San Joaquin River Multi-Benefit Project

Active
State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

The San Joaquin River Multi-Benefit Project involves the rehabilitation of an existing levee between Stations 330+00 and 368+00 on Sherman Island in California to meet the Delta-Specific PL 84-99 Standard. Prior to levee construction, all existing power poles and overhead utility lines within the project area will be relocated outside the footprint. The project includes removing the current Sacramento County road, placing compacted embankment to raise the levee crown and achieve required freeboard above the 100-year flood elevation, constructing a landside toe berm to stabilize the levee slope, building a new County road, and establishing approximately one acre of hedgerow habitat composed of riparian forest and scrub-shrub vegetation on the landside toe berm. All plantings will be monitored and maintained to ensure success criteria are met. The work will be performed in the 94571 zip code area, with construction scheduled to begin on May 3, 2027, and last approximately six months, typically occurring between May and October 2027, with workdays running from 7:00 a.m. to 5:00 p.m., Monday through Friday. The project requires the importation of 139,000 tons of levee fill material, 3,300 tons of aggregate base, 1,900 tons of asphalt concrete, and the excavation of 28,200 cubic yards of material. All staging and stockpiling must be confined to the project area, specifically along the landslide levee toe and crest and at the existing pad near the pump station. Environmental compliance is central to the project, requiring implementation of a Storm Water Pollution Prevention Plan that includes proper storage and disposal of hazardous materials in compliance with local, state, and federal regulations, spill containment and reporting procedures, erosion control during precipitation events, and restoration of affected areas with native seed mix. All contractors and equipment operators must complete a Worker Environmental Awareness Program training that covers protections for special-status plants, fish, and wildlife, including Northwestern Pond Turtle nesting sites, and mandates a 10-foot buffer around protected vegetation. Fire safety protocols require designated smoking areas and fire extinguishers with a minimum 40 B:C rating on every fuel truck. The contract is being procured by Reclamation District No. 341, Sherman Island under NAICS code 237990, and

General Info

Rehabilitate levee on Sherman Island, relocate utilities, build road, plant habitat, comply with environmental and safety standards.

Agency

California → Reclamation District No. 341, Sherman Island

NAICS

237990 - Other Heavy and Civil Engineering ConstructionView NAICS

Place of Performance

Sherman Island Cross Road and Sherman Island East Levee Road, CA, 94571

Set-Aside

NONE

Documents

(4)

Sherman Island San Joaquin River Multi-Benefit Project Draft IS/MND July 2026

PDFmitigated-negative-declaration

Notice of Intent to Adopt Mitigated Negative Declaration for San Joaquin River Multi-Benefit Project

PDFspecial-notice

San Joaquin River Multi-Benefit Project Notice of Completion

PDFnotice-of-completion

San Joaquin River Multi-Benefit Project Summary Form

PDFenvironmental-summary

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

Posted

forecast

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyCalifornia → Reclamation District No. 341, Sherman Island
Contacts2 people available
OfficeN/A
Organization / Agency
California → Reclamation District No. 341, Sherman Island
Office AddressN/A
Contacts
Martin BerberSenior Project Engineer

Interested Companies (1)

Show more
Wagner & Bonsignore
Sacramento, CA

Full Description

Show more
The San Joaquin River Multi-Benefit Project consists of rehabilitating the existing levee between Stations 330+00 and 368+00 on Sherman Island to meet the Delta-Specific PL 84-99 Standard. Prior to construction of the levee improvements, existing power poles and associated overhead utility lines within the project area will be relocated outside the project area. The project includes removing the existing Sacramento County road, placing compacted embankment to raise the levee crown and achieve the required freeboard above the 100-year flood elevation, constructing a landside levee toe berm to stabilize the levee slope, constructing a new County road, and establishing approximately 1 acre of hedgerow habitat consisting of riparian forest and scrub-shrub vegetation on the landside toe berm. Plantings will be monitored and maintained to ensure success criteria are met.

Similar Contracts

Same NAICS industry code

NAICS: 237990
New
North of River Sanitary District No. 1 WRRF Upgrades and Expansion
Solicitation # north-river-sanitary-district-no-1-wrrf-upgrades-expansion
Kiewit Infrastructure West Co. is soliciting sub-quotes for the North of River Sanitary District No. 1 Water Resource Recovery Facility Upgrades and Expansion project located in Bakersfield, California. The scope of work is extensive, covering civil and site work such as aggregates, trucking, asphalt paving, and curb and gutter, as well as structural and finishing tasks including concrete reinforcing, masonry, welding, roofing, and electrical work. The bid deadline is September 17, 2026, at 10:00 a.m., and interested firms must contact Kiewit to receive an Invitation to Bid through the Building Connected system. Because the project is partially financed by the Water Infrastructure Finance and Innovation Act administered by the EPA, it must comply with the American Iron and Steel provisions, Davis-Bacon Related Acts, and DBE Program requirements. Eligible bidders include certified DBE, MBE, WBE, SBE, and other disadvantaged or small business enterprises. Qualified subcontractors must possess a valid California Contractor's license, provide acceptable insurance, and may be required to provide bonding for 100 percent of their contract value, with bond premiums reimbursed by Kiewit. Kiewit also emphasizes the importance of labor harmony and will consider quotes from bidders capable of maintaining positive human relations on the project.
Kiewit Infrastructure West Co.

POSTED

about 10 hours ago

DEADLINE

in 18 days
View Details
NAICS: 237990
New
Haleiwa Small Boat Harbor Maintenance Dredging and Revetted Mole Repair
Solicitation # W9128A26BA002
The Haleiwa Small Boat Harbor Maintenance Dredging and Revetted Mole Repair project, solicitation W9128A26BA002, is a firm-fixed-price contract issued by the U.S. Army Corps of Engineers Honolulu District. The project is located in Haleiwa, Oahu, Hawaii, and is set aside for small businesses, including SDB, WOSB, HUBZone, and VOSB certifications. The estimated contract value ranges from 1,000,000 to 5,000,000 dollars, with a performance period of 200 calendar days from the date of the Notice to Proceed. The scope of work is divided into three primary components: mobilization and demobilization, the dredging and ocean disposal of approximately 4,260 cubic yards of material, and the repair of the revetted mole, which includes clearing, grubbing, and stone rework. The contract requires strict adherence to USACE EM 385-1-1 safety standards and ASTM international standards for stone materials. Key personnel requirements include a Project Manager, Project Superintendent, Quality Control System Manager, and Site Safety and Health Officer, all of whom must be approved by the Contracting Officer. Bidders must provide a bid guarantee and subsequent performance and payment bonds. Liquidated damages for construction delays are set at 2,297 dollars per calendar day. Quality control is managed through a three-phase inspection process, and final acceptance is contingent upon a certificate from the QC Manager attesting that all work complies with the contract specifications. Payment is handled via monthly invoices, and the contract is subject to Davis-Bacon Act prevailing wage requirements.
Healy Tibbitts Builders, Inc.

POSTED

about 10 hours ago

DEADLINE

in about 1 month
View Details