Village Power Communication Line Re-Routing

Closed
FA568226QA003Federal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

Active Opportunities Like This One

NAICS: 237130
New
SLED
Traffic Signal Synchronization Project Along Hamner Ave And Archibald Ave
Solicitation # 26-119CIP
The City of Eastvale, California, is soliciting bids for the Traffic Signal Synchronization Project Along Hamner Avenue and Archibald Avenue under solicitation number 26-119CIP. The project involves the installation of traffic signal controllers, field ethernet switches, fiber optic trunk and breakout cables, and conflict monitor units, as well as the implementation of hybrid detection systems. The scope includes significant infrastructure work such as installing PVC conduits, pull boxes, and performing pavement restoration. All work must be completed within 50 working days from the commencement date and must adhere to the standards of the County of Riverside, Caltrans, and the Americans with Disabilities Act. The contract will be awarded to the apparent low bidder based on the total bid price, including the base bid and specific alternates. To be eligible, the prime contractor must hold a current California Class A General Engineering Contractor license. Required submission documents include a signed bid form, bid security, a statement of qualifications, and a non-collusion declaration, all submitted via the PlanetBids portal. The selected contractor will be required to provide construction performance, labor and material payment, and warranty bonds. Payment will be administered on a lump sum basis according to an approved schedule of values, with final payment contingent upon the submission of project record drawings and the execution of a release of claims.
City of Eastvale

POSTED

about 15 hours ago

DEADLINE

in 16 days
NAICS: 237130
New
Federal
CSSC Utility Feed Transformer Replacement
Solicitation # W912P627SSA001
The U.S. Army Corps of Engineers, Chicago District, is conducting market research via Sources Sought Notice W912P627SSA001 to identify qualified small business contractors for the turnkey removal and replacement of two utility feed transformers at the Chicago Sanitary and Ship Canal Fish Dispersal Barrier facility in Lockport, Illinois. The project involves the removal and disposal of two existing 4,000/5,000 kVA transformers and the installation, testing, and commissioning of two new operational replacements. The contractor will be responsible for all labor, materials, equipment, rigging, and supervision, while existing concrete pads, cabling, and switchgear will be reused. The estimated magnitude of construction is between 500,000 and 1,000,000 dollars, with an estimated project schedule of 365 calendar days. Interested firms must demonstrate technical capabilities in medium-voltage electrical work, including pre-energization electrical acceptance testing in accordance with NETA ATS and IEEE C57 standards. Key requirements include the ability to supply biobased dielectric insulating fluid and steel enclosures with recovered materials, as well as strict adherence to USACE EM 385-1-1 and NFPA 70E safety standards. Applicants must provide their small business status under NAICS code 237130, proof of bonding capacity, and up to three relevant project examples from the last five years. Responses, which should not include price quotes, are due by November 5, 2026, and must be submitted using the provided response template.
W072 Endist Chicago

POSTED

about 19 hours ago

DEADLINE

in 9 days
NAICS: 237130
New
SLED
2026-28 Electric Infrastructure Reconducts
Solicitation # 2026-28
The City of Covington, Georgia, is soliciting proposals under RFP #2026-28 for the reconduct of three-phase overhead utility lines across three separate projects. The scope of work includes Project 1 at Cornish Creek Newtonsboro Road, Project 2 at Elm and Reynold Streets, and Project 3 involving Eagle and Goldar General locations. The selected contractor will provide all labor, equipment, and coordination for the installation of poles, crossarms, conductors, and hardware, while the City will supply all materials. All work must be completed by May 31, 2027, and must adhere to first-quality workmanship and standard utility practices. Proposals must be submitted in sealed envelopes, including one USB drive copy, to the Covington Utility Complex by 10:00am on November 24, 2026. A mandatory pre-proposal meeting is scheduled for November 9, 2026. Submission requirements include a 5% bid bond, a non-collusion affidavit, and verification of compliance with the Illegal Immigration Reform and Enforcement Act of 2011. The awarded contractor must provide payment and performance bonds for 100% of the contract amount within ten days of notification and maintain comprehensive general liability, automobile liability, and worker's compensation insurance with limits of at least $1,000,000. Evaluation will be based on experience, personnel certifications, project approach, cost reasonableness, safety records, and references.
City of Covington

POSTED

1 day ago

DEADLINE

in 27 days
NAICS: 237130
New
SLED
Solar Streetlight Project – Phase 3
Solicitation # 8385
The Solar Streetlight Project – Phase 3 (C.I.P. No. 8385) is a solicitation by the City of Vista, California, for the receiving, storing, transporting, and installation of 125 solar streetlights. The scope of work includes the installation of galvanized steel and concrete light poles, solar modules, power centers, batteries, and luminaires. Comprehensive tasks involve excavation, concrete placement, pole erection, and the repair of any work-related damage to sidewalks, curbs, and utilities. The contractor is responsible for all labor, materials, and equipment, including hoisting and rental gear, traffic and parking control, public notifications, and the implementation of erosion and stormwater protection measures. All work must adhere to ADA standards for curb ramps and sidewalks and be performed during specified working hours, with lane closures restricted to 8:30 AM to 3:30 PM, Monday through Friday. The contract will be awarded to the lowest responsible bidder based on the total amount of Base Bid Items. To be eligible, bidders must possess the required licensure, provide proof of DIR registration per Section 1725.5 of the California Labor Code, and submit bids electronically via the OpenGov Procurement portal by November 25, 2026. Local business entities, as well as certified veteran-owned or disabled veteran business enterprises, may be eligible for specific preferences. Awarded contractors must provide performance and payment bonds, as well as workers' compensation insurance, within ten working days of the Notice of Intent to Award. Payment is processed via progress payments within 30 calendar days of receipt of a valid invoice, contingent upon the submission of certified payroll records and lien releases. Construction must commence within ten working days of the Notice to Proceed, with punchlist items to be completed within twenty working days of issuance.
City of Vista

POSTED

1 day ago

DEADLINE

in 29 days
NAICS: 237130
New
SLED
ON-CALL FIBER OPTIC INSTALLATION, FUSION SPLICING, TERMINATION, TESTING AND RELATED SERVICES
Solicitation # 26-032
The City of Carson is soliciting proposals under RFP #26-032 for qualified telecommunications firms to provide on-call fiber optic installation, fusion splicing, termination, testing, and related services for its municipal fiber optic network. The scope includes working on both new and existing infrastructure, with specific requirements for pulling cable and performing industry-standard testing, including power meter and bi-directional OTDR (1310/1550 nm). The City may award a single or multiple contracts with an anticipated term of five years. Performance standards are strict, requiring emergency onsite arrival within two hours and the start of splice work within four hours, while all test results and documentation must be submitted within two business days of assignment completion. Proposals must be submitted electronically via PlanetBids by November 12, 2026, at 2:00 PM PT. The evaluation process consists of a mandatory written proposal review, followed by optional interviews for high-ranking firms, with the award based on the best overall value in accordance with Carson Municipal Code. Selected contractors must adhere to a minimum local hiring requirement of 30 percent for employees and subcontractors. Financial security requirements include performance and payment bonds totaling 100 percent of the total compensation. Additionally, contractors must provide a detailed safety plan for any trench excavations five feet or deeper on projects exceeding 25,000 dollars and comply with all prevailing wage and insurance requirements.
City of Carson

POSTED

2 days ago

DEADLINE

in 16 days

General Info

Agency

Department Of Defense → FA5682 31 Cons (unit 6102)

NAICS

237130 - Power and Communication Line and Related Structures Construction

Place of Performance

Campia Turzii, RO-CJ, 405100, ROU

Set-Aside

NONE

Documents

2

Village+Power+Communication+Line+ReRouting+SOW.docx

DOCX

Village+Power+Communication+Line+ReRouting+SOW+V2.docx

DOCX

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

1 update
PhaseClosed
Posted

Sources Sought

Notice updated

The notice description changed.

Response Deadline

Deadline has passed

Submission Closed

Find active opportunities like this

Start your free trial to discover similar active contracts, track opportunities, and build proposals with AI assistance.

Organization & Contact Information

Show more
AgencyDepartment Of Defense → FA5682 31 Cons (unit 6102)
Contacts2 people available
OfficeAPO, AE, 09604-6102, USA
Organization / Agency
Department Of Defense → FA5682 31 Cons (unit 6102)
Office AddressAPO, AE, 09604-6102, USA
Contacts

Full Description

Show more

Performance Work Statement: Village Power Communication Line Re‑Routing


1.0 Purpose and Background


The Village’s existing power and communication distribution network is currently routed above ground on a concrete pad using exposed cable trays. This configuration increases vulnerability to weather, physical damage, and operational disruptions. The purpose of this project is to relocate and reorganize the electrical and communication infrastructure into an underground conduit system to improve reliability, safety, and long‑term maintainability while enabling future expansion.



2.0 Scope of Work


The Contractor shall provide all labor, materials, equipment, and supervision required to install four, Ø110 mm underground PVC conduits for the Village’s power and communication lines, rerouting them from the existing concrete pad cable tray system into a new underground conduit network. Work includes:


  • Excavate a trench 14 meters in length with a finished depth of 80–90 cm and a minimum finished width of 45 cm, in full compliance with IEC 60364‑5‑52 and applicable Romanian underground cable installation standards.
  • Installing four, appropriately sized, Ø110 mm underground PVC conduits, for the Village’s power and communication lines conduits for electrical and communication lines.
  • Ensuring all conduits are left empty, capped at both ends, and not filled, sealed, or obstructed with foam or any other material.
  • All work must comply with NEC, IEEE, local utility standards, and site‑specific requirements.
  • Carry out compaction testing, depth verification, and documentation to demonstrate compliance.
  • Provide daily update emails on the progress of work detailing what had been accomplished that day




3.0 Requirements


    1. Excavation of Future Underground Conduit Locations

The contractor shall excavate a trench 14 meters in length with a finished depth of 90 cm and a minimum finished width of 75 cm, in full compliance with IEC 60364‑5‑52 and applicable Romanian underground cable installation standards.


3.1.1 Removal and disposal of previous conduit lines.


The contractor shall remove leftover conduit lines and dispose of any plastics or PVC from previous works.


3.2 Installation of Conduit lines


The contractor shall:


  • Provide a 10 cm 0/4mm clean masonry sand bedding layer at the bottom of the trench prior to conduit installation.
  • Use underground‑rated conduits, materials, and accessories suitable for permanent subsurface installation.
  • Install four (4) Ø110 mm PVC conduits along the full trench length in a 1×4 configuration, maintaining a minimum spacing of 5-7.5 cm between conduits horizontally and vertically, and ensure each conduit terminates 92 cm above finished ground level with a clean 90‑degree sweep, are properly capped, and remain free of obstructions. The use of foam, sealant, or any filler inside spare conduits is strictly prohibited.
  • Provide a draw-string in each conduit to facilitate future cable installation.
  • Maintain all required horizontal and vertical clearances from existing utilities. The Contractor is solely responsible for utility locating, verification, and avoidance.
    1. Trench Backfilling

The contractor shall:


  • After conduit placement, backfill with 21 cm of 0/4mm clean masonry sand to cover the exposed conduits. This will lead to a total sand layer of 31 cm due to the bedding layer and additional backfill.
  • Install warning tape 30cm above conduit crown.
  • After sand layer, the trench will be backfilled with 37mm of 0/32mm well-graded crushed aggregate.
    1. Concrete Capping

The contractor shall:


  • Restore the surface with a 22 cm concrete slab matching the adjacent concrete thickness, strength, finish and appearance.
  • The repaired section will be flush with surrounding surfaces with no visible differential in texture, color, or elevation.
    1. Additional Requirements

The contractor must:


  • Implement all necessary site protection, erosion control, and restoration measures throughout the work.
    • This includes wearing protective helmets, gloves, knee pads, and respiratory masks to protect from cuts, inhaling concrete dust, and any other potential bodily injury
  • Maintain daily progress logs and submit daily work reports in PDF format to the Contracting Officer and the Project Manager.
  • Clean any the surriounding area of leftover materials, dust, and debris.
  • Fill hole located by the designated red circle on figure 2. This should be done manually with shovels and at the end of the project to ensure there is no damage done to the concrete foundation and the structures surrounding it.
  • Execute work from 9AM to 5PM.
  • Not pour concrete when storms are suspected during the curing time of the concrete.



4.0 Deliverables


The Contractor shall deliver:


• Underground routing plan and construction drawings.


• Material submittals and technical data sheets.


• As‑built drawings showing conduit paths, depths, and cable identification.



5.0 Period of Performance


The period of performance is 14 working days from Notice to Proceed (NTP). A detailed schedule with milestones shall be submitted within 10 days upon award.





6.0 Place of Performance


All work will occur within the Village boundaries at the existing concrete pad cable tray locations and along the approved underground routing corridors.



7.0 USG & RoAF Assistance


The U.S. Government and Romanian Air Force may provide:


• Access to controlled areas and work zones.


• Coordination with local authorities and utility providers.


• Review and approval of submittals and design documents.


• Oversight and quality assurance inspections.


• No tools, materials, or labor will be provided by RoAF or USAF unless specifically stated.



8.0 Contractor‑Furnished Equipment/Information


The Contractor shall provide:


• All tools, equipment, vehicles, and machinery required for trenching and conduit installation.


• All conduits.


• PPE for all personnel.


• Surveying and testing equipment.


• Waste disposal and site restoration materials.



9.0 Acceptance Criteria


Work will be accepted when:


• All installations meet NEC, IEEE, and project specifications.


• Conduits are verified to contain draw strings and to be capped and unobstructed.


• As‑built documentation is complete and accurate.


• The site is restored to its original or improved condition.


• All deficiencies identified during inspections are corrected.


• A final inspection must be completed and documented prior to project closeout.



10.0 Security Requirements


The Contractor shall:


• Comply with all USG and RoAF security protocols. Base access requests must be submitted at least 7 days in advance.


• Ensure personnel have proper identification and authorization.


• Protect sensitive infrastructure information.


• Follow controlled‑area procedures where applicable.



11.0 Safety


The Contractor shall implement a comprehensive safety plan that includes:


• OSHA‑compliant work practices.


• Daily safety briefings and hazard assessments.


• Proper trenching and shoring.


• Immediate reporting of accidents or near‑miss incidents.



12.0 Warranty


The Contractor shall provide a minimum 12‑month warranty on all workmanship and installed materials, starting from the date of final acceptance. All defects identified during the warranty period shall be corrected at no additional cost.



13.0 Appendix


The Appendix may include:


• Site maps and routing diagrams


• Material specifications


• Safety plan


• Environmental protection plan


• Quality control plan


Earlier notices in this NAICS code

Posted before this notice, open and closed

Find Active Opportunities Like This

Get AI-powered intelligence on the opportunities still open

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS