Communication Vault Replacement - Temporary Fiber Installation Project At Saddleback College

Active
20260722079State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The project entails the replacement of a communication vault and the installation of temporary fiber optic cabling at Saddleback College in Mission Viejo, California, with all work performed under the California Uniform Public Construction Cost Accounting Act (CUPCCAA). Essential tasks include excavation, vault placement, conduit installation, and fiber optic cabling, with the critical stipulation that all Air Blown Fiber (ABF) removal and installation must be executed exclusively by a Sumitomo-certified installer. Contractors must hold a valid California B-General Contractor or C-10 Electrical license and be registered with the California Department of Industrial Relations (DIR); all subcontractors are subject to the same DIR registration requirement. Prevailing wage rates mandated by the DIR apply to all laborers, and compliance is non-negotiable. Bidders must submit a bid security equal to 10% of their proposed bid amount via cash, certified check, or bid bond, and proposals must be submitted electronically through the PlanetBids portal by the September 3, 2026, deadline. Attendance at one of the two mandatory pre-bid conferences is required, and failure to attend will result in bid rejection. Substitution requests for materials must be submitted in writing and received by August 13, 2026, through the PlanetBids portal, with responses posted exclusively there. The award will follow the Lowest Price Technically Acceptable (LPTA) method, selecting only responsive and responsible bidders with the lowest compliant base bid, with no trade-offs permitted among technical or price factors. The contract does not include options, renewals, or security clearance requirements, and no federal FAR clauses are incorporated; instead, state-specific provisions govern procurement and performance. All pertinent documents—including the bid bond form, prevailing wage scale, and project map—are accessible only through the PlanetBids portal, and payment, invoicing, and accounting details are not specified beyond general agency contact information.

General Info

Replace communication vault and install temporary fiber at Saddleback College using Sumitomo-certified installer by September 3, 2026.

Agency

California → South Orange County Community College DistrictView Agency

NAICS

237130 - Power and Communication Line and Related Structures ConstructionView NAICS

Place of Performance

Mission Viejo, CA, USA

Set-Aside

NONE

Documents

(1)

Bid 15057-2026 Communication Vault Replacement - Temporary Fiber Installation Project

PDFifb

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

PhaseSolicitation
Posted

Solicitation

Response Deadline

Submission deadline

Response Deadline

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia → South Orange County Community College District
Contacts1 person available
OfficeN/A
Organization / Agency
California → South Orange County Community College District
View Agency Profile
Office AddressN/A

Full Description

Show more
Bid #15057-2026: The project involves the replacement of a communication vault and the installation of temporary fiber optic cabling at Saddleback College. The scope includes all necessary excavation, vault placement, conduit work, and fiber installation. A critical requirement is that the Air Blown Fiber (ABF) removal and installation portion of the work must be performed by a Sumitomo-certified installer. The project is being bid under the California Uniform Public Construction Cost Accounting Act (CUPCCAA) procedures.

Similar Contracts

Same NAICS industry code

NAICS: 237130
New
Federal
Feeder 7 Repair
Solicitation # W50S8526BA007
The U.S. Air Force, through the W7NF Uspfo Activity Miang 127, is preparing to issue an Invitation for Bids under solicitation number W50S85-26-B-A007 for the construction of Electrical Repair Feeder 7 at Selfridge Air National Guard Base in Michigan. This is a firm fixed-price contract entirely set aside for small businesses under FAR 19.5, with the NAICS code 237130 for Power and Communication Line and Related Structures, and a size standard of $45 million. The project requires the contractor to furnish all plant, labor, transportation, materials, tools, equipment, appliances, and supervision necessary to complete approximately 5,706 feet of new underground and overhead conductors, demolition of existing cables, full-depth pavement repairs, mill/overlay, crack repairs, and associated site restoration work along Perimeter Road and Jefferson Ave. All work must strictly adhere to Drawings VGLZ262005 Repair Feeder #7, the Statement of Work, and project specifications, with any conflicts resolved in favor of the more stringent or higher-quality requirement. A Macomb County Soil Erosion Permit is mandatory and the responsibility of the contractor to obtain and pay for. The contract period is 240 calendar days from notice to proceed, inclusive of inspection and punch list items. The solicitation is being issued under FAR Part 14 procedures, with award determined solely on price and price-related factors. The prime contractor must comply with limitations on subcontracting, prohibiting payments exceeding 85 percent of the contract value (excluding materials) to non-similarly situated subcontractors under FAR clause 52.219-14(e)(3) with deviation 2021-O0008. All bidders must be registered in SAM.gov, and inquiries must be submitted in writing via email to TSgt Jack Garrettson. The formal solicitation is tentatively scheduled for release on July 13, 2026, with a pre-bid conference on July 22, 2026, and bid opening anticipated on or about August 31, 2026. The estimated contract value ranges between $1 million and $5 million, with the final amount to be determined upon bid submission.
W7NF Uspfo Activity Miang 127

POSTED

1 day ago

DEADLINE

in 23 days
View Details
NAICS: 237130
New
Federal
Request for Information - Sentinel Utility Infrastructure, Malmstrom Air Force Base, MT
Solicitation # W912DW26S1CE0
The U.S. Army Corps of Engineers, Seattle District, is issuing this Request for Information to gather market intelligence for the Sentinel Utility Infrastructure Project at Malmstrom Air Force Base, Montana. This critical enabling project supports the modernization of the land-based intercontinental ballistic missile force by constructing a comprehensive utilities distribution system, including electrical distribution and substation expansion, water and wastewater systems, natural gas service, and a fiber-optic telecommunications backbone. The scope also includes associated site work such as grading, drainage, and access paving. The project is estimated to cost between 160 million and 200 million dollars with an anticipated period of performance of approximately 1,278 calendar days. Because this infrastructure is on the critical path for the overall Sentinel beddown, any schedule delays will impact all subsequent facility construction. The government intends to utilize Other Transaction Authority under 10 U.S.C. section 2808a, meaning the agreement will not be subject to the Federal Acquisition Regulation or standard small-business set-aside rules. The proposed acquisition strategy employs a Construction Management at Risk approach divided into two phases: a preconstruction collaborative phase for constructability reviews and cost development, followed by an at-risk construction phase based on a negotiated Guaranteed Maximum Price. Design is nearly complete and is being managed by Jacobs Engineering, who will remain the Designer of Record. Interested parties must respond via an online questionnaire and may submit a supplemental capabilities statement of no more than five pages to Kyla Couch by 10:00 AM Pacific Time on August 28, 2026. Selection will be based on a trade-off process evaluating qualifications, past performance, proposed approach, commercial terms, and price.
W071 Endist Seattle

POSTED

2 days ago

DEADLINE

in 12 days
View Details

More opportunities from California → South Orange County Community College District

Same awarding agency

NAICS: 238210
SLED
Saddleback College Stadium Improvements Project
Solicitation # 15049-2026
The Saddleback College Stadium Improvements Project encompasses a wide range of exterior and interior upgrades aimed at enhancing safety, functionality, and aesthetics at the college’s stadium facility in Mission Viejo, California. Key elements include the installation of under-bleacher fencing and gates, new lighting systems, screening at Ticket Booth AHU locations, reorientation of a pole-mounted play clock, and the addition of gate and access controls to the Emergency Vehicle Access Road. Acoustical treatments will be applied to scoreboard speakers, with new fencing added at specified gaps, while safety netting in Thrower’s Park will be removed and replaced. Protective padding will be installed at light poles and utility boxes, and new potable water hose bibs will be added to visitor bleachers. Landscaping and irrigation systems will be newly installed, along with motorized projection screens in Team Rooms and carpeting in Officials Rooms. An interior window in the Press Box will be converted to a pass-thru, and corner guards will be added throughout. AV components for the scoreboard and field audio system will be integrated to ensure synchronized operation. The project also includes allowances for unforeseen underground conditions, conflicts with as-built conditions, and technology improvements, each set at $30,000, $30,000, and $10,000 respectively, with additional optional work available through two additive alternates: decorative bollards and IT infrastructure, both priced as lump sums. The solicitation is managed by the South Orange County Community College District under bid number 15049-2026, with responses due by September 3, 2026, and an estimated 120-day performance period beginning upon issuance of the Notice to Proceed. Submissions must be organized into three bound volumes containing contact directories, operation and maintenance instructions, and project certifications, all submitted electronically as PDFs with accompanying paper copies. Bidders must hold a valid California contractor’s license and be registered with the Department of Industrial Relations, and are required to submit certifications confirming compliance with workers’ compensation insurance, a drug-free workplace, no gift policies, and non-collusion. Key personnel, including a full-time superintendent and project manager with minimum five years of relevant experience, must be designated and remain on-site throughout construction. Substitutions require formal approval with technical documentation submitted within 14 days of bid release. Inspection and acceptance occur on-site, governed by California Building Code requirements and standardized material testing criteria from ASTM and other industry benchmarks. The award
Electrical Contractors and Other Wiring Installation Contractors

POSTED

23 days ago

DEADLINE

in 18 days
View Details