LOCK AND DAM 25 NEW 1,200 FT LOCK NAVIGATION AND ECOSYSTEM SUSTAINABILITY PROGRAM (NESP)
Open
W912P926RA004Federal
Response Deadline
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
AI Contract Overview
Show more
The U.S. Army Corps of Engineers, St. Louis District, is soliciting proposals for the design, construction, and commissioning of a new 1,200-foot drilled-shaft founded lock chamber at Lock and Dam 25 in Winfield, Missouri, as part of the Navigation and Ecosystem Sustainability Program. The project scope includes the construction of an upstream ported guard wall, a downstream guard wall, and various site development features such as access routes and staging areas. Once operational, the new lock will allow the existing 600-foot lock to serve as an auxiliary chamber for recreational traffic or emergency use. This is a full and open competition for a firm-fixed-price contract with economic price adjustments based on the Producer Price Index for commodities like steel and concrete.
The contract is structured with a base period of 1,825 calendar days and four optional periods of 365 days each. Award will be based on a best-value tradeoff evaluation considering five factors: past performance, construction approach, river and intermediate wall means and methods, small business participation, and price. Offerors must meet a minimum 25 percent small business participation target and submit proposals electronically via the Procurement Integrated Enterprise Environment by December 9, 2026. Key requirements include the submission of a Project Labor Agreement, adherence to strict cybersecurity protocols for control systems, and the use of specific brand-name instrumentation and automation components to ensure system compatibility.
General Info
US Army Corps design and build 1,200-foot lock chamber at Lock and Dam 25.
Lock and Dam 25 Site, 10 Sandy Slough Road, Winfield, Missouri 63389, MO, 63389
Set-Aside
NONE
Documents
52
PDF
PDF, High priority: read this first243 pages · amendment
HighAI Summary for Amendment 0003 - 1200ft Lock Specifications (Section 00 08 00): Amendment 0003 provides the 'Special Contract Requirements' (Section 00 08 00) for the 1200ft Lock project. It details critical operational requirements including work areas, public utility management, damage to work protocols, quantity survey requirements, and mandatory electronic submission of Davis-Bacon certified payrolls.
PDF
PDF, High priority: read this firstq-and-a
HighAI Summary for Amendment 0003 - Bidder Inquiries and Government Responses - NESP Lock 25: This document contains a report of bidder inquiries and official government responses for the NESP Lock 25 project (W912P9-26-R-A004). Dated August 2026, it provides clarifications on pricing schedules for wall monoliths, painting requirements for embedded metals, cybersecurity protocols for PLC programming, and geotechnical sampling and licensing requirements. The document notes that official amendments will be issued to reflect certain corrections to drawings and specifications.
PDF
PDF, High priority: read this first6 pages · amendment
HighAI Summary for Amendment 0003 - Economic Price Adjustment Clause: Amendment 0003 for the NESP LD25 New 1200ft Lock project, incorporating a detailed Economic Price Adjustment (EPA) clause. The document establishes a mechanism for annual price adjustments based on the Producer Price Index (PPI) for commodities such as steel, aggregate, and concrete, provided the change is at least 5%. It includes specific PPI indices (WPU1017, WPU132, WPU1321), guidelines for retrospective adjustments, and a unit price table for the price proposal.
PDF
PDF, High priority: read this firstamendment
HighAI Summary for Amendment 0003 - Plan Set: Amendment 0003 to the plan set dated 2026-10-05. The document contains technical specifications, including sheet keynotes for staging and disposal areas, material schedules for structural components (ASTM A709 and A36), bolt specifications, and general notes for floor plans and interior construction.
PDF
PDF, High priority: read this first15 pages · amendment
HighAI Summary for Amendment 0003 Pricing Schedule - Base and Options: Amendment 0003 provides a detailed pricing schedule for a construction project involving river wall monoliths and lock modifications. It includes a Base Schedule and Option 1 and 2 Schedules, listing specific CLINs for materials (cement, steel, etc.), labor, and specialized tasks such as drilled shafts, sheet piling, and concrete placement.
PDF
PDF, High priority: read this first470 pages · amendment
HighAI Summary for Amendment 0004 - 1200ft Lock Specifications: This document is Amendment 0004, providing updated specifications for the 1200ft Lock project. It includes Section 00 08 00 (Special Contract Requirements), detailing work areas, public utilities, damage to work, quantity surveys, and electronic submission of Davis-Bacon certified payrolls. It also outlines requirements for partnering, VECP implementation, and design liability.
PDF
PDF, High priority: read this firstq-and-a
HighAI Summary for Amendment 0004 - Bidder Inquiries and Government Responses - NESP Lock 25 Review: This document contains a report of 468 bidder inquiries and corresponding government responses for the NESP Lock 25 Review project (W912P9-26-R-A004). It provides critical technical clarifications regarding pricing schedules for wall monoliths, painting requirements for embedded metals, cybersecurity protocols for PLC programming, and detailed geotechnical specifications for drilling, sampling, and core preservation. The responses indicate that several of these clarifications will be formalized in upcoming official amendments.
PDF
PDF, High priority: read this first617 pages · specifications
HighAI Summary for Amendment 0004 - Geotechnical Data Set - Lock and Dam No. 25: This document is Amendment 0004, providing a Geotechnical Data Set dated October 2026 for the Engineering and Design phase of the New 1200 ft Lock at Lock and Dam No. 25 on the Mississippi River in Winfield, MO. It contains critical technical data including boring logs (historical 1969-1997, 300/400 series, 2022 overwater, and 2024 land borings), rock profiles, soil and rock legends, and rock testing UCC data tables.
PDF
PDF, High priority: read this firstamendment
HighAI Summary for Amendment 0004 - Plan Set: Amendment 0004 dated 2026-10-19 providing updated plan sets and drawing titles. The document includes detailed lists of sheets for downturn metal gate assemblies, components, and machinery platform fixtures (sheets 28-SSH03 through 29-SH41A).
PDF
PDF, High priority: read this first16 pages · amendment
HighAI Summary for Amendment 0004 Pricing Schedule - Base and Options: This document is Amendment 0004, providing a detailed Pricing Schedule for a construction project. It includes a Base Schedule and Option 1 Schedule, featuring line items for site preparation, materials (cement, fly ash, steel), soil stabilization, monolith construction, electrical work, and roadway improvements. It specifies estimated quantities and units for bidding purposes.
PDF
PDF, High priority: read this firstamendment
HighAI Summary for Amendment 0006 - 1200ft Lock Specifications (Section 00 08 00): This document is Amendment 0006, providing updated technical specifications for the 1200ft Lock project. Specifically, it details Section 00 08 00 'Special Contract Requirements,' covering work areas, public utilities, damage to work, quantity surveys, and electronic submission of Davis-Bacon certified payrolls.
PDF
PDF, High priority: read this firstq-and-a
HighAI Summary for Amendment 0006 - Bidder Inquiries and Government Responses (NESP Lock 25): This document is a Bid Inquiry Contractor Report for the NESP Lock 25 project (W912P9-26-R-A004). It contains a series of bidder inquiries and official government responses regarding technical specifications, including pricing schedules for wall monoliths, painting requirements for embedded metals, cybersecurity protocols for PLC programming, and geotechnical sampling and preservation requirements. The document serves as a formal clarification of the solicitation requirements.
PDF
PDF, High priority: read this firstamendment
HighAI Summary for Amendment 0006 Pricing Schedule: This document is Amendment 0006, providing a detailed Pricing Schedule for a construction project. It includes a Base Schedule and Option 1 Schedule, listing specific line items for materials (cement, steel, sheet pile), labor (drilled shafts, concrete placement), and specialized services (soil stabilization, permeation grouting) with estimated quantities and units.
PDF
PDF, High priority: read this firstamendment
HighAI Summary for Amendment 0006 - Section 00 21 16 Proposal Submission Requirements: This document is Amendment 0006, specifically Section 00 21 16, which outlines the proposal submission requirements for a construction project. It details the required proposal volumes (Technical, Small Business Participation, and Price), page limitations for each factor, formatting specifications (margins, font, and file type), and mandatory cover sheet information. It specifies that submissions must be made electronically via the Procurement Integrated Enterprise Environment (PIEE).
PDF
PDF, High priority: read this first4 pages · sow
HighAI Summary for Appendix D - Small Business Participation Commitment Document (Sample): Sample format for a Small Business Participation Commitment Document, identified as Section 00 21 16 Appendix D. It requires all offerors, both large and small businesses, to submit proposed small business participation percentages, prime offeror size/category, subcategory participation by socioeconomic type, principal supplies/services by small business category, and the extent of commitment to use small businesses. The document also notes that other-than-U.S. small business offerors must separately submit a subcontracting plan under FAR 52.219-9 and applicable DFARS clauses.
PDF
PDF, High priority: read this first4 pages · sow
HighAI Summary for Appendix D - Small Business Participation Commitment Document (Sample): Sample format for a Small Business Participation Commitment Document used in source selection. It explains how offerors should report small business participation, including prime offeror size/status, total percentage of work by large and small businesses, participation by small business category, principal supplies/services, and the extent of commitment. It also notes that other-than-U.S. small business offerors must submit a separate subcontracting plan under FAR 52.219-9 and related DFARS clauses.
PDF
PDF, High priority: read this first5 pages · checklist
HighAI Summary for DoD Checklist for Reviewing Subcontracting Plans (Sept 2019): DoD Checklist for Reviewing Subcontracting Plans, Sept. 2019, Version 5 (DFARS PGI 219.7). This appendix provides a review checklist for subcontracting plans, listing required plan elements and compliance questions tied to FAR 52.219-9 and DFARS 219.705-4. It covers goals for small business categories, subcontracting methods, indirect costs, program administration, subcontracting opportunities, required clauses, reporting assurances, and eSRS/SF 294 reporting requirements. Used to evaluate whether an offeror’s subcontracting plan is complete and compliant.
PDF
PDF, High priority: read this first13 pages · pricing-schedule
HighAI Summary for DRAFT Pricing Schedule - Base and 4 Options: Draft pricing schedule for a procurement covering a base schedule and multiple option schedules. It lists item numbers, descriptions, estimated quantities, units, unit prices, and extended amounts for construction-related work such as bonds, mobilization, site preparation, monolith work, electrical/mechanical systems, roadway improvements, and option-priced materials and services. The document includes Base Schedule, Option 1, and Option 2 pricing sections with totals and appears to be part of the bid/price proposal package.
PDF
PDF, High priority: read this first33 pages · wage-determination
HighAI Summary for IL20260017 Wage Determination - Heavy and Highway: General Decision Number IL20260017, published 05/18/2026, for Illinois heavy and highway construction. This wage determination covers multiple counties in Illinois and includes modification numbers 3 (01/30/2026) and 4 (05/18/2026). The document lists prevailing wage rates and fringe benefits for construction trades such as carpenters, pile drivers, electricians, and line construction classifications by county and locality.
PDF
PDF, High priority: read this first7 pages · justification-and-authorization
HighAI Summary for J&A Brand Name Specific Requirement - NESP L25 New 1200ft Lock: Justification and Approval (J&A) for a brand name specific requirement tied to the NESP L25 New 1200ft Lock project in Winfield, MO, prepared by the USACE St. Louis District. The document cites 10 U.S.C. 2304(c)(1) and FAR 6.302-1 for a brand name/only-one-source rationale covering Durham GeoSlope Indicator, Geokon, and Campbell Scientific instrumentation and automated data acquisition components. It explains the need for compatibility with existing systems, staff training, software integration, and cost avoidance versus alternative manufacturers, and includes a cost analysis discussion for the procurement.
PDF
PDF, High priority: read this first9 pages · justification-and-approval
HighAI Summary for J&A for Brand Name Specific Requirement – NESP L25 New 1200FT Lock: Justification and Approval (J&A) for a brand name specific requirement for Rockwell Automation/Allen-Bradley PLC, SCADA, HMI, switch, power supply, and software components for the NESP L25 New 1200ft Lock project at Winfield, MO. Dated for USACE St. Louis District procurement, it cites FAR 6.302-1 and 10 U.S.C. 2304(c)(1) to support limited competition/sole-source justification based on compatibility with existing lock and dam control systems, standardization, reduced downtime, and training/commonality benefits.
PDF
PDF, High priority: read this first14 pages · pricing-schedule
HighAI Summary for Lock 25 Pricing Schedule and Notes: Pricing schedule for Lock 25 work, listing base schedule, Option 1, and Option 2 line items with estimated quantities, units, unit price, and extended amount blanks. Includes major construction and materials items such as bonds, mobilization, data management, concrete, sheet pile, drilled shafts, reinforcement, grouting, instrumentation, electrical/mechanical embedded items, roadway improvements, and lock commissioning. This document appears to be a bid/price schedule tied to a construction procurement.
PDF
PDF, High priority: read this first2 pages · rfi
HighAI Summary for Lock and Dam 25 Market Research Questions for Option 4 FPIS: Market research document for Lock and Dam 25 focused on whether Option 4 should be structured as a fixed-price incentive successive targets (FPIS) arrangement instead of firm-fixed-price. It states that the base and Options 1-3 are assumed firm-fixed-price, and requests industry feedback on competition, pricing, risk allocation, administrative burden, and whether an incentive structure would improve cost, schedule, and delivery outcomes. The document includes draft questions on interest and competition, interface risks between FFP work and Option 4, and whether successive targets are appropriate given uncertainties in quantities, sequencing, access, river conditions, and market pricing.
PDF
PDF, High priority: read this first56 pages · wage-determination
HighAI Summary for MO20260001 Missouri General Decision Wage Determination: General Decision Number MO20260001, dated 05/18/2026, for Missouri heavy and highway construction. The document lists modification history and prevailing wage rates with fringes for multiple labor classifications across Missouri counties, including carpenters, electricians, and line construction workers. It functions as a wage determination used in public construction contracting and includes county-specific rate schedules and effective publication dates.
PDF
PDF, High priority: read this first6 pages · sow
HighAI Summary for NESP LD25 New 1200ft Lock - Draft EPA Clause: Draft Economic Price Adjustment (EPA) clause for the NESP LD25 New 1200ft Lock project. The clause describes annual PPI-based price adjustments starting after 12 months from Notice to Proceed, with rules for up/down changes, 5% threshold, forward pricing exclusions, invoice support, calendar-year quantity treatment, a 1% cap on total contract price adjustments, audit rights, and bilateral removal. It also includes a unit price table with PPI references, units of measure, base schedule line items, and price proposal commodity pricing requirements.
PDF
PDF, High priority: read this first6 pages · sow
HighAI Summary for NESP LD25 New 1200ft Lock - Economic Price Adjustment Clause: Economic Price Adjustment (EPA) clause for the NESP LD25 New 1200ft Lock project. The document sets annual PPI-based price adjustment procedures starting after 12 months from Notice to Proceed, including thresholds, eligible commodities, invoice/supporting-data requirements, treatment of forward pricing agreements, bond/insurance adjustments, record retention, and limits on total cumulative adjustments. It includes an incorporated unit price table and commodity references for steel, aggregate, concrete-related materials, and related CLINs.
PDF
PDF, High priority: read this first12 pages · sow
HighAI Summary for Section 00 21 16 Proposal Submission Requirements: Section 00 21 16 provides proposal submission requirements for a competitive solicitation. It specifies required proposal volumes, page limits, formatting and file submission rules, labeling and content instructions, and instructions for the cover sheet. It also states electronic PDF submission through PIEE, prohibits hyperlinks and excess materials, and requires the proposal to address technical, small business participation, and price/general administrative content in separate files.
PDF
PDF, High priority: read this first13 pages · sow
HighAI Summary for SECTION 00 21 16 – Proposal Submission Requirements: Section 00 21 16 provides proposal submission requirements for a solicitation. It specifies required proposal volumes, page limits, file formatting, labeling, submission method through PIEE, prohibited submission formats, and content rules. It also details the proposal cover sheet information, volume organization, page-count exclusions, proprietary marking instructions, and evaluation-related instructions for technical, small business, and price/general administrative submissions.
PDF
PDF, High priority: read this first14 pages · sow
HighAI Summary for Section 00 22 16 – Evaluation Method: Section 00 22 16 outlines the source selection evaluation method for a best-value construction procurement. It states the basis for award, establishes the relative importance of Factors 1 through 5, requires a project labor agreement, and describes proposal compliance review, negotiations, and oral presentation procedures. The document also begins the detailed evaluation criteria for Volume I, Factor 1 Past Performance, including recency, relevancy, and quality requirements and the minimum number of past projects to submit.
PDF
PDF, High priority: read this first15 pages · amendment
HighAI Summary for Section 00 22 16 - Evaluation Method (Amendment 0003): This document outlines the evaluation criteria and basis for award for a large-scale marine construction project. It specifies a best-value procurement approach based on five factors: Past Performance, Construction Approach, River Wall/Intermediate Wall Means and Methods, Small Business Participation, and Price. It details the evaluation process, including the requirement for a Project Labor Agreement (PLA), the role of the Source Selection Evaluation Board (SSEB), and the conduct of oral presentations and negotiations.
PDF
PDF, High priority: read this first14 pages · sow
HighAI Summary for SECTION 00 22 16 – Evaluation Method / Basis for Award: Section 00 22 16 provides the evaluation method and basis for award for a construction procurement. It states the best value source selection approach, identifies five evaluation factors (past performance, construction approach, river wall and intermediate wall means and methods, small business participation, and price/administrative submission), and explains that non-cost factors must be at least acceptable. The section also requires a project labor agreement, describes compliance review and SSEB evaluation procedures, and outlines discussion/oral presentation rules. It further details Factor 1 past performance requirements, including recency, relevancy, submission organization, and the minimum number of recent relevant projects to submit.
PDF
PDF, High priority: read this first19 pages · amendment
HighAI Summary for Solicitation Amendment 0003 - W912P926RA004: Amendment 0003 to solicitation W912P926RA004, dated October 6, 2026. The purpose is to provide updates based on ProjNet Bidder Inquiries and Government Responses. Key changes include the addition of a disclosure regarding the Government's use of AI in proposal evaluation, updates to the CLIN schedule, revisions to Section 00 08 00 and 01 33 00, and clarifications regarding the transition to the Construction Management Platform (CMP). It also includes updates to the dewatering plan evaluation criteria in Section 00 22 16.
PDF
PDF, High priority: read this first12 pages · amendment
HighAI Summary for Solicitation Amendment 0004 - W912P926RA004: Amendment 0004 to solicitation W912P926RA004, dated October 20, 2026. The purpose is to provide updates based on ProjNet bidder inquiries. Key changes include a revised pricing schedule with renumbered and updated quantities for various CLINs (including drilled shafts, assist vessels, and concrete placement), the addition/deletion of specific CLINs, and updates to the Geotechnical Data Set and specifications for the New 1200ft Lock.
PDF
PDF, High priority: read this firstamendment
HighAI Summary for Solicitation Amendment 0005 - W912P926RA004: Amendment 0005 to solicitation W912P926RA004, issued on October 21, 2026, by the USACE St. Louis District. The primary purpose of this amendment is to extend the proposal response due date from November 16, 2026, to December 9, 2026, at 10:00 AM CST. All other terms and conditions remain unchanged.
PDF
PDF, High priority: read this firstamendment
HighAI Summary for Solicitation Amendment 0006 - W912P926RA004: Amendment 0006 dated 12 Nov 2026 for solicitation W912P926RA004. This amendment provides updates based on ProjNet Bidder Inquiries and Government Responses. Key changes include revisions to the Proposal Submission Requirements (Section 00 21 16), updates to the Pricing Schedule (Section 00 00 10) including CLIN renumbering, new CLINs for bulkhead slot fillers and grouting, and quantity updates for multiple CLINs. It also includes updated specifications and drawing sets for the New 1200ft Lock.
PDF
PDF, High priority: read this first58 pages · rfp
HighAI Summary for W912P926RA004 Draft Solicitation – Lock & Dam 25 New 1,200 ft Lock Phase 2: Draft solicitation and SF 1442 for the Lock & Dam 25 New 1,200 ft Lock Phase 2 construction project. The document includes solicitation/offer/award forms, CLIN schedule, draft procurement and contracting requirements, and references attached sections such as proposal submission requirements, basis for award, specifications, drawings, EPA clause, and pricing schedule. It describes construction of a new 1,200-foot pile-founded lock and approach guard walls, with a 58-page solicitation package dated 31 Mar 2026 and options included in the pricing structure.
PDF
PDF, High priority: read this first81 pages · ifb
HighAI Summary for W912P926RA004 Lock & Dam 25 New 1,200 ft Lock Phase 2 Solicitation: Standard Form 1442 solicitation for Lock & Dam 25 New 1,200 ft Lock Phase 2, issued for construction of a new 1,200-foot drilled shaft-founded lock, upstream ported guard wall, and downstream guard wall. The document includes solicitation instructions, offer and award provisions, project narrative, and incorporated attachments such as proposal submission requirements, basis for award evaluation method, specifications, plans, pricing schedule, past performance questionnaire, and related appendices. It identifies the procurement as a sealed bid/invitation for bid and notes that technical proposal portions may be incorporated into the contract at award.
PDF
PDF, High priority: read this firstspecifications
HighAI Summary for W912P9-26-R-A004 New 1200' Lock Construction Specifications: Construction specifications for the Upper Mississippi River NESP Lock and Dam No. 25 New 1200' Lock project, dated June 2026. Includes the solicitation number W912P9-26-R-A004 and a contract number placeholder, along with a detailed table of contents covering procurement and contract requirements, general requirements, concrete, masonry, metals, finishes, specialties, plumbing, HVAC, electrical, earthwork, and exterior improvements. The document provides technical specification divisions and performance requirements for construction work.
PDF
PDF, High priority: read this first2 pages · special-notice
HighAI Summary for W912P926RA004 Pre-Bid Site Visit Handout – NESP Lock & Dam 25: Pre-bid site visit handout for Solicitation Notice ID W912P926RA004, USACE St. Louis District, for the NESP Lock & Dam 25 New 1200-Ft. Lock Mega Project in Winfield, Missouri. Dated for the August 26, 2026 site visit, it provides solicitation precedence language, key procurement dates, project base-and-options structure, and major coordination constraints. The handout also summarizes active advance contracts, navigation closure schedules, intermittent outage limits, site access, staging areas, and dam gate closure request information. It notes that an amendment is forthcoming regarding laydown restrictions.
PDF
PDF, High priority: read this first3 pages · presolicitation
HighAI Summary for W912P926RA004 Pre-Solicitation Synopsis – Lock and Dam 25 New 1,200 Ft Lock: Pre-solicitation synopsis for proposed solicitation W912P926RA004 for the Lock and Dam 25 New 1,200 Ft Lock project under the Navigation & Ecosystem Sustainability Program (NESP) in Winfield, Missouri. Issued by the U.S. Army Corps of Engineers, St. Louis District, it announces a future full and open competition for a firm-fixed-price contract with economic price adjustment and best value tradeoff source selection. The notice describes the work, including construction and commissioning of a new 1,200-foot drilled-shaft founded lock chamber, approach walls, dewatering/unwatering, system modifications, demolition, dredging, and coordination with navigation interests. The solicitation is expected on or about July 15, 2026, and proposals must be submitted electronically through PIEE/Solicitation Module. SAM registration is required.
PDF
PDF, High priority: read this firstspecifications
HighAI Summary for W912P9-XX-X-XXX 95% ATR/BCOES Specifications, Jan 2026: 95% ATR/BCOES specifications for the Upper Mississippi River Navigation Ecosystem Sustainability Project (NESP), Lock and Dam No. 25, New 1200' Lock, dated January 2026. The document includes the project table of contents and detailed specification divisions covering procurement and contracting requirements, general requirements, existing conditions, concrete, metals, mechanical, electrical, utilities, transportation, and waterway/marine construction, along with technical section references for construction, testing, commissioning, and related requirements.
PDF
PDF, High priority: read this first22 pages · wage-determination
HighAI Summary for WD_IL20260018 - Illinois General Decision Wage Determination: General Decision Number IL20260018, dated 06/17/2026, for Illinois heavy construction and dredging/marine construction work. The document lists covered counties and wage rates/fringes for multiple labor classifications, including dredging, hydraulic dredging, tug and launch operators, mechanics, and related marine/floating equipment work. It includes modification history showing prior publication dates and updated rates, plus footnotes on holidays, medical benefits, and hazardous/toxic waste pay differentials.
PDF
PDF, High priority: read this first10 pages · wage-determination
HighAI Summary for WD_IL20260019 - Illinois Heavy Construction Wage Determination: General Decision Number IL20260019, published 05/18/2026, for heavy construction in Illinois counties and specified dredging projects. This wage determination lists prevailing wage and fringe benefit rates for dredging classifications across Corps of Engineers district areas, includes modification history, classification rates, footnotes, and Davis-Bacon/Executive Order labor compliance notes.
PDF
PDF, Low priority3 pages · other
LowAI Summary for Appendix B - Project Detail Sheet: Appendix B project detail sheet form used for contractor past performance or experience submissions. It requests project identifiers, agency contacts, delivery method, detailed project description, contractor role, relevancy explanation, problems encountered, lessons learned, schedule milestones, and original/final cost data. The form also includes space for additional narrative on project description, work performed, and relevancy.
PDF
PDF, Low priority3 pages · past-performance
LowAI Summary for Appendix B Project Detail Sheet: Appendix B Project Detail Sheet form for construction past performance and project experience submissions. It requests contractor, project, agency, and technical representative information, plus detailed project description, work performed, relevancy to the solicitation, problems encountered, lessons learned, safety incidents, schedule milestones, and original/final cost data. The form is labeled CUI and includes additional space for expanded narrative responses.
LowAI Summary for Appendix B - Subcontractor Consent / Experience Information Form: Section L, Appendix B subcontractor consent and experience information form for government solicitation W912P9xxxxxxx. Captures contractor, contract/task order details, project information, prime and subcontractor identities, project description, and signature authorization allowing performance discussions for evaluation purposes.
PDF
PDF, Low priority4 pages · past-performance
LowAI Summary for NAVFAC/USACE Past Performance Questionnaire (PPQ-0): NAVFAC/USACE Past Performance Questionnaire Form PPQ-0 (9/30/11) for Section L Appendix A. The form is completed by the contractor and client to document contract information, project description, and client contact details, then rate contractor performance. It includes adjective rating definitions (Exceptional to Not Applicable) and performance evaluation criteria such as quality, schedule/timeliness, and customer satisfaction. Intended as a proposal support document for USACE solicitations.
PDF
PDF, Low priority4 pages · past-performance
LowAI Summary for NAVFAC/USACE Past Performance Questionnaire (PPQ-0): NAVFAC/USACE Past Performance Questionnaire Form PPQ-0 (9/30/11) for Section L Appendix A. The form is completed by the contractor and client to document past contract performance, including contractor and contract information, project description, client contact details, and performance ratings. It includes adjective rating definitions and evaluation criteria for quality, schedule/timeliness, and customer satisfaction. The completed questionnaire is intended to be submitted with USACE proposals and used as a reference for contractor past performance.
PDF
PDF, Low priority1 page · special-notice
LowAI Summary for W912P926RA004 Pre-Bid Site Visit Agenda: Pre-bid/pre-proposal site visit agenda for Solicitation W912P926RA004, dated August 26, 2026, for the NESP LD25 1200-Ft. Lock project at Lock and Dam 25 in Winfield, Missouri. The document outlines check-in, safety briefing, project overview, guided site tour stops, and closing remarks. It also states that information from the site visit or handouts does not supersede the official solicitation package.
PDF
PDF, Low priority2 pages · other
LowAI Summary for W912P926RA004 Pre-Proposal Site Visit Sign-In Sheet: Sign-in sheet for the pre-proposal site visit for NESP LD25 1200ft Lock under solicitation W912P926RA004. Dated August 26, 2026, it records attendee information and includes notices that solicitation information from the visit does not supersede the official package, inquiries must be submitted through ProjNet by September 25, 2026, and proposals must be submitted in PIEE by November 16, 2026.
Notice type changed from Special Notice to Presolicitation. Response deadline changed from May 1, 2026 to Jun 12, 2026. The notice title changed. The notice description changed. The point of contact changed.
Type Changed
Presolicitation → Sources Sought
Type Changed
Sources Sought → Presolicitation
Deadline changed
Response deadline changed from Jul 15, 2026 to Jul 14, 2026.
Type Changed
Presolicitation → Solicitation
Notice updated
The notice description changed.
Notice updated
The notice description changed.
Notice updated
The notice description changed.
Notice updated
The notice description changed.
Notice updated
The notice description changed.
Notice updated
Response deadline changed from Nov 16, 2026 to Dec 9, 2026. The notice description changed.
Notice updated
The notice description changed.
Response Deadline
Submission deadline
Response Deadline
Ready to pursue this opportunity?
Get full access to track this contract, build proposals with AI assistance, and manage your pipeline.
Organization & Contact Information
Show more
AgencyDepartment Of Defense → W07V Endist St Louis
NESP LD25 1200 ft Lock --------- The new lock at Lock 25 will be constructed in the downstream direction in the auxiliary miter gate bay, which has minimum provisions for an adjacent 360-foot-long lock and is referred to as Location 3 in the System Feasibility Study (September 2004). This contract will consist of construction of a new 1,200-foot drilled shaft-founded lock in the auxiliary miter gate bay, a 1,200-foot upstream ported guard wall, and a 650-foot downstream guard wall. The existing 600-foot lock will remain in place and once the new lock is constructed and operational, will become an auxiliary lock chamber used primarily by recreation traffic or when the 1,200 ft lock is out of service. ------------ SEE ATTACHMENT FOR FULL DETAILS OF UPCOMING REQUIREMENT SOLICITATION. --------- Attachment 0004 Plans (Volume 1-7) and Attachment 0005 Navisworks Federated Model must be requested via email to Contract Specialist, Whitney Dee at •••••@•••••.•••Sign up to see this detail. Upon request they will be sent via DoD SAFE, since the files are too large to attach within PIEE or send via email. ------ SEE UPDATE LABELED 0817 FOR FULL DETAILS OF UPCOMING PRE-PROPOSAL SITE VISIT. -------------------- AMENDMENT 0001 provides updates in accordance with some of the ProjNet Bidder Inquiries and Government Responses posted through 31 August 2026. Additional questions and answers and updates will be provided in forthcoming amendments. See all attachments for full details.-------------------- AMENDMENT 0002 provides updates in accordance with some of the ProjNet Bidder Inquiries and Government Responses posted through 15 September 2026. Additional questions and answers and updates will be provided in forthcoming amendments. See all attachments for full details.-------------------- AMENDMENT 0003 provides updates in accordance with some of the ProjNet Bidder Inquiries and Government Responses posted through 5 October 2026. Additional questions and answers and updates will be provided in forthcoming amendments. See all attachments for full details.-------------------- AMENDMENT 0004 provides updates in accordance with some of the ProjNet Bidder Inquiries and Government Responses posted through 20 October 2026. Additional questions and answers and updates will be provided in forthcoming amendments. See all attachments for full details.-------------------- AMENDMENT 0005 extends the proposal due date to 10:00AM CST, Wednesday, December 9, 2026. See all attachments for full details..-------------------- AMENDMENT 0006 provides updates in accordance with the final set of ProjNet Bidder Inquiries and Government Responses. See all attachments for full details.