USCGC Stratton Load Bank Test
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
Active Opportunities Like This One
AI Contract Overview
This contract involves performing load bank testing on the No. 1 Ship Service Diesel Generator (SSDG) aboard the USCGC STRATTON at the Coast Guard Base Alameda, with work scheduled from December 8 to December 12, 2025. The scope requires the contractor to supply a 1500 KW resistive load bank, install and route cables per Coast Guard drawings, and oversee the entire testing process, including initial startup, incremental load increases up to 100%, and sustained operation for at least two hours at full load. The testing aims to verify generator performance following recent modifications such as bearing replacement, shaft alignment, and engine overhaul. The contractor must develop and submit a detailed load testing plan for approval, ensuring compliance with Coast Guard technical standards and safety protocols, including establishing exclusion zones and emergency shutdown procedures. Data collection involves monitoring engine parameters and ECM recordings every 15 minutes, with all results documented and submitted electronically as part of the contractor furnished reports. The contract emphasizes safety, technical compliance, and precise execution, with the government personnel operating the ship’s machinery during testing. The work location is primarily aboard the vessel, with testing equipment placed either on the ship or on the pier. The contractor is responsible for furnishing all necessary materials, including cables and hardware, and for removing all equipment post-testing. The solicitation is designated as a total small business set-aside under NAICS code 336611, with no special security clearances required. While detailed technical and procedural requirements are outlined, the document does not specify contract clauses, pricing, or evaluation factors, focusing instead on technical performance, safety standards, and timely submission of test data and reports.
General Info
Place of Performance
Alameda, CA, 94501, USASet-Aside
Timeline
Submission Closed
Organization & Contact Information
Full Description
SOW for #1 SSDG Load Bank Testing
USCGC STRATTON (WMSL-752)
- This solicitation is to provide:
Load bank testing of 01 SSDG for CGC STRATTON
- Vendor to Perform work at ships homeport:
CGC STRATTON
UNITED STATES COAST GUARD BASE ALAMEDA
1 EAGLE ROAD ALAMEDA, CA 94501
- Security requirements: No special security requirements needed. Vendor will only require base and ship access during POP.
- POP: 08DEC25 – 12DEC25
- POC:
- STRATTON Engineer Officer:
LCDR Benjamin Williamsz
- STRATTON Port Engineer:
LTJG Summer Gould
- STRATTON APM:
LT Adrian Rubio
31100_BEC_0924_418
WORK ITEM 1: Ship Service Diesel Generator, Load testing, perform
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform load testing of designated Ship Service Diesel Generator (i.e., SSDG) listed in Table 1.
TABLE 1 – LIST OF SHIP SERVICE GENERATOR
CATERPILLAR mODEL NO.
DESCRIPTION
location
3512B
No.1 Ship Service Diesel Generator (NSC 009), 1360 KW, 450 Volt AC, 3 Phase, 60 Hz
Auxiliary Machinery Room (5-36-01-E)
1.2 Government-furnished property.
None.
2. REFERENCES
Coast Guard Drawings
Coast Guard Drawing 750-WMSL-501-002, Rev E, Machinery Arrangements (ASC501001)
Coast Guard Drawing 418A-WMSL-801-001, Rev A, Booklet of General Plans
Coast Guard Publications
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Coast Guard Technical Publication (TP) 7119, Ship Service Diesel Generator - Model 3512B
Coast Guard Technical Publication (TP) 7165B, Ship Service Switchboards 1S, 2S, 3S & 1SP Shore Power – Operation, Maintenance & Installation – Volume 1
Coast Guard Technical Publication (TP) 7166B, Ship Service Switchboards 1S, 2S, 3S & 1SP Shore Power – Operation, Maintenance & Installation – Volume 2 & 4
Coast Guard Technical Publication (TP) 7167, Ship Service Switchboards 1S, 2S, 3S & 1SP Shore Power – Operation, Maintenance & Installation – Volume 3
Other References
COMDTINST 9077.1 (series) Equipment Lockout-Tags-Plus Instruction
MIL-STD-1310, Sep 2009, Shipboard Bonding, Grounding, and Other Techniques for Electromagnetic Compatibility and Safety
3. REQUIREMENTS
3.1 General. contractor to provide load bank and OEM technical representative services to oversee overall break-in and run-up procedures for reassembled Caterpillar 3512B engine, to include all steps required from initial startup to satisfactory completion of 100% load operation for OEM prescribe timeframe.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
None.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
- Piping
- Electrical Cables
- Switchboard Enclosure
- Vent Ducting
- Motor Operated Valves
3.1.5 Background information. SSDG listed in Table 1 will be modified by the Coast Guard for the following task:
- Generator Bearing Replacement
- Shaft Alignment
- Pinning and Machine Work
- Diesel Engine Top-end Overhaul
3.1.5.1 After completion of above listed tasks, this Work Item is to be used for the Contractor to perform load testing of designated SSDG listed in Table 1.
3.2 Work location. The concerned work area is listed in Table 1. See the applicable drawings in References in Paragraph 2 for guidance, locations, and details.
3.2.1 Proposed temporary cable routing must be developed using USCG Dwg 418A-WMSL-801-001. Submit a CFR.
3.2.1.1 Temporary load bank cables must be routed from the switchboard to the load bank via a single route, and must not be routed separately by any method which would lead to unbalanced phase cables to transit through hull or bulkhead openings.
3.3 Grounding. The Contractor must ensure conductive surfaces of the load bank enclosure are appropriately bonded and grounded for protection of personnel.
3.4 Contractor Furnished Materials (CFM). The Contractor must furnish materials listed in the Table 2 for load testing of the SSDG listed in Table 1.
TABLE 2 – CONTRACTOR furnish MATERIALS
MATERIALS
description
SOURCE OF SUPPLY
Load Bank
1500 KW, 450 Volt AC, 3 Phase, 60 Hz, Resistive
Electrical Equipment’s Rental Company
Load Bank Cables
Approximate length of 300 Feet Cables with ring tongue compression lugs, 6 Paralleled #4/0 copper (single conductor) per phase (18 Total x 300 Feet) and one additional length for the equipment grounding conductor or Six LSTSGU-400
Tony Santiago
Murray Benjamin Electric
397 West Ave.
Stamford CT 06902
(+1 (555) 000-0000) OR Any Electrical Cable Supplier
3.4.1 The contractor must provide miscellaneous hardware required for electrical installation (i.e. Nylon Stuffing Tubes, Chafing Gear, Box Connectors, Lugs, Fasteners, Wire Nuts, Tapes, Cable ties & Cable Mounting Brackets, etc) of the electrical equipment.
3.5 Load testing. The Contractor must provide labor and crane services as necessary for placing load bank at suitable location (i.e., On the pier or the ship). After completion of load bank testing of SSDG, the Contractor must remove all installed equipment and cables used during testing.
3.5.1 Testing plan. The Contractor must submit a plan for load testing of the SSDG in accordance with TP 7119.
3.5.1.1 The plan must cover the following topics at a minimum:
- Steady increase of load in multiple steps up to 100% real power load
- No less than 2 hours of continuous testing at 100% load
- Simulated start of 450 HP load (assume no more than 200% FLA)
- Emergency shutdown procedures
- Load bank specification and location
- Cable locations for load bank
- No-load tests
- Data to be collected during tests
- All proposed connections, cable and load bank configurations
3.5.1.2 The Contractor must start testing of the SSDG after COR Approval of submitted Test Plan and official acceptance by the Contract Officer (KO).
3.5.2 After placing load bank at suitable location (i.e., On the pier or the ship) the Contractor must install the cables from the load bank to associated SS Switchboard bus bars (i.e. Back side of SS Switchboard No.2S), according to the agreed upon cable routing.
CAUTION
THE BACK SIDE OF THE SWITCHBOARD SHOULD BE ROPED OFF AS A PERSONNEL EXCLUSION AREA (APPROXIMATELY 10 FOOT RADIUS FROM ANY VISIBLE LIVE BUS
3.5.2.1 The Contractor must route the cables from designated SSDG to load bank through hatches and passageway. The Contractor must run cables in overheads as much as possible to avoid trip hazards.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
SAFETY
At any point in the load test or operational testing period if the need presents itself the engine – Prime mover may be shut down by the Tech rep with communication to the USCG operational Engineer utilizing the local EOS, E stop or shut down from the switch gear. Any of the three options will automatically open the SSDG buss breaker
3.5.3 After warmup of SSDG until coolant temperature reaching 140 Degree F, the Contractor must perform the load testing of designated SSDG listed in Table 1 at following load condition.
TABLE 3 – LOAD TESTING
LOAD
HOURS
*No Load
0.5 Hrs
25 % Load
0.5 Hrs
50 % Load
0.5 Hrs
75 % Load
0.5 Hrs
100 % Load
2.0 Hrs
No Load
0.5 Hrs
- Running no load testing. No load testing will consist of running the engine at idle rpm until the engine coolant temperature reaches 140 deg. F during that warmup time safety testing will be performed for oil pressure, temp warning, emergency shut down conditions, and coolant temp. warning and shutdown. Shipboard alarm verification will be observed at that time as well.
3.5.3.1 Engine parameter readings during the load bank test must be taken every 15 minutes including, but not limited to the bullet points in this paragraph. Submit a CFR.
- Engine temp, Coolant temp, oil pressure, boost pressure, intake air temp after the aftercooler, exhaust stack temp, left and right bank exhaust temperatures.
- In addition to the generator load test form, a Caterpillar steady state engine performance file shall be recorded on the engine ECM all related available information.
- Generator information, voltage reading per phase, amperage readings per phase, HZ, bearing and winding temps.
- Pre and post-test PSSRP shall be saved on the ECM to provide verification of all available diagnostic codes and events.
- All electronic files and reports must be submitted via CFR.
3.6 Load test documentation. After completion of testing, the Contractor must provide all collected data sheets to the Contracting Officer.
4. NOTES
This section is not applicable to this work item.
More opportunities from Department Of Homeland Security → Sflc Procurement Branch 2(00085)
Same awarding agency
Earlier notices in this NAICS code
Posted before this notice, open and closed
Find Active Opportunities Like This
Get AI-powered intelligence on the opportunities still open
Every page of the solicitation package shredded into a compliance breakdown
AI-powered matching based on your capabilities and past performance
Competitor and incumbent history on the requirement
Automated alerts on amendments, Q&A deadlines, and award
Join 750+ contractors already using CLEATUS