MSR #22635264_1826806 -- (IH-DB_22635264) PW 6 Drainage Upgrade (Phase 2) (Replace Pump 3), B706, PSNS

Active
Federal

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

AI Contract Overview

Show more

This contract, managed by Navfac Northwest for the Department of the Navy, involves the second phase of the PW 6 Drainage Upgrade at Dry Dock 6, BREMER-706, PSNS. The primary objective is to replace drainage pump 3 and its associated components because the current system has reached the end of its life and is at immediate risk of failure. The scope of work includes installing a new VFD pump and motor, replacing the drainage pump 3 starter with a VFD starter, and replacing valves 9A, 15, 16, 17, 18, as well as the check valve and related piping. Classified under NAICS code 237990 for Other Heavy and Civil Engineering Construction, this project follows the successful completion of Phase 1. The work is to be performed at the NW: BREM PDC location. Key stakeholders for the project are Nick Arsers and Dave Barr.

General Info

Navfac Northwest contract to replace drainage pump 3 and components at Dry Dock 6.

NAICS

237990-Other Heavy and Civil Engineering Construction

Place of Performance

NW: BREM PDC, USA

Set-Aside

NONE

Documents

0

No documents available

Documents will appear here when they are available.

AI Contract Breakdown

Uniform Contract Format

No documents to break down

The breakdown needs solicitation documents. None were found from this contract's source.

Timeline

Posted

forecast

Ready to pursue this opportunity?

Start your free trial to track this contract, build proposals with AI assistance, and manage your pipeline.

Organization & Contact Information

Show more
AgencyDepartment Of The Navy → Navfac Northwest
ContactsNo contacts available
OfficeN/A
Office AddressN/A
ContactsNo contact information available

Full Description

Show more
ELIVERABLE: CAT-2, DB, TO REQUESTED SCHEDULE: LOCATION: Dry Dock 6, BREMER-706, PSNS 1391: Yes REQUIREMENT: Replace drainage pump #3 and associated valves. 1. Replace drainage pump 3 with new VFD pump/motor. 2. Replace valves 9A, check valve and piping. 3. Replace drainage pump 3 starter with VFD starter. 4. Replace valves 15,16,17,18 and check valve. NOTES: Phase 1 of phased project was completed on MSR: 18313104 JUSTIFICATION: System is at end of life and at immediate risk of failure. PROJECT STAKEHOLDERS: Nick Arsers 360-204-2847 Dave Barr 360-6203721

Similar Contracts

Same NAICS industry code

More opportunities from Department Of The Navy → Navfac Northwest

Same awarding agency

NAICS: 236220
Federal
MSR #23207821_1787796 -- (23207821) Repair Crane Track and Tunnel Arch Support DD1, PSNSThis project involves comprehensive seismic upgrades to the superstructure and substructure of a facility managed by Navfac Northwest, specifically focusing on the repair of crane tracks and tunnel arch support. The scope of work includes retrofitting building brace connections, modifying restrooms for American Barrier Act compliance, and updating heating and ventilation systems. Additionally, the project requires the removal and reinstallation of various architectural, electrical, and mechanical interferences, including plant equipment, shop tools, and storage racks. Electrical upgrades will be implemented to install a 480VAC three-phase grounded system and correct documented HDA safety hazard deficiencies across RAC 2, 3, and 4 categories. All work must comply with the Unified Facility Code, National Fire Protection Association, and International Building Code, while prioritizing energy efficiency and low life cycle costs. Because the machine shop is on the historical register, all modifications require review and concurrence from the State Historical Preservation Office to maintain the building's historical integrity. Station support will be provided through red badge escorts, outage coordination, hazardous material handling assistance, and a facility production process specialist to ensure seamless project execution.
Commercial and Institutional Building Construction

POSTED

3 months ago

DEADLINE

N/A
View Details

Ready to Pursue This Opportunity?

Get AI-powered intelligence on this solicitation and the ones like it

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS