PA-2300155 (C) Manure Digester

Awarded
PA-2300155State & Local

Contract Overview

Solicitation details, issuing organization, response deadlines, documents, and interested companies for this government contract opportunity.

Active Opportunities Like This One

NAICS: 237990
New
SLED
Carroll Creek Stream Restoration - CIP# 350007 (MWBE Goals)
Solicitation # IFB-27-11
The City of Frederick is soliciting bids for the Carroll Creek Stream Restoration project (CIP# 350007), located near Old Gas House Pike and Fairview Cemetery in Frederick, Maryland. This comprehensive construction project involves in-stream structure installation, floodplain bench grading, bank stabilization, and extensive planting. Key technical requirements include the installation of reinforced soil lifts, rock sills, and various riparian plantings, with an engineer's estimated project cost of $6,884,784.12. The project is performed on a lump sum and unit price basis and requires strict adherence to Virginia OSHA Standards for excavation and Maryland Department of the Environment guidelines for waterway construction. The bid submission deadline is November 13, 2026, at 3:00 pm, with all responses submitted via the OpenGov Portal. Bidders must meet specific socioeconomic goals, including 31% MBE, 11% WBE, and 2% SDVOSB participation. Required financial securities include a bid bond of 5% of the bid price, followed by 100% performance and materialmen's bonds upon award, and a two-year maintenance bond upon completion. The contract includes a two-year guarantee on all work and stipulates liquidated damages of $500 per calendar day for delays beyond the substantial completion date. Award decisions will be based on the vendor's responsiveness to material requirements and their overall responsibility, including technical capacity and performance record.
Engineering

POSTED

about 1 hour ago

DEADLINE

in 7 days
NAICS: 237990
New
SLED
9801 - Madison LakeWay - SkyLine Improvements
Solicitation # 9801
Contract 9801 for the Madison LakeWay – SkyLine Improvements is a solicitation by the City of Madison for the construction of a half-mile linear parkway along the shoreline of Lake Monona adjacent to John Nolen Drive. The project scope is divided into a Base Bid, covering the installation of north and south pile-supported timber-framed boardwalks, pedestrian-scale lighting, enhanced paths, bicycle amenities, wayfinding signage, and extensive landscaping, and an Alternate Bid Item for the construction of the SkyLine Pier. The project also requires significant traffic control, including the implementation of vehicular and bicycle detours and the installation of curb, gutter, and colored concrete medians. The contract will be awarded to the lowest bidder based on unit prices and a grand total. Bidders must provide a bid bond of at least 5 percent of the bid and comply with strict Small Business Enterprise (SBE) participation goals and reporting requirements. Additionally, contractors must adhere to Best Value Contracting apprenticeship standards and non-discrimination policies. Technical requirements include the use of a Wisconsin-registered Professional Engineer for precast and connection designs, adherence to ADA guidelines for signage, and the provision of site mock-ups for masonry, metal, and wood elements. Construction must commence within seven calendar days of receiving a written notice to proceed.
City of Madison

POSTED

about 2 hours ago

DEADLINE

in about 1 month
NAICS: 237990
New
Federal
Maintenance Dredging of the Isle au Haut Thoroughfare near Isle au Haut, Maine
Solicitation # W912WJ27BA003
Solicitation W912WJ27BA003 is a 100 percent small business set-aside for the maintenance and advance maintenance dredging of the Isle au Haut Thoroughfare Federal Navigation Project in Maine. The project involves mechanically dredging approximately 3,355 cubic yards of highly compacted coarse sand, gravel, cobbles, and small boulders from a 1,200-foot long channel to a depth of -7 feet Mean Lower Low Water, with an additional one-foot allowable overdepth for a maximum depth of -8 feet. All dredged material will be transported and placed at the Flake Island Disposal Site to enhance juvenile lobster and cod habitats. The estimated price range for this effort is between 1,000,000 and 3,000,000 dollars. Performance is strictly governed by an environmental window from September 15, 2026, to March 15, 2027, with all dredging and disposal activities required to be completed by March 1, 2027. The mandatory performance period is 120 calendar days after the receipt of the Notice to Proceed. Award is based on a sealed bidding process under NAICS 237990, requiring performance and payment bonds. Contractors must utilize the Procurement Integrity Enterprise Environment for submissions and adhere to a three-phase quality control process, including preparatory, initial, and follow-up inspections, with all documentation managed via a Construction Management Platform.
W2SD Endist New England

POSTED

about 7 hours ago

DEADLINE

in 4 days
NAICS: 237990
New
Federal
Borough of Millvale, Pennsylvania, Local Protection Project (LPP) PL84-99 Rehabilitation
Solicitation # W911WN27QA004
The Borough of Millvale Local Protection Project (LPP) rehabilitation is a USACE project located along Girty's Run in Millvale Borough, Pennsylvania. The scope of work involves repairing significant flood damage from April 2024, specifically addressing bank erosion, shoaling, ruptured gabion baskets, and washed-out concrete buttresses that currently impede streamflow. The contractor will be responsible for site preparation, including erosion and sediment controls and temporary water diversions, as well as the excavation and removal of debris, replacement of damaged concrete paving and gabions, and the placement of stone-filled gabions between Station 68+00 and Station 73+80. This is a 100% Small Business Set-Aside under NAICS 237990, with an anticipated construction cost between $300,000.00 and $350,000.00. The award will be a single Firm-Fixed-Price purchase order based on best value, evaluating price and past performance. The project must be completed within 365 calendar days of the written Notice to Proceed, with work commencing within 10 days of that notice. Key requirements include the provision of performance and payment bonds at 100% of the contract price, adherence to the Davis-Bacon Act, and the appointment of a Superintendent who cannot also serve as the Site Safety and Health Officer.
W072 Endist Pittsburgh

POSTED

about 7 hours ago

DEADLINE

in about 1 month
NAICS: 237990
New
Federal
Y--Timucuan Ecological and Historic Preserve TIMU-335
Solicitation # 140P2026R0081
Solicitation 140P2026R0081 is a Small Business Set-Aside, Firm-Fixed-Price contract issued by the National Park Service for the stabilization of the Kingsley Plantation shoreline at the Timucuan Ecological and Historic Preserve in Jacksonville, Florida. The project, estimated between $1 million and $5 million, involves repairing and extending a seawall damaged by Hurricane Ian. The scope of work includes selective demolition, the installation of a new weatherable rigid vinyl sheet pile wall with tie rods and deadman walls, the addition of a structural FRP composite sheet pile wall extension to the east, and various civil works such as excavation, limestone riprap installation, and spartina sea grass restoration. The mandatory performance period is 259 calendar days, with work required to begin within 10 days of award. Award selection will be based on the Best Value Continuum Tradeoff Process, where non-price factors—including technical approach, schedule, management approach, safety, project experience, key personnel experience, and past performance—are combined to be significantly more important than price. Due to the sensitive location, the contractor must adhere to strict environmental protection procedures to protect marine mammals, sea turtles, and endangered species, and must comply with the Marine Mammal Protection Act and the Endangered Species Act. Key personnel requirements include a Project Manager, Job Site Superintendent, Quality Control Manager, and Safety Manager. Invoicing is processed electronically through the U.S. Department of the Treasury's Invoice Processing Platform, requiring a signed cover letter from the Contracting Officer's Representative.
Dsc Contracting Services Division

POSTED

about 7 hours ago

DEADLINE

in 7 days

AI Contract Overview

Show more

San Joaquin County has approved Conditional Use Permit PA-2300155 for the construction and operation of a manure anaerobic digester and natural gas processing system located at 23335 E. Dodds Rd. in Escalon, California. The project, designated for renewable energy biomass use, will occupy 10 acres of a 218.19-acre dairy parcel. The scope of work includes the installation of biogas collection systems, solids separation and wastewater recycling components, a new lined and covered pond, an 800 square foot office building, and a 1,404 square foot equipment building. To maintain production targets, the facility will receive solid manure from 10 farms within a 4-mile radius via approximately 17 daily supply trips, while renewable natural gas will be trucked away three times per day. The project was approved by the San Joaquin County Planning Commission on October 16, 2025, following a California Environmental Quality Act review that resulted in a Mitigated Negative Declaration. This determination confirms that the project will not significantly affect the environment, provided that the adopted mitigation and monitoring plans are implemented.

General Info

San Joaquin County approved a manure anaerobic digester and gas system in Escalon.

Place of Performance

Escalon-Bellota Rd., E. Mariposa Rd., Skiff Rd., S. Van Allen Rd., Escalon, CA

Set-Aside

NONE

Documents

0

No documents available

Documents will appear here when they are available.

AI Contract Breakdown

Uniform Contract Format

Sign up to view the full breakdown with detailed analysis of each section.

Timeline

PhaseAwarded
Posted

forecast

Awarded

Contract was awarded

Find active opportunities like this

Get full access to discover similar active contracts, track opportunities, and build proposals with AI assistance.

Organization & Contact Information

Show more
AgencyCalifornia → San Joaquin County
Contacts2 people available
OfficeN/A
Office AddressN/A
Contacts
Alisa GoulartAssociate Planner
Jack N. DeLiddoDeveloper

Full Description

Show more
Conditional Use Permit application to install a manure anaerobic digester and natural gas processing system to capture greenhouse gases. Located on 10 acres of a 218.19-acre dairy parcel, the project includes installation of the components for solids separation and wastewater recycling, installation of the anaerobic digester and biogas collection system, as well as construction of a new lined and covered pond, an 800 square foot office building, and a 1,404 square foot equipment building. To meet the biogas production target, solid manure will be trucked in from 10 farms within a 4-mile radius, generating an estimated 17 daily supply trips. Renewable natural gas (RNG) will be trucked away 3 times per day. (Use Type: Renewable Energy- Biomass)

More opportunities from California → San Joaquin County

Same awarding agency

NAICS: 221117
SLED
PA-2500075 (C)
Solicitation # PA-2500075
Orland Power Solutions, LLC is establishing an anaerobic dairy digester system at the Borges Dairy site located at 8350 E Brady Road, Manteca, California. The project, approved under Conditional Use Permit PA-2500075, involves the construction of two 7,200 square foot above-ground in-vessel anaerobic digesters on a 2-acre footprint within a larger 78.8-acre parcel. The facility is designed to capture methane from cow manure and convert it into renewable natural gas, utilizing a biogas upgrading and cleaning system, an emergency biogas storage bladder, a permit-exempt electric boiler, and auxiliary processing equipment. The project has undergone comprehensive environmental review, resulting in a Mitigated Negative Declaration which concludes that all potentially significant environmental effects can be reduced to less than significant levels through specific mitigation measures. Approval was granted by the San Joaquin County Planning Commission on July 16, 2026, and further certified by the San Joaquin Valley Unified Air Pollution Control District. Compliance requirements include adherence to San Joaquin Valley Air Pollution Control District regulations and participation in the San Joaquin County Multi-Species Habitat Conservation and Open Space Plan for any ground-disturbing activities. Project administration is managed by the San Joaquin County Department of Community Development.
Biomass Electric Power Generation

POSTED

about 2 months ago

DEADLINE

N/A
View Details

Earlier notices in this NAICS code

Posted before this notice, open and closed

Find Active Opportunities Like This

Get AI-powered intelligence on the opportunities still open

Every page of the solicitation package shredded into a compliance breakdown

AI-powered matching based on your capabilities and past performance

Competitor and incumbent history on the requirement

Automated alerts on amendments, Q&A deadlines, and award

Miguel
Hillary
Keith Deutsch
Christine

Join 750+ contractors already using CLEATUS