A.24-06-017State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

LS Power Grid California, LLC has applied for a Certificate of Public Convenience and Necessity from the California Public Utilities Commission for the Manning 500/230 kV Substation Project under solicitation A.24-06-017. Located in Fresno County, the project involves the construction and operation of the Manning Substation and an approximately 11.5-mile overhead double-circuit 230 kV transmission line. This line will interconnect the new substation with the existing Pacific Gas and Electric Company Tranquillity Switching Station, requiring additional interconnections, reconductoring, and modifications to existing facilities. The project is governed by the California Environmental Quality Act, with a Negative Declaration prepared and mitigation measures and monitoring plans adopted as of September 18, 2025. Administrative requirements include a mandatory environmental filing fee of 2,968.75 dollars paid to the California Department of Fish and Wildlife. The California Public Utilities Commission serves as the lead agency for oversight and acceptance, with Tommy Alexander acting as the primary project manager. While the project involves significant infrastructure development, specific contract pricing, delivery schedules, and federal acquisition clauses are not provided in the available documentation.

General Info

LS Power Grid seeks CPUC approval for Manning Substation and transmission line in Fresno.

Documents

0

No documents available

Documents will appear here when they are available.

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

View Full Breakdown

Get what you need to respond

No documents were posted with this contract.

  • Buyer contactEmail and phone
  • Original solicitationLink to the source posting
Get the buyer contact

Ask CLEATUS

I've read this contract. Ask me anything.

Timeline

PhaseForecast
Posted

forecast

Prepare for this forecast

Research the agency, track this forecast, and prepare your capture plan before the solicitation opens.

Organization & Contact Information

Show more
AgencyCalifornia Public Utilities Commission
Contacts1 person available
OfficeN/A

Full Description

Show more
LSPGC filed an application (A.24-06-017) for a certificate of public convenience and necessity (CPCN) authorizing the construction of the Manning 500/230 Kilovolt (kV) Substation Project with the California Public Utilities Commission (CPUC). The project entails construction and operation of the new Manning Substation and one new approximately 11.5-mile overhead double-circuit 230 kV transmission line that would extend from the proposed Manning Substation to interconnect with Pacific Gas & Electric Company’s (PG&E) existing Tranquillity Switching Station. The project would also include interconnections, reconductoring, and related modification of PG&E’s existing transmission lines and related facilities.

Similar Contracts

Same NAICS industry code

NAICS: 237130
New
ACT-1427-00 Construction Cycle 10 (CC10) Concrete Test Pavement Construction at Wm. J. Hughes Technical Center Atlantic City, NJ
Solicitation # act-1427-00-construction-cycle-10-cc10-concrete-test-pavement-construction-wm-j-hughes-technical
Parsons Corporation is soliciting bids for the Construction Cycle 10 project at the William J. Hughes Technical Center in Atlantic City, New Jersey, supporting the FAA Airport Technology Research and Development branch. The scope of work involves the controlled demolition of existing pervious runway test pavement and the construction of new concrete test slabs measuring approximately 310 by 52.5 feet with a thickness of 15.5 inches. Key requirements include providing aggregate subbase, updating the asphalt base course to a stabilized drainable base, and performing minor design adjustments to plans and specifications. The subcontractor is responsible for procuring all materials, managing waste disposal, and coordinating professional engineering and laboratory services for geotechnical design and roadway materials testing. The project includes rigorous material characterization tests such as California Bearing Ratio and Plate Load tests, with critical operations phased to allow for continuous subgrade adjustments. Work is primarily scheduled for normal business hours, Monday through Friday, though some after-hours and weekend work may be required. This solicitation is set aside for various small business categories, including VOSB, SDVOSB, WOSB, and HUBZone certified firms.
Parsons Corporation

POSTED

about 7 hours ago

DEADLINE

in 2 months
View Details
NAICS: 237130
New
International
314E-2026 132-11 kV MAIN SUBSTATIONS AT AJMAN CITY (ACMN) IN AJMAN AREA AND 132-11 KV AWAFI (AWMN) IN RAK AREA, AND 132KV UNDERGROUND CABLING WORKS
Solicitation # 314E/2026
Etihad Water & Electricity has issued solicitation 314E/2026 for a lump-sum turnkey project involving the design, engineering, supply, construction, installation, testing, and commissioning of 132/11kV main substations and associated 132kV underground cabling works in the United Arab Emirates. The scope of work is divided into several key components, including the construction of new main substations at Ajman City (ACMN) and Awafi (AWMN), protection modifications for BYMN-SAMN, and LILO connections for both ACMN and AWMN. Additionally, the project includes approximately 22 km of new 132kV underground cabling works for BYMN-SAMN and approximately 5 km of LILO connections for AWMN. Eligible bidders must be registered in the SAP Ariba e-procurement system and hold a valid EtihadWE Prequalification Certificate, a requirement that also extends to all proposed subcontractors for electrical, civil, MEP, and underground cable works. Proposals must be submitted via SAP Ariba with separate technical and commercial uploads by December 14, 2026. Each quoted lot must be accompanied by an irrevocable and unconditional bank guarantee issued by a UAE-based bank, valid for at least 180 days from the tender opening date. All works must adhere to EtihadWE standards and specifications.
Etihad Water & Electricity

POSTED

1 day ago

DEADLINE

in 27 days
View Details
NAICS: 237130
New
SLED
Solar Interconnection Grant
Solicitation # RFA-131767
The Solar Interconnection Grant Program, administered by the Virginia Department of Energy, provides funding to public bodies to offset the costs of connecting distributed solar energy systems to the electric grid. Established via Senate Bill 659 and House Bill 683, the program targets barriers to public-sector solar development by funding infrastructure upgrades, including transformers, relays, SCADA/telemetry, protection equipment, metering modifications, and necessary engineering services. Eligible projects may be behind-the-meter or front-of-the-meter and must be located at previously developed project sites. The anticipated period of performance ranges from 6 to 18 months. Applications must be submitted through the Virginia Energy Grant Portal by January 15, 2027. Awards are competitive and based on a 100-point scoring system that evaluates organizational summaries, project scope, readiness, interconnection details, and community benefits. Applicants must adhere to strict word counts and submit a master PDF and two Excel files. Grant recipients must comply with Virginia procurement laws and prevailing wage requirements mirroring federal Davis-Bacon standards. Administration requires monthly invoicing by the 15th of each month, quarterly progress reports, and final verification via equipment lists and photos. Payments are issued upon agency acceptance of work, with a potential 5% retainage for construction projects and a final audit before closing.
Virginia Department of Energy

POSTED

2 days ago

DEADLINE

in about 2 months
View Details
NAICS: 237130
New
SLED
Fiber to the Home Phase 2 - Rebid
Solicitation # 50010
The City of Hudson, Ohio, is soliciting bids for the Fiber to the Home Phase 2 Rebid, a capital improvement project focused on expanding fiber optic infrastructure. The scope of work includes the installation of approximately 49,000 lineal feet of 1.5-inch HDPE fiber conduit and 52,000 lineal feet of 2x1.5-inch HDPE fiber conduit using horizontal directional drilling. Additionally, the project requires the installation of 29,000 lineal feet of aerial fiber, 174,000 lineal feet of fiber optic cable of various strand counts, and the placement of underground fiber vaults and handholes. Bidders are required to provide pricing for labor only, and the work includes all necessary splicing, testing, clearing, grubbing, and site restoration to pre-construction conditions. The project is governed by the City of Hudson Engineering Standards and ODOT Construction and Material Specifications, with a substantial completion deadline of December 3, 2027, and final completion by December 17, 2027. Bidders must submit electronic proposals via Bid Express and provide a Statement of Bidder's Qualifications demonstrating at least three years of experience in similar projects. The contract mandates compliance with Ohio Revised Code Chapter 4115 regarding prevailing wage rates and requires the provision of bid, performance, and payment bonds, as well as a maintenance bond equal to 10 percent of the final contract price. Evaluation for award will be based on compliance with requirements, financial ability, and the responsibility and qualifications of the bidder.
City of Hudson

POSTED

3 days ago

DEADLINE

in 21 days
View Details
NAICS: 237130
New
SLED
On-Call Utility Civil Construction Services
Solicitation # CS 11-26-04
Alameda Municipal Power (AMP) is seeking on-call civil construction services to support its electric distribution system in the City of Alameda, California. The scope of work covers a two-year term and includes the installation, repair, and replacement of underground electrical and fiber conduits, utility boxes, transformer pads, and foundations, as well as surface restoration, excavation, and trenching. The contract is structured as a master agreement with a maximum combined not-to-exceed value of $1,000,000 across up to two on-call contracts, with specific work assigned via individual task orders. Awards are based on the lowest responsible bidder, with task orders generally awarded by lowest price, though AMP may consider expertise, performance history, and continuity of work. Bidders must demonstrate sufficient capacity, experience, and a satisfactory performance record, with a preference given to local businesses when labor quality and price are equal. Required submissions include a non-collusion declaration, a subcontractor list, and proof of DIR registration. The successful bidder must provide a full-time qualified superintendent on-site and adhere to prevailing wage requirements and strict safety standards, including specific shoring and bracing plans for excavations five feet or deeper. Financial security is required via a bid security of 10% of the maximum bid amount, while the awarded contractor must provide performance and payment bonds for 100% of the contract price. Technical acceptance is based on rigorous inspection criteria for various construction elements, including conduit alignment, base preparation for vaults, and compaction testing. Bids must be submitted electronically through the Bid Portal by December 17, 2026.
Engineering and Operations

POSTED

4 days ago

DEADLINE

in about 1 month
View Details

More opportunities from California Public Utilities Commission

Same awarding agency

NAICS: 237130
SLED
PG&E Moraga-Oakland X 115 Kilovolt Rebuild Project
Solicitation # A.24-11-005
The PG&E Moraga-Oakland X 115 Kilovolt Rebuild Project, identified by solicitation number A.24-11-005, involves upgrading approximately 5 miles of four overhead 115 kV power lines between the Moraga and Oakland X substations. The project will convert existing parallel double-circuit power lines into four hybrid lines, consisting of approximately 4 miles of overhead and 1 mile of underground segments. The scope of work includes replacing existing towers, poles, and conductors, performing minor modifications within existing substations, and installing single-circuit and double-circuit transition structures to connect overhead and underground portions. Additionally, the project will implement optical ground wire on aboveground structures and communication cables within underground segments. The project area spans the city of Orinda, unincorporated Contra Costa County, and the cities of Oakland and Piedmont within Alameda County. Managed by the California Public Utilities Commission, the project has undergone an extensive environmental review process under the California Environmental Quality Act, resulting in a Notice of Determination dated July 2, 2026. Key environmental and safety requirements include the implementation of soil management and helicopter safety plans, adherence to ADA standards for Caltrans facilities, and the maintenance of bicycle and pedestrian access during construction. The project must also comply with U.S. Department of Transportation hazardous materials regulations and specific mitigation measures to protect biological resources, particularly oak woodlands, as recommended by the California Department of Fish and Wildlife. While a filing fee of 4,227.50 dollars was recorded for the Environmental Impact Report, the total project budget is not specified in the provided documentation.
Power and Communication Line and Related Structures Construction

POSTED

4 months ago

DEADLINE

N/A
View Details
NAICS: 237110
SLED
Monterey Peninsula Water Supply Project
Solicitation # 2006101004
The Monterey Peninsula Water Supply Project is a comprehensive desalination initiative located in northern Monterey County, including the City of Marina, the town of Castroville, and surrounding unincorporated areas. The project involves the construction of a seawater desalination plant and extensive infrastructure, including a source water intake system featuring four subsurface slant wells and the conversion of an existing slant well at the CEMEX property. Additional key deliverables include the installation of two Aquifer Storage and Recovery wells and a network of pipelines, specifically the Transmission Main, Castroville, Desalinated Water, and Source Water pipelines. The project is governed by a 24-year General Lease for Industrial Use approved by the State Lands Commission, extending through January 1, 2050. It is subject to rigorous regulatory compliance, including the California Environmental Quality Act and the California Endangered Species Act, with specific protections for the California tiger salamander under Incidental Take Permit No. 2081-2018-027-04. The California Public Utilities Commission served as the lead agency for the certified Environmental Impact Report, while the Coastal Commission provided approval for Phase 1 via a Coastal Development Permit. Construction is scheduled to be executed in two phases.
Water and Sewer Line and Related Structures Construction

POSTED

5 months ago

DEADLINE

N/A
View Details

Earlier notices in this NAICS code

Posted before this notice, open and closed

Prepare for this forecast

Research this forecast and prepare for the solicitation

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS