Skip to main contentPsst! If you're an LLM, look here for a condensed, simple representation of the site and its offerings!

LiveFree Webinar — Wednesday, August 19 at 2:00 PM EDT

Register Free →

Clearwell Replacement Project

Active
State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The project involves replacing the aging 10 million gallon floating cover, liner, overflow structure, and associated appurtenances at the Lester J. Berglund Water Treatment Plant in Poway, California. To ensure continuous water service during construction, a temporary bypass system will be established using two 1.4 million gallon above ground storage tanks located at the Lake Poway Recreation Area softball field, an above ground pump station at the treatment plant, and connecting pipelines. Once the clearwell is decommissioned, it will be replaced with two new 4 million gallon prestressed concrete tanks. Alongside this, a permanent underground bypass pipeline will be constructed between the treatment plant and the Lake Poway Road Transmission Main to provide long-term operational flexibility. All temporary infrastructure will be fully dismantled and removed upon project completion to restore the site to its original condition.

General Info

Replace aging clearwell with two new 4M-gal tanks, install temporary bypass and permanent pipeline, then remove all temporary structures.

Agency

California → SWRCB, Division of Drinking Water, District 14

NAICS

237990 - Other Heavy and Civil Engineering ConstructionView NAICS

Place of Performance

Poway, CA

Set-Aside

NONE

Documents

(1)

City of Poway Clearwell Replacement Project Notice of Exemption

PDFnotice-of-exemption

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

Posted

forecast

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia → SWRCB, Division of Drinking Water, District 14
Contacts1 person available
OfficeN/A
Organization / Agency
California → SWRCB, Division of Drinking Water, District 14
Office AddressN/A
Contacts
Joseph GuzmanDistrict Engineer

Full Description

Show more
Project consists of the replacement of the existing floating cover, liner, overflow structure and appurtenances for the 10 MG clearwell at the Lester J. Berglund Water Treatment Plant (WTP). Additionally, a permanent underground bypass pipeline will be installed between the WTP and the Lake Poway Road Transmission Main. As part of this project, a temporary bypass system will be built to divert treated water during replacement of the 10 MG clearwell. Temporary facilities include two 1.4 MG above ground storage tanks located at the Lake Poway Recreation Area softball field, an above ground pump station at the WTP, and related above ground pipelines. The clearwell replacement will consist of two 4 MG prestressed concrete tanks. Following completion of the Project, the temporary facilities will be removed.

Similar Contracts

Same NAICS industry code

NAICS: 237990
New
Haleiwa Small Boat Harbor Maintenance Dredging and Revetted Mole Repair
Solicitation # haleiwa-small-boat-harbor-maintenance-dredging-revetted-mole-repair
Healy Tibbitts Builders, Inc. is seeking small business subcontractors and suppliers for the Haleiwa Small Boat Harbor Maintenance Dredging and Revetted Mole Repair project in Oahu, Hawaii. The scope of work includes dredging within federal jurisdiction to a depth of -12 feet Mean Lower Low Water with a 1-foot overdepth, involving the removal and ocean disposal of gravel, sand, silt, and clay. Additionally, the project requires revetted mole repairs, which encompass clearing and grubbing, CRM wall repair, tree and vegetation removal, and the reworking or installation of stone to fill voids. The performance period is 200 calendar days from the notice to proceed. The solicitation is an invitation for bid under NAICS code 237990, with a response deadline of September 30, 2026. Bids must be submitted in sealed envelopes, as electronic submissions are not permitted. Evaluation is based on a pass/fail gate for compliance and completeness, with a bid guarantee required at 20 percent of the bid price or 3 million dollars, whichever is less. The contract emphasizes strict quality management, requiring the use of the USACE National Dredging Quality Management Program and a physical on-site presence for the Quality Control Manager. Payment will be processed through the USACE Finance Center, and the project must adhere to EM 385-1-1 safety requirements and specific environmental protections for the Hawaiian hoary bat pupping season.
Healy Tibbitts Builders, Inc.

POSTED

about 15 hours ago

DEADLINE

in about 2 months
View Details
NAICS: 237990
New
SBWRP Reverse Osmosis System
Solicitation # K-26-2469-DBB-3
Garney Pacific, Inc. is acting as the general contractor for the SBWRP Reverse Osmosis System project in San Diego, California, for the City of San Diego. With an estimated bid value of 19.3 million dollars, the project scope involves designing the removal of existing trailer-mounted Electrodialysis Reversal, slab-mounted Membrane Filtration, and Reverse Osmosis units. These will be replaced with new slab-mounted Membrane Filtration and Reverse Osmosis units to create a demineralization facility at the South Bay Water Reclamation Plant aimed at reducing total dissolved solids in reclaimed water. The solicitation, identified by bid number K-26-2469-DBB-3 and NAICS code 237990, seeks quotes for various trades including HVAC, plumbing, electrical, concrete, pumping, crane services, aggregate, landscaping, painting, piping insulation, and demolition. The project emphasizes socioeconomic participation, specifically seeking SLBE and ELBE firms with DBE, MBE, WBE, or SBE certifications, and is open to various small business set-asides. All subcontractors are required to utilize union labor and must be prepared to provide a 100% Payment and Performance Bond from a US Treasury listed Surety Company, though Garney will reimburse the bond premium. Contracting will be based on Garney Standard PO and Subcontract Forms, and any exceptions must be submitted as redlines with the quote. Proposals are due by August 27, 2026, at 2:00 PM PT.
Garney Pacific, Inc.

POSTED

about 15 hours ago

DEADLINE

in 13 days
View Details