24344488, Crane Rail & Structural Column #J-13, B873, PSNS

Forecast
Federal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

This project involves the repair and structural support of crane rail and structural column J-13 within Building 873 at PSNS, managed by Navfac Northwest. The facility, a reinforced concrete structure built in 1977, currently faces critical access issues regarding chemical tubs on the North and West sides. Failure to restore full bridge crane access threatens the electroplating capabilities of S31 and S71, which could force operations to other installations and cause significant delays in the undocking schedules of multiple submarines and a carrier. The project is categorized as a CAT-2 / DBB-AE deliverable with design scheduled for the first quarter of fiscal year 2025 and construction slated for the first quarter of fiscal year 2026. Technical challenges include the building's original construction using working stress design rather than modern limit states methodology. The work is prioritized due to its direct impact on mission support and has received high-level attention to ensure the continued operational readiness of naval assets.

General Info

Repair crane rail and column J-13 at PSNS Building 873 to maintain operations.

NAICS

238120 - Structural Steel and Precast Concrete Contractors

Place of Performance

NW: BREM PDC, USA

Set-Aside

NONE

Documents

0

No documents available

Documents will appear here when they are available.

AI Contract Breakdown

Uniform Contract Format

No documents to break down

The breakdown needs solicitation documents. None were found from this contract's source.

Ask CLEATUS

I've read this contract. Ask me anything.

Timeline

PhaseForecast
Posted

forecast

Prepare for this forecast

Research the agency, track this forecast, and prepare your capture plan before the solicitation opens.

Organization & Contact Information

Show more
AgencyDepartment Of The Navy → Navfac Northwest
ContactsNo contacts available
OfficeN/A
Office AddressN/A
ContactsNo contact information available

Full Description

Show more
*DELIVERABLE: CAT-2 / DBB-AE * Design FY25/Q1 * Construction FY26/Q1 *MND: 8-1-2024 *Justification Statement: The inability to access the chemical tubs on the North and West side of B873 will affect S31 and S71's electroplating ability to support the mission. If the mobile cranes currently being used temporarily are unable to support, this will force the electroplating operations out to other installations, causing major delays that could impact the ships abilities to undock on time. Full bridge crane access to the chemical tubs will be critical to the avails of multiple submarines and a carrier. This has the attention of CAPT Crinklaw due to the mission support impacts. BACKGROUND: Building 873, completed in 1977, is a reinforced concrete structure composed of pre-cast tilt-up-panels, bearing wall perimeter and an interior of cast-in-place reinforced concrete columns. Structural steel is used in crane rails and crane support columns as well as structural mezzanines and floor grating support. The roof system is composed of pre-cast, pre-stressed structural tees, resting on a poured concrete ridge beam with poured concrete infill between the tees. Concrete design methodology at the time of construction was working stress design as opposed to the limit states methodology currently in use. Building 873, previously held the designation, Metal Fabrication Facility P/432. The construction of P/432 required the demolition of Building 145 and Building 538 on the site. The primarily level site did not contain utilities that were abandoned in place in the area adjacent to or near to column J-13. The grading plan indicates that the subject column and adjacent slab were not placed in an area of substantial fill. Column J-13 bears the load of approximately 25% of th ... NOTE: description has been truncated, please see Project Note for full description.

Similar Contracts

Same NAICS industry code

NAICS: 238120
New
SLED
McIntosh Power Plant Security Barrier Wall
Solicitation # 2026-RFP-138
The City of Lakeland is seeking a qualified contractor for solicitation 2026-RFP-138 to install a precast concrete security barrier wall approximately 3,916 feet long at the McIntosh Power Plant located at 3030 E. Lake Parker Drive, Lakeland, Florida. The wall must be 10 feet high with columns generally spaced 20 feet apart, hurricane rated for the local wind zone, and feature visually appealing finishes on both faces. The contractor is responsible for providing all engineering, drawings, color renderings, permits, materials, equipment, labor, and supervision. Work must begin within 30 days of the Purchase Order issuance and be completed within 90 days of the first ground break. Proposals are evaluated on a total score basis of 100 points, focusing on the quality of the closure construction plan, pricing, safety performance records (expecting a 5-year average TRIR of 1.0 or less), reference strength, and team qualifications. Bidders must provide a total firm fixed price and a bid bond or certified check of at least 5% of the price. Required documentation includes a State Certified License (CGC or CBC), IRS Form W-9, Sunbiz registration, and a signed Hold Harmless agreement. Payment is based on a schedule of values and a Critical Path Method schedule, subject to a 10% retainage. There is no specified set-aside status for this solicitation.
LE - Engineering

POSTED

4 days ago

DEADLINE

in about 1 month
View Details

More opportunities from Department Of The Navy → Navfac Northwest

Same awarding agency

NAICS: 236220
Federal
MSR #23207821_1787796 -- (23207821) Repair Crane Track and Tunnel Arch Support DD1, PSNSThis project involves comprehensive seismic upgrades to the superstructure and substructure of a facility managed by Navfac Northwest, specifically focusing on the repair of crane tracks and tunnel arch support. The scope of work includes retrofitting building brace connections, modifying restrooms for American Barrier Act compliance, and updating heating and ventilation systems. Additionally, the project requires the removal and reinstallation of various architectural, electrical, and mechanical interferences, including plant equipment, shop tools, and storage racks. Electrical upgrades will be implemented to install a 480VAC three-phase grounded system and correct documented HDA safety hazard deficiencies across RAC 2, 3, and 4 categories. All work must comply with the Unified Facility Code, National Fire Protection Association, and International Building Code, while prioritizing energy efficiency and low life cycle costs. Because the machine shop is on the historical register, all modifications require review and concurrence from the State Historical Preservation Office to maintain the building's historical integrity. Station support will be provided through red badge escorts, outage coordination, hazardous material handling assistance, and a facility production process specialist to ensure seamless project execution.
Commercial and Institutional Building Construction

POSTED

5 months ago

DEADLINE

N/A
View Details

Earlier notices in this NAICS code

Posted before this notice, open and closed

Research this forecast and prepare for the solicitation

Every solicitation package arrives shredded into a compliance breakdown and matched to your past performance, with incumbent history and alerts on amendments and award.

Miguel
Hillary
Keith Deutsch
Christine

Join 900+ contractors already using CLEATUS