Replace Switch and Repair Underground Electrical Near F293; Vance AFB, OK
Contract Overview
Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.
AI Contract Overview
ASRC Federal Gulf State Constructors, LLC, acting as the prime contractor for the government, is seeking quotes for a firm-fixed-price contract to replace a medium-voltage pad-mounted switch and perform related electrical repairs near Facility 293 at Vance Air Force Base, Enid, Oklahoma. The project scope includes installing a 15kV class pad-mounted switch, sectionalizing cabinets, constructing approximately 1300 linear feet of duct bank, laying medium-voltage cable, tie-ins to existing infrastructure, terminations, directional drilling, and all incidental work in accordance with provided drawings and a detailed Statement of Work. This solicitation is being conducted in accordance with FAR Subpart 12.6, and no separate written solicitation will be issued. Quotes must be submitted using the attached bid form by June 30, 2026, at 11:00 AM CST, and remain valid for 180 days after the solicitation closing date to ensure funding and procurement continuity. Funding for this project is not currently available, and the government reserves the right to cancel the solicitation at any time without obligation to reimburse offerors. Offerors are strongly encouraged to attend a non-mandatory site visit scheduled for June 9, 2026, where specific arrival and identification protocols, including REAL ID-compliant licenses or passports, must be followed. All vendor questions must be submitted via an attached Q&A form by June 22, 2026, and vendors must be actively registered in the System for Award Management (SAM) to be considered. The solicitation package includes the Statement of Work, drawings, bid form, Q&A form, and applicable wage determination, all of which must be used to prepare and submit responsive quotes.
General Info
Agency
NAICS
Place of Performance
Enid, OK, 73705, USASet-Aside
Timeline
Response Deadline
Organization & Contact Information
Full Description
Amendment #1: Sign In Sheet;
The purpose of amendment #1, to attached the list of attendees for the site visit.
This is a combined synopsis/solicitation for commercial items prepared in acordance with the format in FAR Subpart 12.6 and supplemented with additional information included in this notice. This announcement constitutes the only solicitation; quotes are being requested and a written solicitation will not be issued.
It is the sole responsibility of all offerors to frequently check this posting on SAM.gov for any amendments, updated attachments, or changes to this solicitation. Failure to acknowledge and comply with posted amendments may result in a quote being deemed non-responsive.
ASRC Federal Gulf State Contructors, LLC (Prime Contractor) for the Government intends to award a Firm-Fixed-Price contract to replace the medium-voltage pad-mounted switch near Facility 293 at Vance Air Force Base, Enid OK. The work included installation of one 15kV class pad-mounted switch, installation of pad-mounted sectionalizing cabinets, construction of duct bank (approx. 1300 LF), installation of medium-voltage cable, tie-ins to existing infrastructure, terminations, directional drilling, and all incidental work in accordance with the project drawings and specifications. All requirements for this project are listed in the attached Statement of Work (SOW).
Funding Notice:
In accordance with FAR 52.232-18, Availability of Funds, funds are not presently available for this requirement. No award will be made until funds are available. AFGSC and/or the Government reserves the right to cancel this solicitation, either before or after the closing date for receipt of proposals. In the event AFGSC or Government cancels this solicitation, AFGSC nor the Government has no obligation to reimburse any offeror for any costs.
Quote Validity:
Quotes must remain valid for 180 days after the solicitation close date of June 30, 2026. This extended timeframe will provide the government with the strongest opportunity to secure the necessary funding and ensure continuity in the procurement process.
Offers providing less that 180 calendar days for solicitation will not be considered or accepted.
Bid Requirements:
A bid form is attached and will need to be completed and emailed to Betty Kliewer; betty.kliewer.ctr@us.af.mil no later than June 30, 2026 at 11:00 AM CST. No offers will be considered or excepted after the dead line.
Site Visit and Arrival Instructions:
A site visit is scheduled for June 9, 2026 at 10:00 AM CST. Offerors are strongly encouraged to attend but not mandatory, a list of attendees is recommened at least 48 hours prior to visit and email to:
Betty Kliewer; betty.kliewer.ctr and Shannon Perry; shannon.perry.1.ctr@us.af.mil.
All attendees must report to the Visitor Center, Building F72, which is the first building on the right after entering through the first gate thirty minitues prior to be sponsored on.
A base-provided bus will be provided to transport all visitors to the project site and riding the bus is encouraged.
If you choose not to ride the bus, you must provide • Current vehicle registration, and • Current vehicle insurance.
Identification Requirements
You MUST have one of the following forms of ID:
• REAL ID-compliant driver's license
• U.S. Passort
Non-U.S. citizens MUST bring: Passport, and visa, work permit, or I-94 documentation.
Failure to provide proper identification will result in denial of base access.
All attendees must comply with all Vance AFB rules and regulations while on base.
Questions and Answer Requirements:
A Question and Answer (Q&A) Form is attached to this solicitation, All vendor questions must be submitted using the form only. Questions submitted in any other format will not be accepted.
Completed Q&A forms must be emailed to: Betty Kliewer - betty.kliewer.ctr@us.af.mil
The deadline for submitting questions is June 22, 2026 at the close of business.
All vendors must be registered and active in the System for Award Management (SAM) at the time of quote submission. Quotes submitted by vendors who are not active in SAM cannot be considered for award.
ATTACHMENTS:
The following documents are attached to this solicitation and must be used when preparing your quote.
Statement of Work - Provides the detailed scope, technical requirements, and project specifications for XTLF26-1019.
Drawings
Bid Form - All vendors must submit pricing using the provided bid form.
Question & Answer Form - Vendors must use this form to submit any questions.
Wage Determination - Applicable U.S. Department of Labor wage determination for this project.