicitation is issued, see FAR Clause 52.211-10 for exact date.) Estimated Price Range: $2 million to $3 million To view the INTERESTE VENDERS LIST you must register as an FBO user. Go to https://www.fbo.gov/. Scroll down to the "Venders/Citizens" box. Click on "Register Now" and follow the directions. THIS SOLICITATION IS OFFERED FOR FULL AND OPEN COMPETITION ON AN UNRESTRICTED BASIS PRELIMINARY PLANS and a letter with additional project information are in electronic format only and are posted with this synopsis. Registering at ADD TO WATCHLIST box insures notification when solicitation documents are posted. When solicitation documents are issued, the INVITATION FOR BIDS/REQUEST FOR PROPOSAL (specifications and plans) will be posted at this link. This paragraph announces possible financing available to small businesses. The three types of businesses that are eligible to receive a loan through this program are: (1) Firms that have received DBE certification from a state or local transportation agency; (2) Eligible small business firms; and (3) Firms that have received a disability rating by the Veteran's Administration and have certified themselves as a SDVOSB. Start-up businesses are not eligible to receive a STLP line of credit and should contact the SBA for information about other possible forms of financial assistance. (NOTE - This paragraph does not reserve this solicitation for these types of business): The Department of Transportation's (DOT) Short-Term Lending Program (STLP) offers working capital financing in the form of lines of credit to finance accounts receivable for transportation related contracts. The Maximum line of credit is $750,000. The STLP loan has a variable rate, which is connected to the prime rate. For more information see: http://www.dot.gov/osdbu/financial-assistance/short-term-lending-program.

More opportunities from Department Of Transportation → 690567 Western Federal Lands Division

Same awarding agency

NAICS: 532490
New
Federal
Modular Buildings & Restroom Rental with Ancillary Services
Solicitation # 69056727Q000005
Solicitation number 69056727Q000005 is a combined synopsis and request for quotation issued by the Department of Transportation's Western Federal Lands Highway Division to support operations during a facility renovation in Vancouver, Washington. The requirement is for the temporary lease of prefabricated modular office buildings, including one double-wide unit of approximately 24 by 60 feet with specific office and conference room configurations, two 8 by 40 foot single-wide modular units with HVAC, and an executive restroom trailer. The scope of work encompasses the entire lifecycle of the installation, including site preparation, delivery, utility connection, weekly septic pumping, preventative maintenance, and eventual demobilization. All units must be ADA compliant and adhere to International Building Code standards for commercial occupancy. This acquisition is unrestricted and open to all qualified vendors under NAICS code 532490. The government will utilize a Lowest Price Technically Acceptable model for the award, evaluating offers based on price, requirement specifications, relevant past experience, and past performance. A 10 percent price preference is available for HUBZone small business concerns. Quotations must be submitted via the GSA eBuy Portal by November 24, 2026, at 2:00 pm PT. Invoicing will be processed through the DELPHI iSupplier system, and the contract incorporates various FAR clauses regarding labor standards, security requirements, and business ethics.
Other Commercial and Industrial Machinery and Equipment Rental and Leasing

POSTED

1 day ago

DEADLINE

in 26 days
View Details
NAICS: 237310
New
Federal
WA NP OLYM 12(8), Hurricane Ridge Rockfall Mitigation MP 9.4
Solicitation # 69056726B000010
Solicitation 69056726B000010 is an Invitation for Bids for the Hurricane Ridge Rockfall Mitigation MP 9.4 project located in Olympic National Park, Clallam County, Washington. This firm fixed-price construction project, managed by the Department of Transportation's Federal Highway Administration Western Federal Lands Division, involves the installation of a rockfall mitigation system approximately 11 miles south of Port Angeles. The scope of work includes the installation of 102 linear feet of Geobrugg RXE-8000 flexible rockfall barrier fence and the treatment of 260 square yards of galvanized steel using Natina Steel weathering agent. Additional requirements include survey and staking, quality control, testing, clearing and grubbing, excavation, and the construction of retaining walls, all adhering to FP-24 standard specifications. The estimated project value ranges between 2 million and 5 million dollars, with a tentative completion date of Fall 2027. This opportunity is a total small business set-aside, and awards will be made to the responsible bidder offering the most advantageous price. Bids must be submitted in sealed envelopes by 1400 local time on November 4, 2026, and must include a valid Standard Form 24 bid bond. Contractors are required to use the Masterworks web-based system for daily reports and measurement notes, and they must comply with specific restrictions prohibiting audio/video recording or AI note-taking during government meetings. The contractor is also responsible for securing all necessary permits for any material sites or sources they identify. Payment will be processed via Electronic Funds Transfer.
Highway, Street, and Bridge Construction

POSTED

1 day ago

DEADLINE

in 6 days
View Details
NAICS: 237310
Federal
WY NP YELL 10(24), Grand Loop Road Norris to Golden Gate, Phase 3
Solicitation # 69056726R000020
The project WY NP YELL 10(24), Grand Loop Road Norris to Golden Gate, Phase 3, is a firm-fixed-price task order contract under a Multiple Award Task Order Contract (MATOC) for the Western Federal Lands Highway Division. Located 0.4 miles southwest of Mammoth, Wyoming, the project involves the reconstruction of a 0.7-mile roadway section and associated parking areas within Yellowstone National Park. The scope of work is comprehensive, including 4R roadway reconstruction, excavation, blasting, rock scaling, embankment, drainage and roadside improvements, retaining wall construction, stone masonry, utility relocation, waterline construction, and the installation of concrete curbs, gutters, striping, and signage. The estimated price range for the project is between 45 million and 55 million dollars, with a tentative completion date set for Fall 2028. The solicitation is structured around two primary bid schedules and one option. Schedule A focuses on mainline construction with a 22-foot typical pavement width and the reconstruction of the Norris Geyser Basin parking lot, while Schedule B specifies a 30-foot typical pavement width for the same areas. Option Z covers grading, base, pavement, major drainage, and the construction of a steel boardwalk at the Rustic Falls Boardwalk and the Osprey Pit Road Box Culvert. Only one of the two schedules will be awarded. The project is solicited to approved MATOC contractors, with the formal request for proposal anticipated in Winter 2026/2027. All work must adhere to the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects for the FP-24 project area.
Highway, Street, and Bridge Construction

POSTED

9 days ago

DEADLINE

N/A
View Details
NAICS: 237310
Federal
ID FLAP KOOTEN 8450(1), Yellowstone Trail Road, Segment 1
Solicitation # 69056726R000019
Solicitation 69056726R000019 is a firm fixed-price task order request for proposals issued by the Federal Highway Administration Western Federal Lands Division for the Yellowstone Trail Road, Segment 1 project in Kootenai County, Idaho. Located in the Coeur d'Alene National Forest, the 0.20-mile project involves roadway realignment and reconstruction, the installation of a new single-span precast prestressed concrete structure, and rock-mass stabilization. The estimated price range for the work is between 2 million and 5 million dollars, with a tentative completion date in Fall 2027 and an assumed notice to proceed date of January 12, 2027. This is a restricted MATOC solicitation, meaning proposals will only be accepted from six specific prime contractors: ASCORP Inc (DBA Debco Construction), Granite Construction, Hamilton Construction, M.A. Deatley Construction, MJ Hughes Construction, and Thompson Contracting. Award will be based on the best value, primarily focusing on the lowest price among responsible offerors. The project must adhere to the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-24) and requires strict compliance with various Federal Acquisition Regulation clauses regarding labor standards, equal opportunity, and material workmanship.
Highway, Street, and Bridge Construction

POSTED

16 days ago

DEADLINE

in 15 days
View Details

Earlier notices in this NAICS code

Posted before this notice, open and closed

Find Active Opportunities Like This

Get AI-powered intelligence on the opportunities still open

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS