*UPDATE - Bean Ridge Tower Remediation - RFI / Responses and ADDITIONAL PHOTOS
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
Active Opportunities Like This One
General Info
Contract Value
$28,208Place of Performance
Thebes, IL, 62990, USASet-Aside
Awardee
BRANAT CONSTRUCTION LLCAward Issued Date
Timeline
Submission Closed
Organization & Contact Information
Full Description
UPDATE (2) Two - RFIs / Responses and ADDITIONAL PHOTOS - 6973GH-26-R-00074.
- SOW Requirement 2.b, Repairs, bullet 5 states: Install new security wire on the perimeter fence of the compound.
- Can the Government confirm that torque arm assemblies are the preferred solution to this requirement? If not, please confirm if 3-runs of barbed wire across the top of the fence is an acceptable solution?
- Replace existing barbed wire at the top of the compound fence with new barbed wire. Picture of existing attached.
- Can the Government confirm that torque arm assemblies are the preferred solution to this requirement? If not, please confirm if 3-runs of barbed wire across the top of the fence is an acceptable solution?
- SOW Requirement 2.e, Site Specific Requirements, bullet 1 states: Installation of four guy wire bracket assemblies on tower.
- Question: Can the Government provide additional information on the current brackets such as make/model or provide a product cut sheet?
- No brackets are currently installed, and guy wires are wrapped around the tower leg. The requirement is for four new Rohn 55 guy bracket assemblies to be installed. Picture of existing guy attachment attached.
- Question: Can the Government provide additional information on the current brackets such as make/model or provide a product cut sheet?
- SOW Requirement 2.e, bullet 5 states: Remove and trim excess transmission line as required and re-terminate the line.
- Question: Are the current connectors re-usable?
- No
- If not, can the Government provide the current connector brand model and connector type?
- The connector brand model and type is not currently available.
- Question: Are the current connectors re-usable?
UPDATE (1) One - ADDITIONAL PHOTOS 6973GH-26-R-00074.
The purpose of this update is to respond to an Request for Information (RFI) for Pre-Bid Site Walk-thru and additional site photos.
- There will not be an opportunity for a pre bid site walk-thru.
- Additional site photos are hereby provided as attatchment "Bean Ridge Photo Deck. 2".
All other terms and conditions remain in full force and effect.
----------------------------------------------------------------------------------------------------------------------------------------------------------------
The scope of this contract includes the implementation of guy system tensioning, installation of guy wire bracket assemblies, tower lightning protection, corrosion abatement, and any minor repairs necessary to properly tension the designated USFS communication tower. All work shall conform to applicable industry standards relevant to the specific tower structure identified.
The selected contractor is responsible for furnishing all labor, tools, equipment, materials, and technical expertise necessary to complete the tasks.
More opportunities from Department Of Transportation → 6973GH Franchise Acquisition Svcs
Same awarding agency
Earlier notices in this NAICS code
Posted before this notice, open and closed
Find Active Opportunities Like This
Get AI-powered intelligence on the opportunities still open
Every page of the solicitation package shredded into a compliance breakdown
AI-powered matching based on your capabilities and past performance
Competitor and incumbent history on the requirement
Automated alerts on amendments, Q&A deadlines, and award
Join 750+ contractors already using CLEATUS