UM - WW - REPLACE WWTP SUBNATANT PIPING

Forecast
Federal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

This project, managed by Navfac Hawaii for the Department of the Navy, involves the critical replacement of a severely corroded 8-inch subnatant force main. The scope of work requires the trenching and installation of approximately 140 feet of new HDPE force main extending from the Dissolved Air Flotation Tanks System Subnatant Wetwell Pump Station to the Influent Channel of the Anoxic/Aeration Tanks. Technical requirements include connecting the new line to existing subnatant pumps and coring through the influent channel wall to secure the pipe end. The urgency of this construction is driven by the failure of the existing infrastructure, which has suffered multiple breaks and resulting spills reported to the State Department of Health over the past nine months. Classified under NAICS code 237110, this forecast outlines the necessary infrastructure upgrades to prevent further environmental contamination and restore system reliability.

General Info

Navfac Hawaii will replace 140 feet of corroded HDPE force main for Navy.

NAICS

237110 - Water and Sewer Line and Related Structures Construction

Place of Performance

USA

Set-Aside

NONE

Documents

0

No documents available

Documents will appear here when they are available.

AI Contract Breakdown

Uniform Contract Format

No documents to break down

The breakdown needs solicitation documents. None were found from this contract's source.

Timeline

PhaseForecast
Posted

forecast

Prepare for this forecast

Research the agency, track this forecast, and prepare your capture plan before the solicitation opens.

Organization & Contact Information

Show more
AgencyDepartment Of The Navy → Navfac Hawaii
ContactsNo contacts available
OfficeN/A
Office AddressN/A
ContactsNo contact information available

Full Description

Show more
Scope involves constructing a replacement 8-inch subnatant force main from the Disolved Air Flotation Tanks System Subnatant Wetwell Pump Station to the Influent Channel of the Anoxic/Aeration Tanks. Work will include trenching and installing approximately 140 feet of new HDPE force main, connecting the force main to the existing subnatant pumps, and coring a hole through the wall of the influent channel and affixing the new pipe end in place. The existing force main is severely corroded and has recently (within the last nine months) broken several times; each time, a spill is recorded and reported to the State Department of Health.

Similar Contracts

Same NAICS industry code

NAICS: 237110
New
26350 Lynchburg, VA - CSO 70 Sewer Improvements
Solicitation # 2027-027
Cleary Construction is soliciting quotations from certified Disadvantaged Business Enterprises for the City of Lynchburg CSO 70 Sewer Improvements project in Virginia, identified by solicitation number 2027-027. This opportunity is open to various small business set-asides, including Veteran Owned, Service-Disabled Veteran Owned, Women-Owned, and HUBZone certified firms. Interested parties must submit their responses by December 4, 2026. The scope of work involves comprehensive sewer infrastructure improvements, including the open-cut installation of PVC and Ductile Iron Pipe ranging from 6 to 30 inches in diameter, as well as 24-inch diameter trenchless crossings with associated launch and receiving shafts. Additional requirements include the installation of standard and doghouse manholes, drop assemblies, and a CSO regulator fit out. Site preparation tasks consist of clearing and grubbing over 5,100 square yards of wooded areas, seeding, fine grading, and the implementation of a Stormwater Pollution Prevention Plan. Key operational deliverables include the maintenance of flows and bypass for all pipes and manholes during construction, geotechnical instrumentation and monitoring, and the procurement of railroad insurance. The project also involves various abandonment tasks for existing pipes and manholes and extra depth excavation. Point of contact for this solicitation is John Connelly.
Cleary Construction, Inc.

POSTED

about 3 hours ago

DEADLINE

in 24 days
View Details

More opportunities from Department Of The Navy → Navfac Hawaii

Same awarding agency

Prepare for this forecast

Research this forecast and prepare for the solicitation

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement