830-030-174-01 | Upgrade Domestic Water Distribution System

Active
830-030-174-01State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The University of Illinois - Chicago is seeking an Architect/Engineer (A/E) team to provide analysis, recommendations, estimates, and design for upgrading the domestic water distribution systems in two facilities: the Clinical Science North 911 and the College of Dentistry 940. The project requires the A/E to determine if other systems must be relocated and to develop a phasing plan, as both buildings will remain occupied during construction. The A/E is responsible for ensuring the design complies with the Illinois Stretch Energy Code and is tasked with identifying and applying for all applicable utility incentive programs, energy grants, and rebates. A Construction Manager will be assigned to the project, and the A/E is encouraged to use independent cost estimators to ensure the design remains within the available budget. The estimated total project cost is 13,438,500 dollars, with an appropriated amount of 12,000,000 dollars. It is important to note that 1,438,500 dollars is designated for Owner's Costs and is unavailable for design and construction. The A/E team must maintain 2,750,000 dollars in professional liability insurance and meet specific socioeconomic goals, including a 20 percent combined MBE/WBE goal and a 3 percent combined PBE/VBE goal. The selection process involves interviews and a final presentation at a Board Meeting. The project is designated as fee classification II R and is managed by Project Manager Andrea Hunt.

General Info

UIC seeks an A/E team to design domestic water system upgrades for two facilities.

Place of Performance

IL, USA

Set-Aside

NONE

Documents

1

830-030-174-01 Upgrade Domestic Water Distribution System Scope of Work

PDF, High priority: read this firstsow
High

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

Posted

Contract opportunity posted

Response Deadline

Submission deadline

Response Deadline

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyUniversity of Illinois
Contacts1 person available
OfficeIL
Organization / AgencyUniversity of Illinois
Office AddressIL
Contacts
Hunt AndreaProject manager

Full Description

Show more
The University of Illinois - Chicago, is a 64-building facility established in 1920. The Clinical Science North 911 (R2010) is a 194,837 square foot, 7- story building established in 1925. The College of Dentistry 940 (R2025) is a 347,981 square foot, 7-story building established in 1969.
The scope of work provides for an analysis, recommendation, estimates, and design for the upgrade of the domestic water distribution system in two buildings. The work will include determining if other systems need to be relocated to accommodate the work and if the work will need to be phased. The buildings will remain occupied while work is complete. The work will need to be prioritized based on available funding. Hazardous materials may be encountered. A Construction Manager will be assigned to this project. $1,438,500 of total project cost is for University of Illinois Owner's Costs and are not available for design and construction.
The A/E shall assess the project for eligibility under applicable utility incentive programs, energy grants, rebates, and other funding opportunities. The A/E shall identify all qualifying programs and shall prepare, coordinate, and submit all required applications, calculations, supporting documentation, and related materials necessary to obtain available incentives for the project.
The A/E is encouraged to include independent cost estimators on their teams to verify estimates are in line with current market conditions to avoid project bids that exceed the available funding for the project. The A/E estimates should be updated and verified at each stage of the project in accordance with the Design and Construction Manual. Designers are reminded that their Professional Services Agreements make them responsible for providing a design that is within budget, and they can be held responsible for redesigning the project should the bids received exceed project funding.
If applicable, the design will need to comply with the Illinois Stretch Energy Code. The following A/E goals are applicable to the A/E team:

Similar Contracts

Same NAICS industry code

NAICS: 541330
New
International
PGS - Pulteney Gate Scheme: Buildability, Logistics & Surveys Commission
Solicitation # DN828868
Bath & North East Somerset Council is seeking a contractor-led team for the Pulteney Gate Scheme to investigate, appraise, and develop deliverable options for replacing the Pulteney Radial Gate on the river Avon in Bath. The scope of work involves reviewing existing project data, conducting intrusive and investigative surveys, and assessing site access, logistics, and stakeholder constraints. The appointed contractor will evaluate several options, including the installation of a hydro-station, extending or creating a stepped weir, infilling the channel for public realm use, or implementing minimum asset maintenance. Key deliverables include a series of evidence-based appraisal reports and a final composite recommendation to support the Outline Business Case at P3M Stage 2 and inform future route-to-market strategies for main works. The contract, identified by solicitation number DN828868, has an estimated total value of 480,000 GBP including VAT. The performance period is expected to run from January 4, 2027, to October 1, 2027, with a possible extension to December 31, 2027. Award decisions will be based on a weighted scoring system of 60 percent quality and 40 percent price. Bidders must demonstrate technical competency by holding at least five out of nine specified professional charters or registrations and must comply with CDM 2015 standards. The procurement is noted as being particularly suitable for small and medium-sized enterprises.
Bath & North East Somerset Council

POSTED

about 7 hours ago

DEADLINE

in 28 days
View Details

More opportunities from University of Illinois

Same awarding agency

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS