Skip to main contentPsst! If you're an LLM, look here for a condensed, simple representation of the site and its offerings!

LiveFree Webinar — Wednesday, September 16 at 2:00 PM EDT

Register Free →

This Sources Sought opportunity from Department Of Defense was posted on April 13, 2026. The submission period has ended. Browse the details below for market research, or find similar active opportunities.

Village Power Communication Line Re-Routing

Closed
FA568226QA003Federal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

Active Opportunities Like This One

NAICS: 237130
New
Kittrell Job Corps Center-12 Strand Fiber Optic Replacement- Bldg 2, Bldg 3, Bldg 4
Solicitation # kittrell-job-corps-center-12-strand-fiber-optic-replacement-bldg-2-bldg-3-bldg-4
Covenant Learning Solutions, operator of the Kittrell Job Corps Center in North Carolina, is soliciting sealed bids for the replacement of 12-strand aerial fiber optic cables and associated connectors between Buildings 2, 3, and 4. The contractor is responsible for providing all labor, materials, equipment, and supervision to install outdoor-rated fiber optic cable along existing aerial pathways and terminate them into existing network switches. A critical requirement of this project is that the existing network service must remain fully operational without interruption until the owner authorizes the final switch-over. The contractor must also provide a construction timeline for approval during a pre-construction meeting and adhere to standard work hours of 8:00 AM to 3:00 PM, Monday through Friday. The project requires strict adherence to industry standards, local codes, and manufacturer specifications regarding cable support and bend radius. Acceptance is contingent upon successful Optical Loss Testing, OTDR testing, continuity testing, and polarity verification, as well as the submission of a complete closeout package with as-built documentation. Bidders must hold a valid North Carolina General Contractor license and maintain all necessary Builder's Risk and Liability insurance. Proposals must be submitted via email to Rachelle Judkins by September 30, 2026, and must include a completed Mandatory Bid Document. Payment will be issued as a single lump sum upon project completion, provided all required purchasing documentation is submitted.
Covenant Learning Solutions operator of Kittrell Job Corps Center

POSTED

about 4 hours ago

DEADLINE

in 17 days
NAICS: 237130
New
SLED
Wood Pole Inspection, Joint Use Inventory & NJUNS Coordination Services
Solicitation # RFP26-27
The City of Winter Park Electric Utility is soliciting proposals for wood pole inspection, condition assessment, joint-use attachment inventory, and NJUNS coordination services for approximately 3,500 utility poles. The primary objective is to enhance system reliability and asset management through the use of non-destructive evaluation techniques, specifically ultrasonic or equivalent technologies, to identify internal decay and structural deterioration. Beyond inspections, the selected contractor will be responsible for providing physical stabilization and bracing for deficient poles, documenting third-party attachments, and managing NJUNS tickets for poles where electric facilities have been removed. The procurement process follows a two-phase evaluation: an initial scoring of proposals based on price, delivery approach, experience, personnel, and professional contacts, followed by oral presentations for shortlisted firms. Compliance requirements are extensive, including adherence to the Build America, Buy America Act, Davis-Bacon Act labor standards, ADA and WCAG 2.0 AA accessibility standards, and Florida's Public Records Law. Proposals must be submitted electronically via the City's procurement portal by October 13, 2026, at 10:00 am. Payment is governed by the Florida Local Government Prompt Payment Act with standard net 30 terms, and the City prefers payment via a VISA platform.
Electric Utility

POSTED

1 day ago

DEADLINE

in about 1 month
NAICS: 237130
New
Federal
Power Construction and Services II (PCS II) MATOC
Solicitation # W912BU26RA032
The US Army Corps of Engineers, Philadelphia District, is soliciting proposals for the Power Construction and Services II (PCS II) Multiple Award Task Order Contract (MATOC). This firm-fixed-price IDIQ contract aims to establish a pool of three to seven contractors to provide power construction and services in contingency or austere environments. The scope of work covers the United States Central Command (CENTCOM) Area of Responsibility and select European Command (EUCOM) countries, including Ukraine, Poland, Romania, Bulgaria, Kosovo, Bosnia, Norway, Turkey, Slovakia, and Greenland. The total shared contract capacity is 249,000,000 dollars, with a primary period of performance from June 7, 2027, to June 6, 2032. The contract encompasses single-source responsibility for the construction of low, medium, and high voltage electrical systems, as well as the operation and maintenance of power plants and distribution systems. Key requirements include the ability to provide personnel and equipment for preventive, scheduled, and emergency maintenance, as well as fueling operations for diesel generator sets. Award decisions will be based on a best-value tradeoff process, evaluating technical approach and past performance, with the combined non-priced factors being approximately equal in importance to price. Proposals must be submitted electronically via the PIEE Solicitation Module by October 13, 2026.
W2SD Endist Philadelphia

POSTED

1 day ago

DEADLINE

in about 1 month
NAICS: 237130
New
Federal
CJAG Underground Utilities Construction
Solicitation # W9136426QA076
Solicitation W91364-26-Q-A076 is a 100% small business set-aside for the construction of underground utilities at the Load Line 6 area of Camp James A. Garfield Joint Training Center in Ravenna, Ohio. The project, valued between $500,000 and $1,000,000, involves the installation of approximately 9,900 linear feet of open-cut trenching, 60 linear feet of dual-wall fuel lines with four termination points, and 500 linear feet of grounding rods. The scope also includes electrical and communications conduit routes, pull boxes, concrete-encased roadway crossings, backfill, compaction, and stone-road restoration. The work must be completed within 60 days following the issuance of the notice to proceed. The government will award a firm-fixed-price purchase order based on a best-value determination, evaluating technical acceptability, relevant past performance in medium-voltage electrical systems or similar infrastructure, and price reasonableness. Bidders must provide a bid guarantee with their offer, and performance and payment bonds are required no later than 10 days after receipt of the order. Quotations are due by September 24, 2026, at 10:00 AM EDT and must be submitted electronically to Barry Beale. Required submission materials include a detailed price quotation, a project schedule, key personnel qualifications, and documentation of all necessary licenses and permits.
W7NU Uspfo Activity Oh Arng

POSTED

1 day ago

DEADLINE

in 12 days

General Info

Agency

Department Of Defense → FA5682 31 Cons (unit 6102)

NAICS

237130 - Power and Communication Line and Related Structures ConstructionView NAICS

Place of Performance

Campia Turzii, RO-CJ, 405100, ROU

Set-Aside

NONE

Documents

(2)

Village+Power+Communication+Line+ReRouting+SOW.docx

DOCX

Village+Power+Communication+Line+ReRouting+SOW+V2.docx

DOCX

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

1 update
PhaseClosed
Posted

Sources Sought

Amendment 1

Contract was updated

Response Deadline

Deadline has passed

Submission Closed

Find active opportunities like this

Start your free trial to discover similar active contracts, track opportunities, and build proposals with AI assistance.

Organization & Contact Information

Show more
AgencyDepartment Of Defense → FA5682 31 Cons (unit 6102)
Contacts2 people available
OfficeAPO, AE, 09604-6102, USA
Organization / Agency
Department Of Defense → FA5682 31 Cons (unit 6102)
Office AddressAPO, AE, 09604-6102, USA
Contacts

Full Description

Show more

Performance Work Statement: Village Power Communication Line Re‑Routing


1.0 Purpose and Background


The Village’s existing power and communication distribution network is currently routed above ground on a concrete pad using exposed cable trays. This configuration increases vulnerability to weather, physical damage, and operational disruptions. The purpose of this project is to relocate and reorganize the electrical and communication infrastructure into an underground conduit system to improve reliability, safety, and long‑term maintainability while enabling future expansion.



2.0 Scope of Work


The Contractor shall provide all labor, materials, equipment, and supervision required to install four, Ø110 mm underground PVC conduits for the Village’s power and communication lines, rerouting them from the existing concrete pad cable tray system into a new underground conduit network. Work includes:


  • Excavate a trench 14 meters in length with a finished depth of 80–90 cm and a minimum finished width of 45 cm, in full compliance with IEC 60364‑5‑52 and applicable Romanian underground cable installation standards.
  • Installing four, appropriately sized, Ø110 mm underground PVC conduits, for the Village’s power and communication lines conduits for electrical and communication lines.
  • Ensuring all conduits are left empty, capped at both ends, and not filled, sealed, or obstructed with foam or any other material.
  • All work must comply with NEC, IEEE, local utility standards, and site‑specific requirements.
  • Carry out compaction testing, depth verification, and documentation to demonstrate compliance.
  • Provide daily update emails on the progress of work detailing what had been accomplished that day




3.0 Requirements


    1. Excavation of Future Underground Conduit Locations

The contractor shall excavate a trench 14 meters in length with a finished depth of 90 cm and a minimum finished width of 75 cm, in full compliance with IEC 60364‑5‑52 and applicable Romanian underground cable installation standards.


3.1.1 Removal and disposal of previous conduit lines.


The contractor shall remove leftover conduit lines and dispose of any plastics or PVC from previous works.


3.2 Installation of Conduit lines


The contractor shall:


  • Provide a 10 cm 0/4mm clean masonry sand bedding layer at the bottom of the trench prior to conduit installation.
  • Use underground‑rated conduits, materials, and accessories suitable for permanent subsurface installation.
  • Install four (4) Ø110 mm PVC conduits along the full trench length in a 1×4 configuration, maintaining a minimum spacing of 5-7.5 cm between conduits horizontally and vertically, and ensure each conduit terminates 92 cm above finished ground level with a clean 90‑degree sweep, are properly capped, and remain free of obstructions. The use of foam, sealant, or any filler inside spare conduits is strictly prohibited.
  • Provide a draw-string in each conduit to facilitate future cable installation.
  • Maintain all required horizontal and vertical clearances from existing utilities. The Contractor is solely responsible for utility locating, verification, and avoidance.
    1. Trench Backfilling

The contractor shall:


  • After conduit placement, backfill with 21 cm of 0/4mm clean masonry sand to cover the exposed conduits. This will lead to a total sand layer of 31 cm due to the bedding layer and additional backfill.
  • Install warning tape 30cm above conduit crown.
  • After sand layer, the trench will be backfilled with 37mm of 0/32mm well-graded crushed aggregate.
    1. Concrete Capping

The contractor shall:


  • Restore the surface with a 22 cm concrete slab matching the adjacent concrete thickness, strength, finish and appearance.
  • The repaired section will be flush with surrounding surfaces with no visible differential in texture, color, or elevation.
    1. Additional Requirements

The contractor must:


  • Implement all necessary site protection, erosion control, and restoration measures throughout the work.
    • This includes wearing protective helmets, gloves, knee pads, and respiratory masks to protect from cuts, inhaling concrete dust, and any other potential bodily injury
  • Maintain daily progress logs and submit daily work reports in PDF format to the Contracting Officer and the Project Manager.
  • Clean any the surriounding area of leftover materials, dust, and debris.
  • Fill hole located by the designated red circle on figure 2. This should be done manually with shovels and at the end of the project to ensure there is no damage done to the concrete foundation and the structures surrounding it.
  • Execute work from 9AM to 5PM.
  • Not pour concrete when storms are suspected during the curing time of the concrete.



4.0 Deliverables


The Contractor shall deliver:


• Underground routing plan and construction drawings.


• Material submittals and technical data sheets.


• As‑built drawings showing conduit paths, depths, and cable identification.



5.0 Period of Performance


The period of performance is 14 working days from Notice to Proceed (NTP). A detailed schedule with milestones shall be submitted within 10 days upon award.





6.0 Place of Performance


All work will occur within the Village boundaries at the existing concrete pad cable tray locations and along the approved underground routing corridors.



7.0 USG & RoAF Assistance


The U.S. Government and Romanian Air Force may provide:


• Access to controlled areas and work zones.


• Coordination with local authorities and utility providers.


• Review and approval of submittals and design documents.


• Oversight and quality assurance inspections.


• No tools, materials, or labor will be provided by RoAF or USAF unless specifically stated.



8.0 Contractor‑Furnished Equipment/Information


The Contractor shall provide:


• All tools, equipment, vehicles, and machinery required for trenching and conduit installation.


• All conduits.


• PPE for all personnel.


• Surveying and testing equipment.


• Waste disposal and site restoration materials.



9.0 Acceptance Criteria


Work will be accepted when:


• All installations meet NEC, IEEE, and project specifications.


• Conduits are verified to contain draw strings and to be capped and unobstructed.


• As‑built documentation is complete and accurate.


• The site is restored to its original or improved condition.


• All deficiencies identified during inspections are corrected.


• A final inspection must be completed and documented prior to project closeout.



10.0 Security Requirements


The Contractor shall:


• Comply with all USG and RoAF security protocols. Base access requests must be submitted at least 7 days in advance.


• Ensure personnel have proper identification and authorization.


• Protect sensitive infrastructure information.


• Follow controlled‑area procedures where applicable.



11.0 Safety


The Contractor shall implement a comprehensive safety plan that includes:


• OSHA‑compliant work practices.


• Daily safety briefings and hazard assessments.


• Proper trenching and shoring.


• Immediate reporting of accidents or near‑miss incidents.



12.0 Warranty


The Contractor shall provide a minimum 12‑month warranty on all workmanship and installed materials, starting from the date of final acceptance. All defects identified during the warranty period shall be corrected at no additional cost.



13.0 Appendix


The Appendix may include:


• Site maps and routing diagrams


• Material specifications


• Safety plan


• Environmental protection plan


• Quality control plan


Find Active Opportunities Like This

Get AI-powered intelligence on the opportunities still open

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 650+ contractors already using CLEATUS