Replace Waterline, Barrigada to Harmon

Forecast
Federal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

This project, managed by Navfac Marianas for the Department of the Navy, involves the replacement of existing asbestos-cement pipe water supply transmission lines running from the Harmon Booster pump Station to the Barrigada Reservoir. The scope of work requires the removal and disposal of approximately 10,662 linear feet of 12-inch diameter and 4,000 linear feet of 14-inch diameter pipe, which will be replaced with new heat fused joint Polyvinyl Chloride pipe of similar diameters. Installation includes necessary fittings, gate valves, meters, metering vaults, manholes, thrust blocks, backfill, and compaction. Comprehensive site work is required, including clearing, cutting, trenching, and excavation, as well as the full restoration of roadways, asphalt pavement, Portland cement concrete, and subgrade materials. To ensure uninterrupted water supply services throughout the construction process, the contractor may be required to install a temporary water transmission line. This forecast is categorized under NAICS code 237110 for water and sewer line construction.

General Info

Navfac Marianas project replacing asbestos-cement water pipes with PVC from Harmon to Barrigada.

NAICS

237110 - Water and Sewer Line and Related Structures Construction

Place of Performance

USA

Set-Aside

NONE

Documents

0

No documents available

Documents will appear here when they are available.

AI Contract Breakdown

Uniform Contract Format

No documents to break down

The breakdown needs solicitation documents. None were found from this contract's source.

Timeline

PhaseForecast
Posted

forecast

Prepare for this forecast

Research the agency, track this forecast, and prepare your capture plan before the solicitation opens.

Organization & Contact Information

Show more
AgencyDepartment Of The Navy → Navfac Marianas
ContactsNo contacts available
OfficeN/A
Office AddressN/A
ContactsNo contact information available

Full Description

Show more
This project is to replace existing asbestos-cement pipe(ACP) water supply pipe transmission line from Harmon Booster pump Station to Barrigada Reservoir. Work will include removal, disposal, and replacement of 12-inch diameter (approximately 10,662 LF) and 14-inch diameter (approximately 4,000 LF) ACP with new 12 to 14 inch diameter inch heat fused joint Polyvinyl Chloride (PVC) pipe, associated fittings, gate valves, meter, metering vaults, manholes, thrust blocks, taping backfill and compaction. The project includes and but not limited to clearing, cutting, trenching, excavation, removal, disposal and restoration of roadway including asphalt pavement, Portland cement concrete, base course, sub base and sub grade. Water supply service shall remain active during construction of the replacement and maybe accomplished by installing a temporary water transmission line.

Similar Contracts

Same NAICS industry code

NAICS: 237110
New
Morgans Branch Force Main and Pump Station Improvements
Solicitation # SRP-W-134-0290
The Morgans Branch Force Main and Pump Station Improvements project for the City of Belmont, North Carolina, involves the construction of 16,435 linear feet of new 20-inch ductile iron force main and significant upgrades to the Morgans Branch Pumping Station. The scope of work includes installing a new wet well and valve vault with associated appurtenances, as well as the demolition of existing pumps and piping. The project has an estimated value of 16,690,000 dollars and a performance period of 560 calendar days following the issuance of a Notice to Proceed. The contract is administered using EJCDC standard forms and will be awarded to the responsible bidder submitting the lowest responsive bid. Key requirements for bidders include the submission of bid security, evidence of authority to sign, and specific M/WBE compliance documentation, including a Good Faith Efforts Form and Table A. Participation goals are set at 10.9 percent for MBE and 10.4 percent for WBE per EPA guidelines, with a combined state goal of 10 percent. The contractor must provide performance and payment bonds, maintain insurance from providers with an A.M. Best rating of A-VII or better, and adhere to OSHA fall protection and various technical standards, including AWS D1.2 for welding and NEMA MG1 for motors. Payment will be processed in equal monthly amounts via EJCDC C-620 applications, with a 200,000 dollar contingency allowance available for authorized additional work.
Don Moorhead Construction, Inc.

POSTED

about 6 hours ago

DEADLINE

in about 19 hours
View Details
NAICS: 237110
New
Jefferson St. Pump Station Replacement
Solicitation # ITB-2026141
The City of Winchester is soliciting bids for the Jefferson Street Pump Station Replacement project in Virginia under solicitation ITB-2026141. The scope of work includes the construction of a new pump station featuring a precast concrete building, controls, and a standby generator, as well as site electrical work, yard piping, security fencing, grading, and paving. Additionally, the project requires the relocation of an existing fuel tank and the demolition of existing facilities. All work must be completed within 610 calendar days following the Notice to Proceed, with adherence to VDOT 2020 Road and Bridge Specifications and the City of Winchester Standards Manual. WG Construction is seeking MBE/WBE subcontractor participation for paving, material supply, site development, fencing, MEP, roofing, and carpentry. Bids are due by 2:00 pm on November 12, 2026, via the City's e-Procurement Portal. The contract will be awarded to the lowest responsive and responsible bidder based on qualifications, compliance, and pricing. Requirements include a 5 percent bid guarantee, performance and payment bonds equal to 100 percent of the contract amount, and compliance with Davis-Bacon wage determinations and OSHA safety standards. Bidders must provide a minimum of three similar project references and confirm they are not on any government debarment lists.
WG Construction Co., Inc.

POSTED

about 6 hours ago

DEADLINE

in about 19 hours
View Details

More opportunities from Department Of The Navy → Navfac Marianas

Same awarding agency

Prepare for this forecast

Research this forecast and prepare for the solicitation

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS